CM 4221 QUIZZES QUESTIONS & ANSWERS
This testing process helps to reduce the risk that major project systems (HVAC,
electrical, etc) will work according to the project objectives, plans, and specifications.
Select one:
a.
As-builts
b.
Notice to Proceed
c.
None of these
d.
Constructability reviews
e.
Commissioning
e. Commissioning
Which of the following is not a method used to procure a constructor?
Select one:
a.
Low bid
b.
Job order contracting
c.
Best value
d.
Qualifications-based selection
e.
None of these
b.
Job order contracting
Vertical building projects are first designed by an architect and then engineered by
design engineers while horizontal infrastructure projects are typically designed and
engineered by design engineers
Select one:
True
False
, True
A feasibility study is used early in the construction phase of a project to help determine
the means and methods of construction
Select one:
True
False
False
Scoping and planning are two management activities that occur during the engineering
and design phase of a project lifecycle
Select one:
True
False
True
A program manager is the same as a project manager.
False
one major advantage of multi-prime contracting is the ease in phasing a project.
True
Which of the following delivery methods is the most used method in construction today?
Select one:
a.
Multi-prime Contracting
b.
Construction Manager at-Risk
c.
Design-Build
d.
None of these
e.
Design-Bid-Build
e.
Design-Bid-Build
This testing process helps to reduce the risk that major project systems (HVAC,
electrical, etc) will work according to the project objectives, plans, and specifications.
Select one:
a.
As-builts
b.
Notice to Proceed
c.
None of these
d.
Constructability reviews
e.
Commissioning
e. Commissioning
Which of the following is not a method used to procure a constructor?
Select one:
a.
Low bid
b.
Job order contracting
c.
Best value
d.
Qualifications-based selection
e.
None of these
b.
Job order contracting
Vertical building projects are first designed by an architect and then engineered by
design engineers while horizontal infrastructure projects are typically designed and
engineered by design engineers
Select one:
True
False
, True
A feasibility study is used early in the construction phase of a project to help determine
the means and methods of construction
Select one:
True
False
False
Scoping and planning are two management activities that occur during the engineering
and design phase of a project lifecycle
Select one:
True
False
True
A program manager is the same as a project manager.
False
one major advantage of multi-prime contracting is the ease in phasing a project.
True
Which of the following delivery methods is the most used method in construction today?
Select one:
a.
Multi-prime Contracting
b.
Construction Manager at-Risk
c.
Design-Build
d.
None of these
e.
Design-Bid-Build
e.
Design-Bid-Build