CEM 100 EXAM 2 QUESTIONS AND ANSWERS

Document preview thumbnail
Preview 2 out of 10 pages

CEM 100 EXAM 2 QUESTIONS AND ANSWERS

Content preview

CEM 100 EXAM 2 QUESTIONS AND
ANSWERS

To make certain that a contractor pays only the correct price to vendors and
subcontractors for goods and services received to date and to also make certain that
total payment does not exceed the purchase order or subcontract amount a ______
system must be established by the contractor - Answer- Progress payment

Concerning a WBS, a WBS allows hierarchical build-up of costs and schedule therefore
Cost and Schedule can be reported _____ of the WBS - Answer- only at mid-level

A _____ is a hierarchical (from general to specific) tree structure of deliverables and
tasks that need to be performed to complete a project - Answer- Work Breakdown
Structure

A _____ is a person or group of people who have a vested interest in the success of an
organization and the environment in which the organization operates - Answer-
Stakeholder

The lowest level of the WBS is the _____. The _____ contains a list of Tasks to be
Performed that form the basis for the Schedule - Answer- Work Package (WP)

What is a contract clause? - Answer- protects owner and/or the architect engineer by
transferring risk and uncertainty to the contractor

Is the contractor responsible for end results? Are they liable for the consequences of
design defects? - Answer- No

What is indemnification? - Answer- - Protects owners and architect-engineer from third
person liability
- construction contracts include indemnification or "hold-harmless" clauses

What is a hold-harmless clause? - Answer- requires that the contractor indemnify and
hold harmless the owner and architect-engineer, from all loss or expense by a reason of
liability imposed by law on them for damages because of bodily injury or damage to
property arising out of, or as a consequence of, the work

Limited form indemnification - Answer- holds owner and architect-engineer harmless
against claims caused solely by the negligence of the prime contractor or subcontractor

, intermediate-form indemnification - Answer- includes not only claims caused by
contractor or subcontractors but also in which the owner and/or architect-engineer may
be jointly responsible, regardless of degree of fault

Broad-form indemnification - Answer- Indemnifies the owner and/or architect-engineer
against all losses, even when the party indemnified is solely responsible for the loss

what is a complication of a subcontract? - Answer- if general contractor presents a
subcontract agreement for the subcontractor to sign that contains significant conditions
not set forth in the bidding documents or contract documents, it can be considered as a
counteroffer by the general contractor, and the bid of the subcontractor may not be
binding

Subcontract provisions - Answer- - similar to subcontract agreements in both form and
content
- pass-through clauses

What is a scope statement? - Answer- detailed description of work to be done by the
subcontractor. This should be included in the subcontract agreement

What is a no damage for delay clause? - Answer- In case of delay caused by general
contractor, the subcontractor's only remedy will be an extension of time to complete its
work

What is contract time? - Answer- contract documents state duration (# of days) in which
a contractor must satisfactorily complete all the requirements of the contract documents
- often uses the term calendar days

What is liquidated damages? - Answer- An assessment. Used in lieu of a determination
of the actual damages suffered

What are extensions of time? - Answer- occurrences that delay or add to the period of
time necessary to build the project

T or F: failure to complete a project in a certain amount of time is a breech in contract -
Answer- True

What is acceleration? - Answer- Owner's directing the prime contractor to accelerate its
performance of the work so as to complete the project at an earlier date than the current
rate work advancement will permit

What is differing site? - Answer- - a physical aspect of project or its site that differs
materially from that indicated by the contract documents

Document information

Uploaded on
October 21, 2025
Number of pages
10
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Scholarsstudyguide
3.8
(169)
Sold
838
Followers
475
Items
16317
Last sold
5 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions