CAPM Practice Exam Questions With Complete Solutions

A key resource is assigned to work on a project using a hybrid
approach. The project has kicked off, and work has begun. This
resource lives in another country and cannot move to the United
States to work in the office for three months. What should the
project manager do in this situation?

a. Hire an external vendor to complete this portion of the work.
b. Delay the project until the resource is available to be in the
office.
c. Train another member of the team so that they can complete
this work.
d. Request that the team member work remotely until they can
move into the country. Correct Answers d. Request that the
team member work remotely until they can move into the
country.

Explanation:
Because the resource is living in another country, it would be
best to have this resource work remotely until they can arrive in
the country. This would be a better alternative than rescheduling
the work and possibly delaying the project.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
04 - Development Approach and Life Cycle Performance
Domain

,A key stakeholder approaches you and says that there is a
missing requirement that they want incorporated without going
through a formal change control process. What do you do next?

a. Escalate to the project sponsor.
b. Accommodate the request because it is coming from a key
stakeholder.
c. Assess the impact of the requirement and submit it through
the formal change control process.
d. Negotiate with the key stakeholder to remove less valuable
requirements in exchange for this new request. Correct Answers
c. Assess the impact of the requirement and submit it through
the formal change control process.

Explanation:
Changes to a project should always be assessed and evaluated
and brought through change control.

Domain:
IV. Business Analysis Frameworks
Objective:
10 - Business Analysis Frameworks

A key stakeholder has asked you for an update on the adaptive
project you are working on. They are specifically asking how
much work remains in the current iteration. What do you direct
the stakeholder to?

a. Iteration burnup chart
b. Iteration burndown chart
c. Project schedule

,d. Work breakdown structure Correct Answers b. Iteration
burndown chart

Explanation:
An iteration burndown chart shows the work remaining in the
iteration. An iteration burnup chart shows the work completed
so far in the iteration. The other two options are used in
predictive projects.

Domain:
III. Agile/Adaptive Frameworks and Methodologies
Objective:
07 - Planning, Project Work, and Delivery: Adaptive
Approaches

A key stakeholder on an adaptive project is confused about the
product roadmap and a release plan and asks you to clarify. How
do you explain this?

a. A product roadmap contains the high-level requirements and
epics broken up into releases; a release plan showcases the
number of iterations needed to deliver certain features and user
stories decomposed from epics.
b. A release plan contains the high-level requirements and epics
broken up into products; a product roadmap showcases the
number of iterations needed to deliver certain features and user
stories decomposed from epics.
c. A product roadmap is a highly detailed plan, and a release
plan is very high level.
d. A product roadmap and release plan are used only when scope
and schedule baselines are still not defined. Correct Answers a.

, A product roadmap contains the high-level requirements and
epics broken up into releases; a release plan showcases the
number of iterations needed to deliver certain features and user
stories decomposed from epics.

Explanation:
A product roadmap acts as a high-level summary of a product's
alignment to strategic initiatives and objectives. A product
roadmap generally contains themes, epics, and goals broken up
into releases. A release plan decomposes a product roadmap's
high-level strategy into an actionable plan that outlines specific
release dates for work on features, user stories, bug fixes,
enhancements, maintenance, and so on. Essentially, a release
plan sets the number of iterations within a release and which
features are to be developed during that time frame.

Domain:
IV. Business Analysis Frameworks
Objective:
11 - Business Analysis Domains

A key stakeholder reviewed the product roadmap document,
hoping to see which iterations will deliver specific features
throughout the adaptive project. Instead, all the stakeholder saw
was high-level and strategic information about the product's
deliverables, with very broad date ranges. What document
should you tell the stakeholder to refer to instead?

a. The project management plan
b. The product backlog
c. The release plan

Document information

Uploaded on
November 12, 2025
Number of pages
238
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$31.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Classroom
4.0
(1211)
Sold
5006
Followers
3246
Items
56710
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions