CONS 127 Sample Questions & Answers Solved
100% Correct.
Unilateral modifications are modifications signed only by the Government's contracting

officer.



You can process a unilateral modification when the change has no substantive effect on the

contractor or the Government, the change can be made unilaterally under a specific

contract term, or a contractor's agreement is not required.

Unilateral modifications are used to do the following:



Make administrative changes (e.g., correct a typo in the accounting line or change the address of

the payment office).



Issue change orders (FAR 52.243-4, Changes)



Make change authorized by other contract clauses (FAR 52-217-7, Options and FAR 52.242-14

Suspension of Work)



Issue termination notices

One of the most widely recognized uses of a unilateral modification is as a change order.



The following are some examples:

Changes Fixed Price, FAR 52.243-1

,Changes Cost Reimbursement, FAR 52.243-2

Changes Time and Materials or Labor Hours, FAR 52.243-3

Changes, FAR 52.243-4

Changes and Changed Conditions, FAR 52.243-5

For supplemental regulatory information about contract changes, please take a moment to

read FAR subpart 43.2.

According to FAR subpart 43.2, unilateral changes are accomplished by issuing written change

orders on Standard Form 30, Amendment of Solicitation, Modification of Contract SF 30, unless

otherwise provided.

Definitization means we are defining, or making definite, exactly what the contract terms

and conditions are: specifications, price, and other terms as necessary.

A bilateral modification is a modification signed by both contracting parties: the contracting

officer and the contractor. Bilateral modifications are also known as supplemental agreements

Bilateral modifications are used to:

Make negotiated equitable adjustments — contract modifications that are fair and

reasonable to both contracting parties —to the contract resulting from the issuance of a

change order.



Definitize — supplemental agreement reflecting the resulting equitable adjustment in

contract terms, prices or costs —letter contracts.



Reflect other agreements of the contracting parties modifying the terms of contracts.

,You are administering a firm-fixed price construction contract. The contracting officer's

technical representative (COTR) informs you that the customer wants the building materials

changed from brick to sandstone block.



You verify that the customer has the additional funds to cover the difference in materials cost.

Under the authority of clause 52.243-2, Changes - Fixed Price, you issue a unilateral

modification to the contract instructing the contractor to change the type of materials.



This same clause gives the contractor the right to request an equitable adjustment in the contract

price, to fairly reimburse him for the increased cost of the sandstone block. In accordance with

the clause, the contractor has 30 days to submit his request for equitable adjustment and to

submit documentation to support his new price.



Once you and the contractor have agreed on the increased price of the contract due to the

directed contract change, you then issue a bilateral modification (supplemental agreement) to

definitize the cost of the change.



The definitization of the contract change is issued as a supplemental agreement to the contract,

which is agreed to and signed by both parties.

Whatever the basis for a modification, the authority to process the modification is always

restricted to situations in which the Government receives adequate value in exchange for

an agreement to modify a contract; what we in contracting call consideration.

, In some instances, adequate consideration will reflect a factor trade off resulting in no

increase or decrease in price, as in a no-cost contract modification.

Modifications of letter contracts are written preliminary contractual instruments that authorize

the contractor to begin work immediately, but for which the cost or price and other contract

terms and applicable clauses have yet to be determined.



Modifications of letter contracts are subject to the same policies and procedures as modifications

of definitive contracts.

The steps for processing a modification are as follows:

Step 1a: Evaluate the contractor's request for proposed contract change.

Step 1b: Evaluate the Government's request for proposed contract change.

Step 2: Determine whether to make a modification to the contract.

Step 3: Determine whether to use a unilateral or bilateral modification.

Step 4a: Modify the contract using a unilateral modification.

Step 4b: Modify the contract using a bilateral modification.

Step 5: Document the contract file and distribute the modification.

The following screens will explain in detail each step of the modification process.

A contractor may request a contract modification when the reason for a modification falls into

one of these three categories:



Circumstances beyond the control of the contractor



Due to action by the contractor

Document information

Uploaded on
October 24, 2025
Number of pages
74
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$21.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
QUINTER
3.6
(73)
Sold
413
Followers
105
Items
40085
Last sold
5 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions