100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CAPM Exam Study 2025 Questions With Complete Solutions

Rating
-
Sold
-
Pages
51
Grade
A+
Uploaded on
12-11-2025
Written in
2025/2026

CAPM Exam Study 2025 Questions With Complete Solutions

Institution
CAPM
Course
CAPM











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CAPM
Course
CAPM

Document information

Uploaded on
November 12, 2025
Number of pages
51
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CAPM Exam Study 2025 Questions With Complete
Solutions

A mobile device manufacturer is halfway through prototyping a
new product when the supplier who provides one of the raw
materials used to manufacture their device casings declares
bankruptcy and goes out of business. The team had not foreseen
this problem during project planning.
Which of the following best describes a process that may not
have been performed comprehensively in this scenario?
A
Perform qualitative risk analysis
B
Monitor risks
C
Identify risks
D
Plan risk management Correct Answers Correct answer:
Identify risks

The identify risks process is used to identify potential project
risks individually as well as overall risks to the project in
general. The characteristics of the risks are documented so that
they can be analyzed (perform qualitative and perform
quantitative risk analysis processes) and planned for (plan risk
responses). Without proper identification of risks before they are
realized, they cannot be planned for, and responses are often
pressured by time and cost constraints.

,Plan risk management is incorrect, as it refers to the process
when the methods of conducting risk management activities for
a project are determined.

Perform qualitative risk analysis is incorrect, as it prioritizes
individual risks for deeper analysis due to factors like
probability of occurrence and impact to the project.

Monitor risks is incorrect, as it tracks the implementation of the
planned risk management activities.

A project manager has been asked by a senior stakeholder to
implement some changes to the project. In evaluating the
situation and talking to the upper leadership team, the team
agreed to proceed forward with the processes to implement the
change. At what point should the project manager evaluate the
impact of a requested change?
A
First, before any other action is started
B
After the change request is approved
C
After they get the customer to buy in on the change
D
After they find a way to save time by implementing the change
Correct Answers Correct answer: First, before any other action
is started

The project manager should evaluate the impact of a requested
change before taking any other action. The project manager
should follow these steps regarding requested changes:

,Evaluate the impact
Create options
Get the change request approved
Get customer buy-in

After conducting a cost-benefit analysis, it is determined that the
project you are working on will increase company sales by 15%
over the next three years. The organization has set a goal to
increase sales by 12% within the next three years. This project
fits into what?
A
The company's business need for the project
B
The company's strategic plan
C
The product scope description
D
The project statement of work Correct Answers Correct answer:
The company's strategic plan

The strategic plan documents the organization's strategic vision,
goals, and objectives and may contain a high-level mission
statement. All projects should be aligned with their
organization's strategic plan. Strategic plan alignment ensures
that each project contributes to the overall objectives of the
organization.

In this case, the organization has announced it would like to see
a 12% increase in sales over the next three years, and
completing this project will exceed that organizational goal.

, Bai is the project manager in charge of a team very diverse in
skill sets and expertise. She works with the HR manager to add
each team member's newly acquired skills to their human
resource records. What process group will best identify where
the project manager is currently in?
A
Closing
B
Monitoring & Controlling
C
Planning
D
Executing Correct Answers Correct answer: Closing

The project manager is in the closing process group when they
are working with the HR manager to add the newly acquired
skills of each team member to the team members' human
resource records. Closing is those processes performed to
formally complete or close a project, phase, or contract.

At project or phase closure, the following may occur:

Obtain acceptance by the customer or sponsor to formally close
the project or phase
Conduct post-project or phase-end review
Record impacts of tailoring to any process
Document lessons learned
Apply appropriate updates to organizational process assets
Archive all relevant project documents in the Project
Management Information System (PMIS) to be used as
historical data

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Classroom NURSING
View profile
Follow You need to be logged in order to follow users or courses
Sold
4689
Member since
3 year
Number of followers
3218
Documents
52002
Last sold
3 hours ago
NURSING

Assignments, Case Studies, Research, Essay writing service, Questions and Answers, Discussions etc. for students who want to see results twice as fast. I have done papers of various topics and complexities. I am punctual and always submit work on-deadline. I write engaging and informative content on all subjects. Send me your research papers, case studies, psychology papers, etc, and I’ll do them to the best of my abilities. Writing is my passion when it comes to academic work. I’ve got a good sense of structure and enjoy finding interesting ways to deliver information in any given paper. I love impressing clients with my work, and I am very punctual about deadlines. Send me your assignment and I’ll take it to the next level. I strive for my content to be of the highest quality. Your wishes come first— send me your requirements and I’ll make a piece of work with fresh ideas, consistent structure, and following the academic formatting rules. For every student you refer to me with an order that is completed and paid transparently, I will do one assignment for you, free of charge!!!!!!!!!!!!

Read more Read less
4.0

1162 reviews

5
612
4
213
3
190
2
39
1
108

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions