Page 1 of 103
CM EXAM 1 NEWEST WITH 3 VERSIONS WITH
400 QUESTIONS AND ANSWERS JUST
RELEASED THIS YEAR
CM EXAM 1
Question: 1. Which is not a part of the three-legged stool of construction?
A. Cost
B. Efficiency
C. Quality
D. Time - CORRECT ANSWER✔✔B
Question: 2. Which of the following is the definition for project scope?
A. A set of guidelines that establishes the budget for the project
B. Sets the design specifications for the project as identified by the architect
C. Sets the parameters for the work and defines what work needs to be done
D. None of the above - CORRECT ANSWER✔✔C
1
SUCCESS!
,Page 2 of 103
Question: 3. Which of the following is NOT a Project Delivery method?
A. Agency CM
B. CM-at-Risk
C. Design-Bid-Build
D. Design-Build - CORRECT ANSWER✔✔A
Question: 4. Who determines what method of delivery is used on a project?
A. Architect
B. Engineer
C. General Contractor
D. Owner - CORRECT ANSWER✔✔D
Question: 5. What is the best description design/build construction?
A. The owner contracts with a design/build entity, which is responsible for the project
B. The owner has the project designed, then a design/build entity takes it to completion
2
SUCCESS!
,Page 3 of 103
C. The design/build entity designs the project, then sends it to a General Contractor for
construction
D. The general contractor is only a part of the design/build entity for the construction phases of
the project - CORRECT ANSWER✔✔A
Question: 1. Open bidding is required on public projects because
A. They are funded by taxpayer's dollars
B. They require an invitation to bid
C. They are only available to certain contractors
D. They are funded by private officials - CORRECT ANSWER✔✔A
Question: 2. Identify the correct pairing of the most common procurement method and
selection criteria:
A. Design build and low bid selection
B. Design-bid-build and qualifications based selection
C. Design-bid-build and low bid selection
D. Design build and qualifications and prose selection - CORRECT ANSWER✔✔C
3
SUCCESS!
, Page 4 of 103
Question: 3. Which best describes the weighted criteria evaluation process?
A. Award the project based on high total points for qualitative and price components
B. Award the project based on low total points for qualitative and price components
C. Award the project based on low cost
D. Award the project based on highest qualitative score - CORRECT ANSWER✔✔A
Question: l. What is the name of the stone carvings dating back to the pyramids that contained
the first written regulations pertaining to construction, commonly referred to as the first known
building code?
a. Amon's Law
b. Rules of Osiris
c. Code of Hammurabi
d. Canon of Tutenkhamen - CORRECT ANSWER✔✔C
Question: 2. What is the role of the owner on a construction project?
a. To develop the final building plans, specifications, and construction details,
4
SUCCESS!
CM EXAM 1 NEWEST WITH 3 VERSIONS WITH
400 QUESTIONS AND ANSWERS JUST
RELEASED THIS YEAR
CM EXAM 1
Question: 1. Which is not a part of the three-legged stool of construction?
A. Cost
B. Efficiency
C. Quality
D. Time - CORRECT ANSWER✔✔B
Question: 2. Which of the following is the definition for project scope?
A. A set of guidelines that establishes the budget for the project
B. Sets the design specifications for the project as identified by the architect
C. Sets the parameters for the work and defines what work needs to be done
D. None of the above - CORRECT ANSWER✔✔C
1
SUCCESS!
,Page 2 of 103
Question: 3. Which of the following is NOT a Project Delivery method?
A. Agency CM
B. CM-at-Risk
C. Design-Bid-Build
D. Design-Build - CORRECT ANSWER✔✔A
Question: 4. Who determines what method of delivery is used on a project?
A. Architect
B. Engineer
C. General Contractor
D. Owner - CORRECT ANSWER✔✔D
Question: 5. What is the best description design/build construction?
A. The owner contracts with a design/build entity, which is responsible for the project
B. The owner has the project designed, then a design/build entity takes it to completion
2
SUCCESS!
,Page 3 of 103
C. The design/build entity designs the project, then sends it to a General Contractor for
construction
D. The general contractor is only a part of the design/build entity for the construction phases of
the project - CORRECT ANSWER✔✔A
Question: 1. Open bidding is required on public projects because
A. They are funded by taxpayer's dollars
B. They require an invitation to bid
C. They are only available to certain contractors
D. They are funded by private officials - CORRECT ANSWER✔✔A
Question: 2. Identify the correct pairing of the most common procurement method and
selection criteria:
A. Design build and low bid selection
B. Design-bid-build and qualifications based selection
C. Design-bid-build and low bid selection
D. Design build and qualifications and prose selection - CORRECT ANSWER✔✔C
3
SUCCESS!
, Page 4 of 103
Question: 3. Which best describes the weighted criteria evaluation process?
A. Award the project based on high total points for qualitative and price components
B. Award the project based on low total points for qualitative and price components
C. Award the project based on low cost
D. Award the project based on highest qualitative score - CORRECT ANSWER✔✔A
Question: l. What is the name of the stone carvings dating back to the pyramids that contained
the first written regulations pertaining to construction, commonly referred to as the first known
building code?
a. Amon's Law
b. Rules of Osiris
c. Code of Hammurabi
d. Canon of Tutenkhamen - CORRECT ANSWER✔✔C
Question: 2. What is the role of the owner on a construction project?
a. To develop the final building plans, specifications, and construction details,
4
SUCCESS!