100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.

Rating
-
Sold
8
Pages
305
Grade
A+
Uploaded on
23-03-2022
Written in
2021/2022

Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.

Show more Read less
Institution
Generals
Module
Generals











Whoops! We can’t load your doc right now. Try again or contact support.

Connected book

Written for

Institution
Generals
Module
Generals

Document information

Uploaded on
March 23, 2022
Number of pages
305
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

TEST BANK FOR INFORMATION
TECHNOLOGY PROJECT
MANAGEMENT,
9TH EDITION, KATHY SCHWALBE

, Chapter 1. Introduction to Project Management


True / False


1. Until the 1980s, project management primarily focused on providing schedule and resource data to top management in
the military, computer, and construction industries. a. True
b. False
ANSWER: True
RATIONALE: Feedback: Until the 1980s, project management primarily focused on providing schedule and
resource data to top management in the military, computer, and construction industries.
Today’s project management involves much more, and people in every industry and every
country manage projects.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.2
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.1 - LO: 1-1
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: Introduction
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



2. A difference between operations and projects is that operations end when their objectives have been reached, whereas
projects do not. a. True
b. False
ANSWER: False
RATIONALE: Feedback: Projects are different from operations in that they end when their objectives have
been reached or the project has been terminated.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.4
QUESTION TYPE: True / False
HAS VARIABLES: False

,LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



3. Every project should have a well-defined objective.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project has a unique purpose. Every project should have a well-defined
objective.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.6
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



4. Projects should be developed in increments.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project is developed using progressive elaboration. Projects are often defined
broadly when they begin, and as time passes, the specific details of the project become
clearer. Therefore, projects should be developed in increments.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.6
QUESTION TYPE: True / False

, HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



5. A project manager’s primary role is to provide the funding for a
project. a. True
b. False
ANSWER: False
RATIONALE: Feedback: A project sponsor usually provides the direction and funding for a project.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



6. One of the main reasons why project management is challenging is
because of the factor of uncertainty. a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project involves uncertainty. Every project is unique and thus it is sometimes
difficult to define its objectives clearly, estimate how long it will take to complete, or
determine how much it will cost. This uncertainty is one of the main reasons project
management is so challenging.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.7

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
wokeshe Massachusetts Institute Of Technology
Follow You need to be logged in order to follow users or courses
Sold
235
Member since
3 year
Number of followers
223
Documents
368
Last sold
2 months ago
Studentsonly

I started studying a long time ago with long-distance learning, found it to be very hard, time-consuming and I was in desperate need of guidance and help. It was not that I was lazy, wanted a quick solution but my time was so scarce. I decided there was a need for notes, memo packs and so I started my journey. I have been doing this for years, I have sold to many of the online tutor sites which I have noticed sell my packs on here now too. I hope my work and research will help you.

Read more Read less
3.4

21 reviews

5
8
4
4
3
3
2
1
1
5

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions