CHFM study guide exam questions with
correct answers
A |project |estimator |is |developing |a |cost |estimate |for |construction |of |a |new |diagnostic |imaging
|wing. |The |projected |costs |are: |
Fixed |equipment |installation |charges |$700,000
Site |isolation |$50,000
Annual |utilities |$425,000
Construction |materials |$1,200,000
Portable |equipment |$900,000
Annual |depreciation |$275,000
What |are |the |expected |contractor |expenses? |- |CORRECT |ANSWER✔✔-1,600,000
Which |of |the |following |contribute |to |typical |general |contractor |fees:
1. |Permit |and |inspection |fees
,2. |General |conditions
3. |Overhead |and |profit
4. |Site |condition |assessment |fees |- |CORRECT |ANSWER✔✔-2, |3, |and |4
Demand |side |management |(DSM) |programs |are |developed |and |offered |to |organizations |by |
energy |providers |to |do |which |of |the |following |during |peak |service? |- |CORRECT |ANSWER✔✔-
Provide |emergency |energy |demand |sources
When |developing |a |preventive |maintenance |program, |a |facility |manager |should |ensure |that |
an |annual |test |is |conducted |on |every |required |battery-powered |lighting |system. |This |test |
should |be |run |for |NOT |less |than: |- |CORRECT |ANSWER✔✔-30 |seconds
In |existing |facilities, |doors |that |open |onto |exit |corridors |should |have |1-3/4 |inch |solid |bonded |
wood |core |or |be |of |construction |that |resists |fire |for |NOT |less |than: |- |CORRECT |ANSWER✔✔-
20 |minutes
Total |dissolved |solids |in |a |cooling |tower |are |regulated |by: |- |CORRECT |ANSWER✔✔-Variable |
speed |drive |fans
What |contracts |requires |a |schedule |of |values |when |negotiating? |- |CORRECT |ANSWER✔✔-
Guaranteed |maximum |price
A |project |has |a |budget |of |$6,600,000. |Planning |and |design |fees |are |estimated |at |$700,000 |and
|construction |expenses |are |estimated |at |$5,100,000. |What |is |the |amount |of |a |10% |
construction |contingency? |- |CORRECT |ANSWER✔✔-580,000
, The |Joint |Commission |standards |require |that |an |organization |develop |and |implement |a |policy |
to |prohibit |smoking |except |in |specified |circumstances. |The |standard |is |intended |to |reduce |
risks |of:
1. |Possible |adverse |effects |on |care, |treatment, |and |services |to |people |who |smoke
2. |Passive |smoke |to |others
3. |Fire
4. |False |alarms |- |CORRECT |ANSWER✔✔-2, |3, |and |4
When |planning |demolition, |construction, |or |renovation, |an |organization |selects |and |
implements |proper |controls |to |reduce |risk |and |minimize |the |impact |of |these |activities |on |
infection |control. |Which |of |the |following |are |proper |controls |within |the |construction |area:
1. |Providing |negative |air |machines
2. |Installing |dust |barriers
3. |Wet-mopping |the |floors
4. |Ensuring |debris-free |job |site |- |CORRECT |ANSWER✔✔-2, |3, |and |4
A |facility |is |installing |an |air |intake |for |a |medical |air |compressor. |What |is |the |minimum |heights, |
in |ft., |at |which |this |should |be |located |above |the |ground? |- |CORRECT |ANSWER✔✔-5
correct answers
A |project |estimator |is |developing |a |cost |estimate |for |construction |of |a |new |diagnostic |imaging
|wing. |The |projected |costs |are: |
Fixed |equipment |installation |charges |$700,000
Site |isolation |$50,000
Annual |utilities |$425,000
Construction |materials |$1,200,000
Portable |equipment |$900,000
Annual |depreciation |$275,000
What |are |the |expected |contractor |expenses? |- |CORRECT |ANSWER✔✔-1,600,000
Which |of |the |following |contribute |to |typical |general |contractor |fees:
1. |Permit |and |inspection |fees
,2. |General |conditions
3. |Overhead |and |profit
4. |Site |condition |assessment |fees |- |CORRECT |ANSWER✔✔-2, |3, |and |4
Demand |side |management |(DSM) |programs |are |developed |and |offered |to |organizations |by |
energy |providers |to |do |which |of |the |following |during |peak |service? |- |CORRECT |ANSWER✔✔-
Provide |emergency |energy |demand |sources
When |developing |a |preventive |maintenance |program, |a |facility |manager |should |ensure |that |
an |annual |test |is |conducted |on |every |required |battery-powered |lighting |system. |This |test |
should |be |run |for |NOT |less |than: |- |CORRECT |ANSWER✔✔-30 |seconds
In |existing |facilities, |doors |that |open |onto |exit |corridors |should |have |1-3/4 |inch |solid |bonded |
wood |core |or |be |of |construction |that |resists |fire |for |NOT |less |than: |- |CORRECT |ANSWER✔✔-
20 |minutes
Total |dissolved |solids |in |a |cooling |tower |are |regulated |by: |- |CORRECT |ANSWER✔✔-Variable |
speed |drive |fans
What |contracts |requires |a |schedule |of |values |when |negotiating? |- |CORRECT |ANSWER✔✔-
Guaranteed |maximum |price
A |project |has |a |budget |of |$6,600,000. |Planning |and |design |fees |are |estimated |at |$700,000 |and
|construction |expenses |are |estimated |at |$5,100,000. |What |is |the |amount |of |a |10% |
construction |contingency? |- |CORRECT |ANSWER✔✔-580,000
, The |Joint |Commission |standards |require |that |an |organization |develop |and |implement |a |policy |
to |prohibit |smoking |except |in |specified |circumstances. |The |standard |is |intended |to |reduce |
risks |of:
1. |Possible |adverse |effects |on |care, |treatment, |and |services |to |people |who |smoke
2. |Passive |smoke |to |others
3. |Fire
4. |False |alarms |- |CORRECT |ANSWER✔✔-2, |3, |and |4
When |planning |demolition, |construction, |or |renovation, |an |organization |selects |and |
implements |proper |controls |to |reduce |risk |and |minimize |the |impact |of |these |activities |on |
infection |control. |Which |of |the |following |are |proper |controls |within |the |construction |area:
1. |Providing |negative |air |machines
2. |Installing |dust |barriers
3. |Wet-mopping |the |floors
4. |Ensuring |debris-free |job |site |- |CORRECT |ANSWER✔✔-2, |3, |and |4
A |facility |is |installing |an |air |intake |for |a |medical |air |compressor. |What |is |the |minimum |heights, |
in |ft., |at |which |this |should |be |located |above |the |ground? |- |CORRECT |ANSWER✔✔-5