What do architects do?
(A) Draw Buildings
(B) Model Buildings
(C) Design Buildings
(D) Construct Buildings
(E) Write about Buildings ...ANSWER...All of the Above
Arrange the following tasks for a typical project in ascending order of scheduled time,
that is, from the task requiring the least time to the most. I. Schematic design phase II.
Bidding phase III. Client approval IV. Design development phase V. Construction
documents phase
(A) II, I, Ill, V, IV
(B) I, III, II, V, IV
(C) III, I, IV, II, V
(D) III, II, I, IV, V ...ANSWER...(D) III, II, I, IV, V
-Client Approval
-Bidding Phase
-Schematic Design
-Design Development Phase
-Construction Document Phase
Most foundation failures are attributed to excessive uniform settlement.
(T) True
(F) False ...ANSWER...(F) False
Which of these materials is suitable for building foundations upon?
(A)Peat
(B) Gravel
(C) Topsoil
(D) Organic soils ...ANSWER...(B) Gravel
, Settlement of a building after it is constructed is likely to be the greatest under which
conditions? (Choose only one)
(A) Foundation is bearing on fiction piles.
(B) Foundation is bearing on engineered fill.
(C) Foundation is bearing on bedrock.
(D) Foundation is bearing on clay. ...ANSWER...(D) Foundation is bearing on clay.
Which of the following is NOT a slope support system for deep excavations?
(A)Slurry Walls
(B) Steel sheet piling
(C) Precast concrete sheet piling
(D) Soldier beams and lagging
(E) Caissons ...ANSWER...(E) Caissons
Frost line refers to the level of earth
(A) at which the soil bearing value is affected by weather.
(B) at which the building foundation should be located.
(C) below which the footings will not freeze.
(D) below which the soil does not freeze. ...ANSWER...(D) below which the soil does
not freeze.
If the loads of a proposed structure are high relative to the bearing capacity of the soil,
one would likely provide
(A) a mat footing.
(B) continuous wall footings.
(C) combined footings.
(D) shallow spread footings. ...ANSWER...(A) a mat footing.
A system of piles may be appropriate for supporting a structure when
(A) moisture in the soil is detected.
(B) the piles can be placed below ground water level.
(C) dense earth makes conventional excavation difficult.
(D) the surface soil has low bearing capacity. ...ANSWER...(D) the surface soil has low
bearing capacity.
Foundation design in northern climates can require footings to be as deep as 5 feet 1
500 mm] below grade for which of the following reasons?
(A) Protect against snow drifts
Complete Solutions
What do architects do?
(A) Draw Buildings
(B) Model Buildings
(C) Design Buildings
(D) Construct Buildings
(E) Write about Buildings ...ANSWER...All of the Above
Arrange the following tasks for a typical project in ascending order of scheduled time,
that is, from the task requiring the least time to the most. I. Schematic design phase II.
Bidding phase III. Client approval IV. Design development phase V. Construction
documents phase
(A) II, I, Ill, V, IV
(B) I, III, II, V, IV
(C) III, I, IV, II, V
(D) III, II, I, IV, V ...ANSWER...(D) III, II, I, IV, V
-Client Approval
-Bidding Phase
-Schematic Design
-Design Development Phase
-Construction Document Phase
Most foundation failures are attributed to excessive uniform settlement.
(T) True
(F) False ...ANSWER...(F) False
Which of these materials is suitable for building foundations upon?
(A)Peat
(B) Gravel
(C) Topsoil
(D) Organic soils ...ANSWER...(B) Gravel
, Settlement of a building after it is constructed is likely to be the greatest under which
conditions? (Choose only one)
(A) Foundation is bearing on fiction piles.
(B) Foundation is bearing on engineered fill.
(C) Foundation is bearing on bedrock.
(D) Foundation is bearing on clay. ...ANSWER...(D) Foundation is bearing on clay.
Which of the following is NOT a slope support system for deep excavations?
(A)Slurry Walls
(B) Steel sheet piling
(C) Precast concrete sheet piling
(D) Soldier beams and lagging
(E) Caissons ...ANSWER...(E) Caissons
Frost line refers to the level of earth
(A) at which the soil bearing value is affected by weather.
(B) at which the building foundation should be located.
(C) below which the footings will not freeze.
(D) below which the soil does not freeze. ...ANSWER...(D) below which the soil does
not freeze.
If the loads of a proposed structure are high relative to the bearing capacity of the soil,
one would likely provide
(A) a mat footing.
(B) continuous wall footings.
(C) combined footings.
(D) shallow spread footings. ...ANSWER...(A) a mat footing.
A system of piles may be appropriate for supporting a structure when
(A) moisture in the soil is detected.
(B) the piles can be placed below ground water level.
(C) dense earth makes conventional excavation difficult.
(D) the surface soil has low bearing capacity. ...ANSWER...(D) the surface soil has low
bearing capacity.
Foundation design in northern climates can require footings to be as deep as 5 feet 1
500 mm] below grade for which of the following reasons?
(A) Protect against snow drifts