• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 3 out of 17 pages
Exam (elaborations)

CM Docs Exam Questions with 100% Accurate Solution

Document preview thumbnail
Preview 3 out of 17 pages

Select the four fundamental stages of the construction management process - CORRECT ANSWER-Pre-Construction, Procurement, Construction, and Post-Construction The design process has four distinct stages, what are they? - CORRECT ANSWER-Programming and feasibility, Schematic design, Design development, and Contract documents Name two procurement instruments used to buy out a job - CORRECT ANSWER-Sub-contracts & Purchase orders Which occurrence marks the official completion of the project? - CORRECT ANSWER-Certificate of substantial completion What activities usually occur during the mobilization stage? - CORRECT ANSWER-Set up field office, Secure site, Provide & place portable toilets Select the best definition of "Punch List" - CORRECT ANSWER-Minor adjustments, repairs, and work items that must be completed Select best definition of "substantial completion" - CORRECT ANSWER-The point at which all punch list work has been completed and the owner can occupy or take possession of the new facility Select the best definition of "As-built drawings" - CORRECT ANSWER-Record drawings completed by the contractor and turned over to the owner at the end of the project that identify changes to original plans and specifications Select the following that are usually included in the final documentation to the owner. - CORRECT ANSWER-Warranties, Operation manuals, Inspection and testing reports, and As-built drawings

Content preview

CM Docs Exam Questions with 100%
Accurate Solution

Select the four fundamental stages of the construction management process -
CORRECT ANSWER-Pre-Construction, Procurement, Construction, and Post-
Construction



The design process has four distinct stages, what are they? - CORRECT ANSWER-
Programming and feasibility, Schematic design, Design development, and Contract
documents



Name two procurement instruments used to buy out a job - CORRECT ANSWER-Sub-
contracts & Purchase orders



Which occurrence marks the official completion of the project? - CORRECT ANSWER-
Certificate of substantial completion



What activities usually occur during the mobilization stage? - CORRECT ANSWER-Set
up field office, Secure site, Provide & place portable toilets



Select the best definition of "Punch List" - CORRECT ANSWER-Minor adjustments,
repairs, and work items that must be completed



Select best definition of "substantial completion" - CORRECT ANSWER-The point at
which all punch list work has been completed and the owner can occupy or take
possession of the new facility



Select the best definition of "As-built drawings" - CORRECT ANSWER-Record drawings
completed by the contractor and turned over to the owner at the end of the project that
identify changes to original plans and specifications

,Select the following that are usually included in the final documentation to the owner. -
CORRECT ANSWER-Warranties, Operation manuals, Inspection and testing reports,
and As-built drawings



___________ keep track of and manages the completion of all loose ends, minor

repairs, and adjustments at the end of the job. - CORRECT ANSWER-Punch lists



A contract is entered into whereby the Design and Scope are partially undefined, the
Owner holds a contract with the A/E, the Owner holds the contracts with each trade and
the Owner also holds a contract with a management service company to perform the
trade coordination, cost control and scheduling services. What is this project delivery
called? - CORRECT ANSWER-Construction Management



In the Agency CM delivery system, the CM (not the owner) contracts with the general
contractor - CORRECT ANSWER-False



Which delivery method is the construction administrator most like a consultant? -
CORRECT ANSWER-CM Agency



Which of the following is a major difference between a CM agency and a CM at risk? -
CORRECT ANSWER-One caps the construction costs the owner is required to pay



One of the advantages of the CM delivery system is the excellent value engineering. -
CORRECT ANSWER-True



Who determines what method of delivery is used on a project? - CORRECT ANSWER-
Owner



Design-Build contracts can be used in any public works projects in any states. -
CORRECT ANSWER-False



A design-build firm may be (check all that apply): - CORRECT ANSWER--a joint
venture contract between a con- tractor and a design firm.

-a single firm with both design and construction capability.

, -a design firm that sub-contracts the construction portion to a construction contractor

-a construction contracting firm that subcontracts the design work to an architect or
engineer firm.



The principal barrier to the use of design-build process in the public sector lies in the
difference between the procurement laws governing the selection process for AE and
GC. - CORRECT ANSWER-True



In the DBB delivery system, the designer works for the general contractor - CORRECT
ANSWER-False



The first company that the owner hires in the DBB delivery system is the general
contractor. - CORRECT ANSWER-False



The contractual relationship in DBB governed by the conditions of the contract is
between: - CORRECT ANSWER-Owner and contractor



Under DBB, the owner has a contractual relationship with suppliers and subcontractors.
- CORRECT ANSWER-False



Under DBB, there being no contractual relationship between the A/E and the
contractor,there is also no contractual relationship between the A/E and the
subcontractors and suppliers. - CORRECT ANSWER-True



The Owner wants to Fast-Track a construction project., Which project delivery
systembest supports this process? - CORRECT ANSWER-Design-Build



Which statement is true about the Design-Build delivery method? - CORRECT
ANSWER-There is a sole source for fault for building system failures



The most common method to pay for a designer is Fixed Lump Sum fee. - CORRECT
ANSWER-True

Document information

Uploaded on
September 23, 2024
Number of pages
17
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$10.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
remojudytask
3.2
(26)
Sold
96
Followers
30
Items
2950
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions