Exam (elaborations)
BUS 395 Cal Poly Midterm 1 (Ch.1-Ch.6) McQuaid Questions With Correct Answers
best practice - Answer An optimal way recognized by industry to achieve a stated goal or objective 
 
critical path - Answer The longest path through a network diagram that determines the earliest completion of a project 
 
enterprise project management software - Answer • Software that integrates information from multiple projects to show the status of active, approved, and future projects across an entire organization; also called portfolio project management software 
 
Gantt chart - Answer...
Exam (elaborations)
BUS 395 Midterm Questions With Correct Answers
PopularWhich objective is true of projects? - Answer they have a unique purpose 
 
project integration management must occur just within the context of a particular project - Answer false 
 
When does payback occur? - Answer when the net cumulative benefits equal the net cumulative costs 
 
Steve, an engineer in a construction company, is at present working on a home construction project. The home is being built for the Robinson family, the owners of the home. Steve is working with his project team and...
Package deal
Bus 395 Bundled Questions Answered Correctly Latest Update 2026/2027
NewBus 395 Bundled Questions Answered Correctly Latest Update 2026/2027
Exam (elaborations)
Bus 395 - Quiz 3 Questions With Correct Answers Latest Update 2026
NewBUS 395 - QUIZ 3 QUESTIONS WITH CORRECT ANSWERS LATEST UPDATE 2026 
 
Schedule Conflicts - Answers Different cultures and individual work styles 
Least Flexible Constraint - Answers Time 
Project Time Management Processes - Answers Planning schedule management 
Defining activities 
Sequencing activities 
Estimating activity resources 
Estimating activity durations 
Developing the schedule 
Controlling the schedule 
Schedule Management Plan - Answers Project schedule model development, scheduling...
Exam (elaborations)
Bus 395 Quiz 2 Prep Questions Answered Correctly Latest Update 2026
NewBUS 395 QUIZ 2 PREP QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026 
 
A customer refuses to sign off deliverables due to misunderstood requirements. Which process group likely caused the issue? 
Executing 
Initiating 
Planning - Answers Planning 
A vendor announces a 3-week delay for a critical component. Which process group manages the impact? 
Closing 
Monitoring & Controlling 
Planning 
Initiating - Answers Monitoring & Controlling 
Which strategic tool is used to identify strengths, weaknes...
Exam (elaborations)
Bus 395 - Midterm Review Questions With Correct Answers Latest Update 2026
NewBUS 395 - MIDTERM REVIEW QUESTIONS WITH CORRECT ANSWERS LATEST UPDATE 2026 
 
Project - Answers Building a new, unique skyscraper with defined start & end date 
Portfolio - Answers Tech comp managing all its investments, projects, ongoing work 
Program - Answers Marketing from launching coordinated series of related campaigns for new product launch 
Risk tolerance - Answers Employees are encouraged to be aggressive & innovative; mistakes are learning opportunities 
Means-end - Answers Management...
Package deal
BUS 395 Exam Package Deal
BUS 395 Final Exam, Bus 395 Final Exam, Final Test, BUS 395 - Midterm, BUS 395 Final Exam, Study Guide, BUS 395 Exam 1, Ch 12 Final Test, BUS 395 Quiz 1, Ch.1-Ch.6, BUS 395 Midterm, Practice Test, BUS 395 ch. 8,
Exam (elaborations)
BUS 395 ch. 8: Project Quality Management Exam Solved 100%
_____________ is the degree to which a set of inherent characteristics fulfills requirements - Answer Quality 
 
What is the purpose of project quality management? - Answer To ensure that the project will satisfy the needs for which it was undertaken 
 
_________ generates ideas for quality improvements by comparing specific project practices or product characteristics to those of other projects or products within or outside the performing organization - Answer benchmarking 
 
What does the term...
Exam (elaborations)
BUS 395 Midterm 1 Practice Test With Complete Solution
Until the 1980s, project management primarily focused on providing schedule and resource data to top management in the military, computer, and construction industries. - Answer True 
 
A project manager's primary role is to provide the funding for a project. - Answer False 
 
In order to be realistic, a project manager should always set discrete goals instead of a range of objectives. - Answer False 
 
Managing the triple constraint primarily involves making trade-offs between resources and qua...
Exam (elaborations)
BUS 395 Quiz 1 With Verified Answers
Advantages of Using Formal Project Management - Answer ◦Better control of financial, physical, and human resources 
◦Improved customer relations 
◦Shorter development times 
◦Lower costs and improved productivity 
◦Higher quality and increased reliability 
◦Higher profit margins 
◦Better internal coordination 
◦Positive impact on meeting strategic goals 
◦Higher worker morale 
 
Project - Answer a temporary endeavor undertaken to create a unique product, service, or result 
 
P...
Exam (elaborations)
BUS 395 Ch 12 Final Test With Complete Solution
project procurement management - Answer acquire goods/services from an outside source 
 
reasons for increasing the use of outsourcing information technology projects - Answer 1) to access skills and technologies that you may not have 
2)reduce fixed and recurrent costs 
3)allow client organization to focus on their business rather than learn new skills 
4)provide flexibility 
5)increase accountability 
 
Project Procurement Management Processes - Answer o Planning procurements 
o Conducting pro...
Exam (elaborations)
BUS 395 Exam 1 Education Savings + Some Ratios Questions With Correct Answers
Appropriate time to rent or lease if - Answer time in property is going to be short (1-3 years) 
 
Appropriate time to buy if - Answer - Time in property is going to be long (>3 years) 
 
Adjustable Rate Mortgage - Answer - is appropriate when time in property is short 
- 2/6 means the interest rate cannot increase more than 2% per year or 6% during the term of the loan 
 
Reverse Mortgages - Answer - homeowner receives a monthly payment or lump sum and retains right to live in house 
-repaym...
Exam (elaborations)
BUS 395 Shortened Final Exam Study Guide With Complete Solution
7 Project Time Management Processes - Answer - Planning schedule management 
- Defining activities 
- Sequencing activities 
- Estimating activity resources 
- Estimating activity duration 
- Developing the schedule 
- Controlling the schedule 
 
Elements of a schedule management plan - Answer - Project schedule model development 
- Scheduling methodology 
- Level of accuracy and units of measure 
- Control thresholds 
- Rules of performance measurement 
- Reporting formats 
- Process descripti...
Exam (elaborations)
BUS 395 Final Exam Questions & Answers Latest Updated
What is the Test Team's job? - Answer Test/quality control (risk mgmt and quality assessment) , quality assurance (test/QC mgmt and ensuring quality throughout the process) , and to make sure you're competent, staffed and politically supported for your role. 
 
Is independent testing a spectrum or linear? - Answer It's a spectrum. 
 
Outline the spectrum of independence from lowest to highest level of independence (6). - Answer (1) No independent testers. Developers test their own code. 
(2) ...
Exam (elaborations)
BUS 395 - Midterm - Ewais Questions With Verified Answers
Operation - Answer work done to sustain a business. Continues 
 
Project - Answer a temporary endeavor undertaken to create a unique product, service, or result. 
 
Projects end when their objectives have been reached or the project has been terminated 
 
Project Attributes - Answer A project: 
-has a unique purpose 
-is temporary 
-drives change and enable value creation 
-is developed using progressive elaboration 
-requires resources, often from various areas 
-should have a primary customer ...
Exam (elaborations)
BUS 395 Final Test With Complete Solution
Project Schedule Management - Answer involves the processes required to ensure timely completion of a project 
 
Main processes in Schedule Management - Answer - Plan Schedule Management 
- Define Activities 
- Sequence Activities 
- Estimate Activity Durations 
- Develop the Schedule 
- Control the Schedule 
 
Plan Schedule Management - Answer involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule 
 
main...
Exam (elaborations)
Bus 395 Final Exam Questions With Correct Answers
Actual Cost - Answer The total of direct and indirect costs incurred in accomplishing work on an activity during a given period 
 
Analogous Estimates - Answer A cost estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project, also called top-down estimates. 
 
Baseline - Answer The original project plan plus approved changes. 
 
Bottom-up estimates - Answer A cost-estimating technique based on estimating individual w...
Exam (elaborations)
BUS 395 Final Exam Questions With Verified Answers
Project Schedule Management - Answer the processes we have to perform to ensure timely completion of the project (has 7 processes) 
 
7 Project time management processes - Answer 1. Planning schedule management 
2. Defining activities 
3. Sequencing activities 
4. Estimating activity resources 
5. Estimating activity durations 
6. Developing the schedule 
7. Controlling the schedule 
 
What is the main output of planning schedule management? - Answer Schedule management plan 
 
Elements of a sch...