1|Page
NCCCO TOWER CRANE FINAL EXAM 2026/2027
NEWEST ACTUAL EXAM COMPLETE 150 QUESTIONS
AND 100%CORRECT DETAILED ANSWERS (VERIFIED
ANSWERS) |ALREADY GRADED A+
According to OSHA after the crane has been checked out
and before personnel lift operations begin the crew should
- ANSWER-Have a pre-lift meeting OSHA 1926.550(g)(8)
Load bearing members of the climbing and support
system shall be inspected before each - ANSWER-
Climbing operation
,2|Page
Where shall a wind velocity indicating device be mounted -
ANSWER-At or near the top of crane
A velocity readout shall be provided - ANSWER-At the
operators station
The area inside the self erecting tower cranes tail swing
must be - ANSWER-Barricaded
The self erecting tower crane must be properly grounded
according with the - ANSWER-National electric code
(NEC)
,3|Page
Self Erecting tower crane erection must be performed by -
ANSWER-Qualified person
Extensive planning must occur before a self erecting tower
crane arrives on the job site. The plan should be divided
into two major sections as follows - ANSWER-Delivery, set
up, erection and dismantle - Lifting operations
According to ASME B30.3 the minimum wraps to be left on
a hoist drum are - ANSWER-3
How much does a cubic foot of steel weigh - ANSWER-
490lbs
, 4|Page
When operating a tower crane and there is an
uncontrolled movement, the operator should - ANSWER-
Engage emergency stop
What will not create a change in stability - ANSWER-
Pulling off a fixed load
When performing a load test on a tower crane that travels.
How should the job be set - ANSWER-So the maximum
weight is on the bogie
When plumbing a tower crane after it has been climbed,
the crane must - ANSWER-be balanced
NCCCO TOWER CRANE FINAL EXAM 2026/2027
NEWEST ACTUAL EXAM COMPLETE 150 QUESTIONS
AND 100%CORRECT DETAILED ANSWERS (VERIFIED
ANSWERS) |ALREADY GRADED A+
According to OSHA after the crane has been checked out
and before personnel lift operations begin the crew should
- ANSWER-Have a pre-lift meeting OSHA 1926.550(g)(8)
Load bearing members of the climbing and support
system shall be inspected before each - ANSWER-
Climbing operation
,2|Page
Where shall a wind velocity indicating device be mounted -
ANSWER-At or near the top of crane
A velocity readout shall be provided - ANSWER-At the
operators station
The area inside the self erecting tower cranes tail swing
must be - ANSWER-Barricaded
The self erecting tower crane must be properly grounded
according with the - ANSWER-National electric code
(NEC)
,3|Page
Self Erecting tower crane erection must be performed by -
ANSWER-Qualified person
Extensive planning must occur before a self erecting tower
crane arrives on the job site. The plan should be divided
into two major sections as follows - ANSWER-Delivery, set
up, erection and dismantle - Lifting operations
According to ASME B30.3 the minimum wraps to be left on
a hoist drum are - ANSWER-3
How much does a cubic foot of steel weigh - ANSWER-
490lbs
, 4|Page
When operating a tower crane and there is an
uncontrolled movement, the operator should - ANSWER-
Engage emergency stop
What will not create a change in stability - ANSWER-
Pulling off a fixed load
When performing a load test on a tower crane that travels.
How should the job be set - ANSWER-So the maximum
weight is on the bogie
When plumbing a tower crane after it has been climbed,
the crane must - ANSWER-be balanced