North Carolina Building Contractor Licensing
Exam – Intermediate Questions And Correct
Answers (Verified Answers) Plus Rationales
2026 Q&A | Instant Download Pdf
1. Which of the following licenses allows a contractor to work on
projects up to $1,000,000 in value in North Carolina?
A. Limited
B. Intermediate
C. Unlimited
D. Residential Only
The Intermediate license allows projects up to $1,000,000.
2. Which document establishes the legal relationship between owner
and contractor?
A. Specification Book
B. Permitting Sheet
C. Construction Contract
D. Change Order
The construction contract formalizes obligations and responsibilities.
3. What is the minimum bond required for an Intermediate contractor
license in NC?
A. $10,000
B. $50,000
C. $75,000
,D. $150,000
Intermediate classification requires a $75,000 surety bond or equivalent
working capital.
4. Which entity enforces contractor licensing regulations in NC?
A. OSHA
B. FEMA
C. NC Licensing Board for General Contractors
D. NC Home Builders Association
The NCLBGC manages licensing and compliance.
5. Which project type requires an NC building contractor to be
licensed?
A. Work below $2,500
B. Landscaping
C. Projects $40,000 or more
D. Painting
NC requires licensure for projects ≥ $40,000.
6. A contract modification after execution is known as:
A. Addendum
B. Punch List
C. Change Order
D. Proposal
Change orders formally modify scope, price, or schedule.
7. OSHA requires fall protection at what height in construction?
A. 4 feet
B. 6 feet
, C. 8 feet
D. 10 feet
Construction fall protection begins at 6 feet.
8. Which document outlines materials and workmanship quality?
A. Permit Sheet
B. Schedule of Values
C. Specifications
D. Job Hazard Analysis
Specs define materials, quality, and performance.
9. Who is responsible for jobsite safety?
A. Owner
B. Architect
C. Engineer
D. Employer/Contractor
Employers must maintain a safe workplace.
10. The critical path in scheduling represents:
A. Optional tasks
B. Longest path determining project duration
C. Tasks with float
D. Daily safety checks
Critical path controls total project completion time.
11. Retainage in NC public projects may not exceed:
A. 2%
B. 5%
C. 10%
Exam – Intermediate Questions And Correct
Answers (Verified Answers) Plus Rationales
2026 Q&A | Instant Download Pdf
1. Which of the following licenses allows a contractor to work on
projects up to $1,000,000 in value in North Carolina?
A. Limited
B. Intermediate
C. Unlimited
D. Residential Only
The Intermediate license allows projects up to $1,000,000.
2. Which document establishes the legal relationship between owner
and contractor?
A. Specification Book
B. Permitting Sheet
C. Construction Contract
D. Change Order
The construction contract formalizes obligations and responsibilities.
3. What is the minimum bond required for an Intermediate contractor
license in NC?
A. $10,000
B. $50,000
C. $75,000
,D. $150,000
Intermediate classification requires a $75,000 surety bond or equivalent
working capital.
4. Which entity enforces contractor licensing regulations in NC?
A. OSHA
B. FEMA
C. NC Licensing Board for General Contractors
D. NC Home Builders Association
The NCLBGC manages licensing and compliance.
5. Which project type requires an NC building contractor to be
licensed?
A. Work below $2,500
B. Landscaping
C. Projects $40,000 or more
D. Painting
NC requires licensure for projects ≥ $40,000.
6. A contract modification after execution is known as:
A. Addendum
B. Punch List
C. Change Order
D. Proposal
Change orders formally modify scope, price, or schedule.
7. OSHA requires fall protection at what height in construction?
A. 4 feet
B. 6 feet
, C. 8 feet
D. 10 feet
Construction fall protection begins at 6 feet.
8. Which document outlines materials and workmanship quality?
A. Permit Sheet
B. Schedule of Values
C. Specifications
D. Job Hazard Analysis
Specs define materials, quality, and performance.
9. Who is responsible for jobsite safety?
A. Owner
B. Architect
C. Engineer
D. Employer/Contractor
Employers must maintain a safe workplace.
10. The critical path in scheduling represents:
A. Optional tasks
B. Longest path determining project duration
C. Tasks with float
D. Daily safety checks
Critical path controls total project completion time.
11. Retainage in NC public projects may not exceed:
A. 2%
B. 5%
C. 10%