A contractor does not notify a change of address and so does not receive a timely
Notice of Renewal. Who is responsible when the contractor does not renew his license
on time?
a) USBC
b)OSHA
c)The licensee Contractor
d)DPOR -ANSThe licensee Contractor
A designated employee should be?
a)any full time worker
b) at least 18 years old, full time employee, has passed required examination
c) at least 18 years old and 5 years experienced for Class A
d) the owner -ANSat least 18 years old, full time employee, has passed required
examination
What is the initial recovery fund fee?
a) $200
b) $50
c) $0
d) $25 -ANS$ 25
If a contractor earns more than $__________ per year, then the contractor requires a
Class A license
a) $120,000
b) $7,500
c) $750,000
d) $150,000 -ANS$750,000
If a contract awards more than $________ per payment, the contractor requires a Class
A license
a) $120,000
, b) $7,500
c) $750,000
d) $150,000 -ANS$120,000
An erosion control conservation plan needs to be approved within ______ days.
a) 18 days
b) 60 days
c) 29 days
d) 45 days -ANS45 days
Where do you go to file an appeal of a violation to the USBC provisions?
a) none because there is no appeal
b) to OSHA
c) to the court
d) to the BBCA -ANSto the BBCA
A contractor is required to submit a renewal within ______ days of the expiration date?
a) 20
b)30
c) 50
d) 180 -ANS30
Who can file a complaint against a contractor>
a) owner
b) DPOR
c) any person
d) only the other part of the contract -ANSany person
What is required when changing the form of entity from a sole proprietorship to
corporation
a) nothing because the licensee is the same
b) a new license
c) pay the fee only
d) take a new exam -ANSa new license
What is the maximum fund allowed for a single tractor (per biennium)?
a) $20,000
b) $7,500
c) $40,000
d) $400,000 -ANS$40,000
QUESTIONS EXAM WITH COMPLETE
SOLUTIONS
A contractor does not notify a change of address and so does not receive a timely
Notice of Renewal. Who is responsible when the contractor does not renew his license
on time?
a) USBC
b)OSHA
c)The licensee Contractor
d)DPOR -ANSThe licensee Contractor
A designated employee should be?
a)any full time worker
b) at least 18 years old, full time employee, has passed required examination
c) at least 18 years old and 5 years experienced for Class A
d) the owner -ANSat least 18 years old, full time employee, has passed required
examination
What is the initial recovery fund fee?
a) $200
b) $50
c) $0
d) $25 -ANS$ 25
If a contractor earns more than $__________ per year, then the contractor requires a
Class A license
a) $120,000
b) $7,500
c) $750,000
d) $150,000 -ANS$750,000
If a contract awards more than $________ per payment, the contractor requires a Class
A license
a) $120,000
, b) $7,500
c) $750,000
d) $150,000 -ANS$120,000
An erosion control conservation plan needs to be approved within ______ days.
a) 18 days
b) 60 days
c) 29 days
d) 45 days -ANS45 days
Where do you go to file an appeal of a violation to the USBC provisions?
a) none because there is no appeal
b) to OSHA
c) to the court
d) to the BBCA -ANSto the BBCA
A contractor is required to submit a renewal within ______ days of the expiration date?
a) 20
b)30
c) 50
d) 180 -ANS30
Who can file a complaint against a contractor>
a) owner
b) DPOR
c) any person
d) only the other part of the contract -ANSany person
What is required when changing the form of entity from a sole proprietorship to
corporation
a) nothing because the licensee is the same
b) a new license
c) pay the fee only
d) take a new exam -ANSa new license
What is the maximum fund allowed for a single tractor (per biennium)?
a) $20,000
b) $7,500
c) $40,000
d) $400,000 -ANS$40,000