100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Information Technology Project Management (9th Edition) – Test Bank for IT Project Management Exam Preparation

Rating
-
Sold
-
Pages
312
Grade
A+
Uploaded on
19-12-2025
Written in
2025/2026

This document provides a complete test bank based on Information Technology Project Management (9th Edition) by Kathy Schwalbe. It includes practice questions covering project initiation, planning, execution, monitoring, and closure within IT environments. The material supports students in understanding project management frameworks, tools, and best practices used in information technology projects.

Show more Read less
Institution
Information Technology Project Management
Course
Information technology project management











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Information technology project management
Course
Information technology project management

Document information

Uploaded on
December 19, 2025
Number of pages
312
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

TEST BANK FOR INFORMATION
TECHNOLOGY PROJECT
MANAGEMENT,
9TH EDITION, KATHY SCHWALBE

, Chapter 1. Introduction to Project Management Y5 Y5 Y5 Y5 Y5




True / False
Y5 Y5




1. Until the 1980s, project management primarily focused on providing schedule and resource data to top
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5



management in the military, computer, and construction industries. a. True
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y 5 Y 5




b. False Y5



ANSWER: True
RATIONALE: Feedback: Until the 1980s, project management primarily focused on providing schedule
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




and resource data to top management in the military, computer, and construction industries.
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




Today’s project management involves much more, and people in every industry and every
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




Y5 country manage projects.Y5 Y5




POINTS: 1
DIFFICULTY: Difficulty: Easy Y5




REFERENCES: p.2
QUESTION TYPE: Y5 True / False Y5 Y5




HAS VARIABLES:
Y5 False
LEARNING OBJECTIVES: Y5 Y 5 INFO.SCHW.14.1 - LO: 1-1 Y 5 Y5 Y5




NATIONAL STANDARDS: Y5 Y United States - BUSPROG: - Comprehension
5 Y5 Y5 Y5 Y5 Y5



TOPICS: Introduction
KEYWORDS: Bloom's: Knowledge Y5




DATE CREATED: Y5 4/27/2018 2:53 PM Y5 Y5




DATE MODIFIED: Y5 4/27/2018 2:53 PM Y5 Y5




2. A difference between operations and projects is that operations end when their objectives have been reached,
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5



whereas projects do not. a. True
Y5 Y5 Y5 Y5 Y 5 Y 5




b. False Y5



ANSWER: False
RATIONALE: Feedback: Projects are different from operations in that they end when their objectives
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




have been reached or the project has been terminated.
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




POINTS: 1
DIFFICULTY: Difficulty: Moderate Y5




REFERENCES: p.4
QUESTION TYPE: Y5 True / False Y5 Y5




HAS VARIABLES:
Y5 False

,LEARNING OBJECTIVES: Y5 Y 5 INFO.SCHW.14.2 - LO: 1-2 Y 5 Y5 Y5




NATIONAL STANDARDS: Y5 Y 5United States - BUSPROG: Analytic
Y5 Y5 Y5 Y5



TOPICS: What is a Project? Y5 Y5 Y5



KEYWORDS: Bloom's: Comprehension Y5




DATE CREATED:
Y5 4/27/2018 2:53 PM Y5 Y5



DATE MODIFIED:
Y5 4/27/2018 2:53 PM Y5 Y5




3. Every project should have a well-defined objective.
Y5 Y5 Y5 Y5 Y5 Y5



a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project has a unique purpose. Every project should have a well-
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




defined objective.
Y5




POINTS: 1
DIFFICULTY: Difficulty: Easy Y5




REFERENCES: p.6
QUESTION TYPE: Y5 True / False Y5 Y5




HAS VARIABLES:
Y5 False
LEARNING OBJECTIVES: Y5 Y 5 INFO.SCHW.14.2 - LO: 1-2 Y 5 Y5 Y5




NATIONAL STANDARDS: Y5 Y 5United States - BUSPROG: - Comprehension
Y5 Y5 Y5 Y5 Y5



TOPICS: What is a Project? Y5 Y5 Y5



KEYWORDS: Bloom's: Knowledge Y5




DATE CREATED:
Y5 4/27/2018 2:53 PM Y5 Y5




DATE MODIFIED:
Y5 4/27/2018 2:53 PM Y5 Y5




4. Projects should be developed in increments.
Y5 Y5 Y5 Y5 Y5



a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project is developed using progressive elaboration. Projects are often
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




defined broadly when they begin, and as time passes, the specific details of the project become
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




clearer. Therefore, projects should be developed in increments.
Y5 Y5 Y5 Y5 Y5 Y5 Y5




POINTS: 1
DIFFICULTY: Difficulty: Easy Y5




REFERENCES: p.6
QUESTION TYPE: Y5 True / False Y5 Y5

, HAS VARIABLES: Y5 False
LEARNING OBJECTIVES: Y5 Y 5 INFO.SCHW.14.2 - LO: 1-2 Y 5 Y5 Y5




NATIONAL STANDARDS: Y5 Y 5United States - BUSPROG: - Comprehension
Y5 Y5 Y5 Y5 Y5



TOPICS: What is a Project?
Y5 Y5 Y5



KEYWORDS: Bloom's: Knowledge Y5




DATE CREATED: Y5 4/27/2018 2:53 PM Y5 Y5




DATE MODIFIED: Y5 4/27/2018 2:53 PM Y5 Y5




5. A project manager’s primary role is to provide the funding
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5



for a project. a. True
Y5 Y5 Y5 Y 5 Y 5




b. False Y5



ANSWER: False
RATIONALE: Feedback: A project sponsor usually provides the direction and funding for a project.
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




POINTS: 1
DIFFICULTY: Difficulty: Easy Y5




REFERENCES: p.7
QUESTION TYPE: Y5 True / False
Y5 Y5




HAS VARIABLES: Y5 False
LEARNING OBJECTIVES: Y5 Y 5 INFO.SCHW.14.2 - LO: 1-2 Y 5 Y5 Y5




NATIONAL STANDARDS: Y5 Y 5United States - BUSPROG: - Comprehension
Y5 Y5 Y5 Y5 Y5



TOPICS: What is a Project?
Y5 Y5 Y5



KEYWORDS: Bloom's: Knowledge Y5




DATE CREATED: Y5 4/27/2018 2:53 PM Y5 Y5




DATE MODIFIED: Y5 4/27/2018 2:53 PM Y5 Y5




6. One of the main reasons why project management is challenging
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5



is because of the factor of uncertainty. a. True
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y 5 Y 5




b. False Y5



ANSWER: True
RATIONALE: Feedback: A project involves uncertainty. Every project is unique and thus it is
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




sometimes difficult to define its objectives clearly, estimate how long it will take to complete, or
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




determine how much it will cost. This uncertainty is one of the main reasons project
Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5 Y5




Y5 management is so challenging. Y5 Y5 Y5




POINTS: 1
DIFFICULTY: Difficulty: Moderate Y5




REFERENCES: p.7

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PrepMasters stuvia
View profile
Follow You need to be logged in order to follow users or courses
Sold
12
Member since
3 months
Number of followers
0
Documents
754
Last sold
7 hours ago
College TestBank Hub

College TestBank Hub offers instant access to college test banks, exam guides, and solution manuals for top textbooks and courses. Get accurate, up-to-date resources that make studying easier and exam prep faster.

5.0

2 reviews

5
2
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions