Isom 300 - Test 1 Questions & Answers|| 2025 Latest Update|| Verified A+

Document preview thumbnail
Preview 2 out of 6 pages

What is a project? - ANSWERA temporary endeavor undertaken to create a unique product, service, or result. What are the main characteristics of a project? - ANSWER- an established objective - defined life span with a beginning and an end - usually, it has interdisciplinary involvement -typically doing something new - specific time, cost, and performance requirements

Content preview

ISOM 300 - TEST 1 QUESTIONS &
ANSWERS|| 2025 LATEST UPDATE||
VERIFIED A+
What is a project? - ANSWERA temporary endeavor undertaken to create a unique
product, service, or result.

What are the main characteristics of a project? - ANSWER- an established objective
- defined life span with a beginning and an end
- usually, it has interdisciplinary involvement
-typically doing something new
- specific time, cost, and performance requirements

what are the 5 main project process groups (also known as project phases)? -
ANSWER- Initiating
- Planning
- Executing
- Monitoring
- Closing

Scope Statement - ANSWERPlanning process

Project Charter - ANSWERInitiating process

Analysis of project progress comparing cost baseline vs actual expenditure -
ANSWERMonitoring process

Stakeholder register - ANSWERInitiating process

What are the three groups/types of skills a Project manager should have? - ANSWER-
technical project management
- leadership
- strategic & business management

What is an Agile project management approach? - ANSWER-Deliver to customer ASAP
-Iterative: allows feedback on unfinished work
- Incremental: create deliverables throughout

What is a traditional project management approach? - ANSWER-Plan project in detail in
the beginning
-Deliver entire project to customer at end

, What is the difference between traditional and agile approach? - ANSWERAgile wants
to get product to customer as fast as they can. Traditional approach allows the project
to be fully completed before delivering to the customer.

What are the 3 organizational structures? - ANSWERfunctional, project, matrix

In which organizational structure does the project manager have a higher level of
authority? - ANSWERproject organization

In the matrix organizational structure does the functional manager have authority? Does
the project manager have authority? - ANSWERyes, and no

This company requires the independent development of each project. However, for an
efficient work the company should have different departments that are managed by their
own functional managers. What is the organizational structure of this company? -
ANSWERmatrix organization

Stakeholder - ANSWERIndividuals and organizations that are actively involved in a
project, or whose interests may be positively or negatively affected as a result of project
execution or completion. They may also exert influence over the project and its results.


John is the project manager of a project that has a specific completion date. After a
discussion with top management, the decisions made showed that while the completion
date is important, the cost is more important and a slip in the finish time would not be
acceptable if required to meet the cost targets. In this case, what would be the
classification in the priority matrix for the time and cost? - ANSWERtime = accept
cost = constrain

What is the objective of the communications plan? - ANSWER- stakeholder
identification and analysis
- communications vehicle

RACI Matrix - what does it mean to be responsible, accountable, consulted, and
informed? - ANSWER-R= responsible, those who do the work
-A=accountable, the one who has final approving authority
-C=consulted, those whose opinions are sought, subject matter experts
-I=informed, those who are kept up to date on progress

In your risk management plan what is the name of the document/form you use to
identify and classify the risks? - ANSWERrisk register

WBS (Work Breakdown Structure) - ANSWERlist of tasks to be completed

Document information

Uploaded on
October 4, 2025
Number of pages
6
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
shantelleG
4.1
(119)
Sold
665
Followers
369
Items
18459
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions