EXAM WITH FREQUENTLY TESTED QUESTIONS and
correct ANSWERS|ALREADY A
GRADED|GUARANTEED PASS|LATEST UPDATE
2025.
Which of these is NOT part of the "sociocultural dimension" of project management?
a. Managing customer expectations
b. Leadership
c. Resource allocation
d. Dealing with politics
e. Negotiation - CORRECT ANSWER- c. Resource allocation
Any project life cycle is made up of stages. The project's schedule and budget will be
determined in the ___________ stage of the project life cycle.
a. planning
b. defining
c. executing
,d. closing
e. conceptual - CORRECT ANSWER- a. planning
Training the customer, releasing staff and resources occurs in the ________ stage of project life
cycle.
a. defining
b. planning
c. conceptual
d. closing
e. executing - CORRECT ANSWER- d. closing
A series of coordinated, related, multiple projects that continue over an extended time period
and are intended to achieve a goal is known as a
a. Campaign.
b. Strategy.
c. Venture.
d. Program.
e. Crusade. - CORRECT ANSWER- d. program
An increase in the complexity of projects, because projects typically include the latest advances,
can be the result of a growth in new __________.
a. services
,b. products and services
c. products
d. processes
e. knowledge - CORRECT ANSWER- e. knowledge
Which of the following is NOT true about project management?
a. It is not limited to the private sector.
b. Many opportunities are available for individuals interested in this career path.
c. It focuses primarily on technical processes.
d. It is a set of tools.
e. It improves one's ability to plan, implement and manage activities to accomplish specific
organizational objectives - CORRECT ANSWER- c. It focuses primarily on technical processes
In which stage of the project life cycle is the project's schedule and budget determined?
a. Closing
b. Identifying
c. Planning
d. Defining
e. Executing - CORRECT ANSWER- c. planning
Project management is not limited to the __________ sector.
a. private
, b. international
c. universal
d. business and government
e. global - CORRECT ANSWER- a. private
Which of the following represents the correct order of stages within the project life cycle?
a. Defining, Planning, Executing, Closing
b. Planning, Defining, Closing, Executing
c. Executing, Defining, Planning, Closing
d. Planning, Defining, Executing, Closing
e. Closing, Planning, Defining, Executing - CORRECT ANSWER- a. Defining, Planning, Executing,
Closing
A project life cycle
a. must be dogmatically followed.
b. will always have a phase called 'visioning'.
c. reduces the amount of planning necessary.
d. can vary based on the industry.
e. will only ever consist of four phases. - CORRECT ANSWER- d. can vary based on the industry.
A project does not include
a. repetitive, same or similar work.