Fire inspector three functional areas - ANSWER - Administration
Field inspection
Plans review
Administrative duties - ANSWER - Processing permits
Applications
Plans review
New policies
Respond to complaints
Keeping records of written and spoken correspondence
time management skills - ANSWER - specific strategies for planning and
using time in effective, healthful ways and complete your duties
Purpose of field inspections - ANSWER - Verify whether buildings are
meeting federal, state, and local fire prevention codes.
,Requirements of field inspection - ANSWER - Assessment of the outside
and surrounding premises. Know and understand the fire safety codes
and standards adopted in thier jurisdiction
Plans review - ANSWER - Process of reviewing building plans and
specifications to determine the safety characteristics of the proposed
building generally done before permission is granted to begin
construction
appropriate dress code - ANSWER - Follows department regulations
professional and neat
shows organization and preparation for the job
Effective fire prevention education program - ANSWER - Positive
Impressions
Relationships with other agencies
community educational programs
National fire prevention week activities
The two documents that establish the legal and ethical authority for fire
inspection within the military - ANSWER - DODI 6055.06 (DOD Fire and
Emergency Services Program)
UFC 3-600-01 (Fire Protection Engineering for Facilities)
,DODI 6055.06 (DOD Fire and Emergency Services Program) - ANSWER -
Establishes the foundation for fire pervention and education program
UFC 3-600-01 (Fire Protection Engineering for Facilities) - ANSWER -
Specifies fire codes and standards that are adopted and implemented
by all DOD fire departments
Special Operation permits include - ANSWER - Maintenance and
storage of Haz products
Haz ops (welding, fireworks, bonfires, open burning)
Installation or operation of equipment in connection with haz ops.
Two main goals for permitting process - ANSWER - 1. ensures Haz
operations or installments meets applicable requirements
2. ensures fire department personnel are aware of the haz ops being
accomplished.
when does the permitting process begin? - ANSWER - when a property
owner or contractor decides to perform a specific activity requiring a
permit.
Before issuing a permit, fire inspector must do the following: - ANSWER
- 1. conduct a site visit
2. Make sure the permit is complete
3. make sure all supporting materials have been provided
, determining wheter a hot work permit should be given: - ANSWER - 1.
ID if there are flammable materials present in work location
2. Ensure combustibles are isolated from ignition
3. Prevent hot works ops from occuring when exposing combustibles to
ignition
4. ensure extinguishing equipment is on hand
5. Half hour after operations are complete there must be a fire watch
Fire Watch Requirements - ANSWER - 1. Watch for fires
2. ensure safe conditions are maintained
3. has authority to stop welding ops if it is unsafe
4. has fire extinquishing equipment on hand
the need for a fire watch - ANSWER - 1. combusible material are 35 ft to
point of ops
2. easily ignited combustibles are adjacent to the opposite side of
partitions, walls, ceilings, or roofs.
Permits must have these three conditions: - ANSWER - 1. What
activities are being allowed
2. guidelines that must be followed
3. The timeframe for which the permit is valid