BMDS 3371 (BMDS 3371)
University Of The Incarnate Word
All 1 results
Sort by
-
BMDS 3371 Week 8 Final Exam 2020_100% Score
- Exam (elaborations) • 6 pages • 2020
-
- $18.98
- + learn more
Arcs in a project network indicate
a. completion times.
b. precedence relationships.
c. activities.
d. None of the alternatives above is correct.2. Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
a. is 10.
b. is 12.
c. is 15.
d. cannot be determined.3. When activity times are uncertain,
a. assume they are normally distributed.
b. calculate the expected time, using (a 4m b)/...
Get paid weekly? You can!
That summary you just bought made someone very happy. Also get paid weekly? Sell your study resources on Stuvia! Discover all about earning on Stuvia