When you find a bottleneck, the first step should be:
a. add additional resources to the bottleneck
b. Look at removing waste in the process
c. line balancing
d. creating standard work
Give this one a try later!
b. Look at removing waste in the process (process in order b,c,d,a)
,Hour by hour charts help track production vs target to help operators and front-line
leaders make timely resource decisions. Hour by hour charts are an example of?
a. Leaders standardized work
b. Visual control
c. 5S
d. Interval
Give this one a try later!
b. Visual control
Which of the following are enablers to "separating man from machine"?
a. Standardized work, Jidoka
b. 5S, VSM
c. Autonomous Maintenace, Kaizen
d. Visual factory, Kaizen
Give this one a try later!
a. Standardized work, Jidoka
One of the foundations of the TPS is standardized work. Its purpose is to:
a. Ensure we capture the best practice work method
b. Reduce operator to operator variation
c. Provide a basis for improvement
d. All of the above
Give this one a try later!
, a. Product Family Matrix
Which is considered to be the WORST of the seven wastes?
a. Inventory
b. motion
c. Overproduction
d. Defects
Give this one a try later!
c. Overproduction
When the Ishikawa Diagram (Fishbone analysis) is used the potential causes are
broken down by:
a. 8P's
b. 4S's
c. 4M's
d. 5S's
Give this one a try later!
c. 4M's
What's the name of an activity that is non-value added but necessary?
a. Incidental
b. Auxiliary
c. Specified
d. A and B only
, Give this one a try later!
d. A and B only
Production standards in a lean system should be established by:
a. Scheduling managers
b. process engineers
c. efficiency experts
d. Production workers
Give this one a try later!
d. Production workers
Idea management systems are an important part of engaging employees at all levels.
Which is NOT an element of a good suggestions system?
a. A suggestion box on the wall
b. A simple approval process
c. A plan for recognition of ideas
d. All ideas are encouraged even small ones
Give this one a try later!
a. A suggestion box on the wall
If my WIP is 10 pieces and my cycle time is 2.5 days, what is my throughput rate?
a. 4 pieces per day
b. 25 pieces per day
a. add additional resources to the bottleneck
b. Look at removing waste in the process
c. line balancing
d. creating standard work
Give this one a try later!
b. Look at removing waste in the process (process in order b,c,d,a)
,Hour by hour charts help track production vs target to help operators and front-line
leaders make timely resource decisions. Hour by hour charts are an example of?
a. Leaders standardized work
b. Visual control
c. 5S
d. Interval
Give this one a try later!
b. Visual control
Which of the following are enablers to "separating man from machine"?
a. Standardized work, Jidoka
b. 5S, VSM
c. Autonomous Maintenace, Kaizen
d. Visual factory, Kaizen
Give this one a try later!
a. Standardized work, Jidoka
One of the foundations of the TPS is standardized work. Its purpose is to:
a. Ensure we capture the best practice work method
b. Reduce operator to operator variation
c. Provide a basis for improvement
d. All of the above
Give this one a try later!
, a. Product Family Matrix
Which is considered to be the WORST of the seven wastes?
a. Inventory
b. motion
c. Overproduction
d. Defects
Give this one a try later!
c. Overproduction
When the Ishikawa Diagram (Fishbone analysis) is used the potential causes are
broken down by:
a. 8P's
b. 4S's
c. 4M's
d. 5S's
Give this one a try later!
c. 4M's
What's the name of an activity that is non-value added but necessary?
a. Incidental
b. Auxiliary
c. Specified
d. A and B only
, Give this one a try later!
d. A and B only
Production standards in a lean system should be established by:
a. Scheduling managers
b. process engineers
c. efficiency experts
d. Production workers
Give this one a try later!
d. Production workers
Idea management systems are an important part of engaging employees at all levels.
Which is NOT an element of a good suggestions system?
a. A suggestion box on the wall
b. A simple approval process
c. A plan for recognition of ideas
d. All ideas are encouraged even small ones
Give this one a try later!
a. A suggestion box on the wall
If my WIP is 10 pieces and my cycle time is 2.5 days, what is my throughput rate?
a. 4 pieces per day
b. 25 pieces per day