DBIA Practice Test – Design-Build Certification Exam Study Guide

Document preview thumbnail
Preview 3 out of 16 pages

Prepare for the DBIA (Design-Build Institute of America) Certification Exam with this comprehensive DBIA Practice Test and Study Guide. Review essential topics including design-build principles, project delivery methods, risk management, contract administration, and leadership best practices. Ideal for professionals pursuing the DBIA™ or Associate DBIA™ credential to enhance their expertise in integrated project delivery.

Content preview

DBIA Practice Test NEWEST 2025 COMPLETE QUESTIONS
AND CORRECT DETAILED ANSWERS (VERIFIED
ANSWERS) |ALREADY GRADED A+||BRAND NEW
VERSION!!




Design-Bid-Build (DBB) - CORRECT ANSWER- linear, sequential process, A/E selected on
qualifications, GC selected on low price, design is fully completed without input from GC, A/E
acting in owner's interests, with a historically strong bond, process is well-established and
understood



construction manager at risk - CORRECT ANSWER- similar org structure to DBB, construction
manager selected by QBS or best value, contractor provides precon services, negotiated gmp
contracting approach, open book estimating process, potential to fast track project,
construction cost determined before design completed, potential issues over what is
reasonably inferable from gmp design documents



Design-Build - CORRECT ANSWER- The owner contracts with one entity (a person or firm) to
provide both design and construction services, designer and contractor have a direct
contractual relationship, selected by QBS or best value, wide spectrum of contracting
approaches and organizational structures, single point responsibility, owner does not manage
designer, owner exposure to claims is significantly reduced



engineer procure construct (epc) - CORRECT ANSWER- similar to design build, in industrial and
power generation sectors, systems and performance testing are central to scope, contractor
will typically perform engineering with its in-house staff, owner has need for single point
responsibility, contracts include plant and process performance guarantees, contract items
include performance and schedule liquidated damages and limitations of liability

,Project Delivery System - CORRECT ANSWER- How team members are organized, establishes
when parties engage, determines roles of parties, and determines sequence of design,
procurement, and construction (db, cmar, dbb)



Procurement Method - CORRECT ANSWER- how team members are selected (QBS, best value,
low price, sole source)



contracting approach - CORRECT ANSWER- how team members are paid (fp, gmp, cost
reimbursement, target price, unit price)



Multiple Prime Contracting - CORRECT ANSWER- owner contracts with multiple trade
contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate
the work



Integrated Project Delivery (IPD) - CORRECT ANSWER- multi-party agreement - all parties equal,
QBS procurement and target pricing contract approach, private sector use (limited at this time),
key: owner's ability to accept risk



public-private partnership (p3) - CORRECT ANSWER- Instead of government building and
maintaining major infrastructure (such as highway, water treatment plant), build and
maintenance is outsourced to a private company. Opposed by public sector unions. this is not
considered a delivery system but its underlying approaches are delivery systems and typically
use DB. multiple procurement and contracting approaches



shift left - CORRECT ANSWER- intense efforts to establish scope early in the process; drives early
team formation to include key trade subcontractors; can enable big decisions to be made early,
affect project outcomes at lowest cost, establish a need for co-location and collaboration, and
compress time during concurrent design and construction

, traditional design build - CORRECT ANSWER- typically two-phase best value procurement with
lump sum contract; owner defines project requirements and scope of prescriptive work; use of
performance-based technical requirements with limited prescriptive specifications



progressive design build - CORRECT ANSWER- design and price are progressively developed after
the design-builder is under contract; final project cost and schedule commitment is not
established as part of the selection process; two phases: preliminary services and final design
and construction services



criteria documents - CORRECT ANSWER- describe the end result



bridging documents - CORRECT ANSWER- prescribes how to achieve the end result



design bid build paradigm - CORRECT ANSWER- prior to bidding, owner undertakes a process to
design the project and all of its details to 100% complete plans and specs. the owner is
therefore responsible for success or failure of details of the design, and warrants the sufficiency
of design to the contractor. the owner is therefore liable to the contractor for any gaps
between plans and specifications and owner's requirements for project performance



design details responsibility - CORRECT ANSWER- the owner should define its performance
requirements and award the contract on the basis of preliminary design; this makes the design-
builder responsible for completing the design in accordance with the owner's performance
requirements. that also causes the design-builder to warrant the sufficiency of the design to
meet the owner's criteria and the sufficiency of the design to subcontractors/suppliers that
have no design responsibility



uniformat - CORRECT ANSWER- subdivides project by functional elements, focuses on systems
and assemblies, useful for preliminary information and early design phases, aligns with BIM
models and conceptual estimating

Document information

Uploaded on
October 28, 2025
Number of pages
16
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$24.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
trustednurse
4.9
(2508)
Sold
985
Followers
416
Items
13331
Last sold
6 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”