Design-Bid-Build (DBB) - CORRECT ANSWER- linear, sequential process, A/E selected on
qualifications, GC selected on low price, design is fully completed without input from GC, A/E
acting in owner's interests, with a historically strong bond, process is well-established and
understood
construction manager at risk - CORRECT ANSWER- similar org structure to DBB, construction
manager selected by QBS or best value, contractor provides precon services, negotiated gmp
contracting approach, open book estimating process, potential to fast track project,
construction cost determined before design completed, potential issues over what is
reasonably inferable from gmp design documents
Design-Build - CORRECT ANSWER- The owner contracts with one entity (a person or firm) to
provide both design and construction services, designer and contractor have a direct
contractual relationship, selected by QBS or best value, wide spectrum of contracting
approaches and organizational structures, single point responsibility, owner does not manage
designer, owner exposure to claims is significantly reduced
engineer procure construct (epc) - CORRECT ANSWER- similar to design build, in industrial and
power generation sectors, systems and performance testing are central to scope, contractor
will typically perform engineering with its in-house staff, owner has need for single point
responsibility, contracts include plant and process performance guarantees, contract items
include performance and schedule liquidated damages and limitations of liability
,Project Delivery System - CORRECT ANSWER- How team members are organized, establishes
when parties engage, determines roles of parties, and determines sequence of design,
procurement, and construction (db, cmar, dbb)
Procurement Method - CORRECT ANSWER- how team members are selected (QBS, best value,
low price, sole source)
contracting approach - CORRECT ANSWER- how team members are paid (fp, gmp, cost
reimbursement, target price, unit price)
Multiple Prime Contracting - CORRECT ANSWER- owner contracts with multiple trade
contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate
the work
Integrated Project Delivery (IPD) - CORRECT ANSWER- multi-party agreement - all parties equal,
QBS procurement and target pricing contract approach, private sector use (limited at this time),
key: owner's ability to accept risk
public-private partnership (p3) - CORRECT ANSWER- Instead of government building and
maintaining major infrastructure (such as highway, water treatment plant), build and
maintenance is outsourced to a private company. Opposed by public sector unions. this is not
considered a delivery system but its underlying approaches are delivery systems and typically
use DB. multiple procurement and contracting approaches
shift left - CORRECT ANSWER- intense efforts to establish scope early in the process; drives early
team formation to include key trade subcontractors; can enable big decisions to be made early,
affect project outcomes at lowest cost, establish a need for co-location and collaboration, and
compress time during concurrent design and construction
, traditional design build - CORRECT ANSWER- typically two-phase best value procurement with
lump sum contract; owner defines project requirements and scope of prescriptive work; use of
performance-based technical requirements with limited prescriptive specifications
progressive design build - CORRECT ANSWER- design and price are progressively developed after
the design-builder is under contract; final project cost and schedule commitment is not
established as part of the selection process; two phases: preliminary services and final design
and construction services
criteria documents - CORRECT ANSWER- describe the end result
bridging documents - CORRECT ANSWER- prescribes how to achieve the end result
design bid build paradigm - CORRECT ANSWER- prior to bidding, owner undertakes a process to
design the project and all of its details to 100% complete plans and specs. the owner is
therefore responsible for success or failure of details of the design, and warrants the sufficiency
of design to the contractor. the owner is therefore liable to the contractor for any gaps
between plans and specifications and owner's requirements for project performance
design details responsibility - CORRECT ANSWER- the owner should define its performance
requirements and award the contract on the basis of preliminary design; this makes the design-
builder responsible for completing the design in accordance with the owner's performance
requirements. that also causes the design-builder to warrant the sufficiency of the design to
meet the owner's criteria and the sufficiency of the design to subcontractors/suppliers that
have no design responsibility
uniformat - CORRECT ANSWER- subdivides project by functional elements, focuses on systems
and assemblies, useful for preliminary information and early design phases, aligns with BIM
models and conceptual estimating