ENCE 325 Exam 2025 The widening of a state highway is an example of which sector of the construction industry? - ANS-Infrastructure Specialty trade contractors are typically hired on the job by which of the following? - ANS-The contractor A construction project is characterized by the following? - ANS-It results in deliverables, it is unique, it uses resources (DUR) In which of the following stages does the contractor have the major responsibility to coordinate all necessary tasks associated with that stage? - ANS-Close-out Which member of the contractor's team is responsible for the day-to-day production activities on the jobsite? - ANS-The superintendent The residential sector of the industry is characterized by which of the following? - ANS Projects are fairly low tech What is the major rating system for green buildings - ANS-LEED During the start-up and mobilization stage the following activities occur? - ANS-The contractor moves onto the jobsite The Owner is responsible for the project feasibility stage. - ANS-True 3 outcomes of the bidding and award stage - ANS-bid submittals by contractors, bid package , award of construction contract A design-build delivery method typically results in the owner having one contract with the architect and another contract with the contractor. - ANS-False The owner will decide which of the following as a result of the feasibility stage - ANS Move forward with project, abandon the project, adjust the scope, budget, and/or schedule Project design typically occurs in three distinct phases Schematic Design , Design Development , and Construction Documents . Answer in the order of design phase progression. - ANS-Schematic Design, Design Development , Construction Documents ENCE 325 ENCE 325 An owner is considering building a 120 unit housing development on the outskirts of town. What would you refer to in determining if livestock would be allowed as part of the property development? - ANS-Zoning Ordinance Private owners may prefer to negotiate a fixed price with a contractor. In that situation, the delivery method is called - ANS-Design Negotiate Build (DNB) In an agency construction management (agency CM) delivery method, the CM is financially responsible and self-performs work. - ANS-False The primary technology enabler for the Integrated Project Delivery (IPD) method is - ANS-Building Information Modeling (BIM) . The primary advantages of the Design-Bid-Build delivery method include which of the following (3) - ANS-Competitively Bid , Known upfront cost , Most familiar to all parties For typical projects that are competitively bid, the process is fairly consistent and includes five key steps. Which of the following is NOT one these steps. (4) - ANS Architect analyzes bids and awards contract; Architect completes bid package , Owner solicits bids , Contractors review bid information , Contractors develop and submit bids Integrity of the bidding process is important to the industry in protecting contractor's bid submissions in a competitive environment. Trade secrets refers to maintaining the confidentiality of Contractor's bid estimate. - ANS-True There is a unique difference between open or closed projects during the bidding process. For most publicly funded projects, open bidding (or allowing any qualified contractor to bid) is the norm. - ANS-True A "responsible" bidder is one who meets all the bidding requirements outlined in the bid package. - ANS-False Contractors consider many factors when deciding whether to bid on a job. These include which of the following? Select all of the correct answers. (4) - ANS-Location of the job, Time frame and liquidated damages, type of contract The three primary types of surety bonds include which of the following. Select all of the correct answers. - ANS-Bid bonds , performance bonds, payment bonds An Owner estimate of project costs is the same as the Contractor estimate. - ANS-False Which of the following are considerations when developing a project construction estimate? (L, M, S, T) - ANS-Location of the Project, Market Conditions, Schedule and Time Frame Value Engineering is not the same as cost cutting. - ANS-True ENCE 325 ENCE 325 An owner is interested in building a 50,000 square foot (SF) office building. He/She develops a cost estimate based on cost per SF using industry references such as RS Means. This is an example of which type of estimate. - ANS-Preliminary Estimate Project costs are generally identified in two categories - direct and indirect. Direct costs include which of the following? 3 - ANS-Labor, Materials, Equipment The Davis-Bacon Act is important in the estimating process to determine which of the following of the cost categories? - ANS-Labor What are the primary ingredients of a contract? - ANS-Mutual Agreement, Capacity, Consideration, Lawfulness From an Owner's perspective, a cost plus fee contract is the riskiest of all the types of contracts. - ANS-True One way to reduce Owner's risk is to have a cap on the contract cost of a project. This is an example of which type of contract? - ANS-Cost Plus with a GMP According to Dykstra, what issues impact the choice of a contract? - ANS-The Project's Delivery Method, Risk Allocation, The Quality of Design Information The key to mutual agreement is that all parties agree to exactly what is written in the contract documents. - ANS-True The following is an example of which type of contract? A contractor bids a fixed unit price and at the completion of work is paid based on the actual quantities. - ANS-Unit Price Contract Documents include many key components - ANS-General Conditions, agreement, supplementary conditions, drawings & specs Specifications complement drawings by answering several key information requirements. Select all of the following applicable areas that Specifications address. (S, Q, IR) - ANS-Submittals, Quality of material and products & quality assurance, Special installation requirements General conditions are standards that can be used on multiple projects and are provided with the agreement. General conditions outline and specify many key provisions, including which of the following? - ANS-Outline broad rights and responsibilities of the parties, Outline terms for making changes to the work, Provide guidance for dealing with disputes or delays , Specify the procedures for contractor payment ENCE 325 ENCE 325 The agreement is one of the documents that make up a contract and is sometimes referred to as the contract because it includes by reference all the other documents. Select all of the following applicable components of the agreement. - ANS-Address of the project and brief description of the work, List of documents referenced by the agreement, Time for completion & contractor exclusions The widening of a state highway is an example of which sector of the construction industry? - ANS-Infrastructure Specialty trade contractors are typically hired on the job by which of the following? - ANS-The contractor A construction project is characterized by the following? - ANS-It results in deliverables, it is unique, it uses resources (DUR) In which of the following stages does the contractor have the major responsibility to coordinate all necessary tasks associated with that stage? - ANS-Close-out Which member of the contractor's team is responsible for the day-to-day production activities on the jobsite? - ANS-The superintendent The residential sector of the industry is characterized by which of the following? - ANS Projects are fairly low tech What is the major rating system for green buildings - ANS-LEED During the start-up and mobilization stage the following activities occur? - ANS-The contractor moves onto the jobsite The Owner is responsible for the project feasibility stage. - ANS-True 3 outcomes of the bidding and award stage - ANS-bid submittals by contractors, bid package , award of construction contract A design-build delivery method typically results in the owner having one contract with the architect and another contract with the contractor. - ANS-False The owner will decide which of the following as a result of the feasibility stage - ANS Move forward with project, abandon the project, adjust the scope, budget, and/or schedule Project design typically occurs in three distinct phases Schematic Design , Design Development , and Construction Documents . Answer in the order of design phase progression. - ANS-Schematic Design, Design Development , Construction Documents ENCE 325 ENCE 325 An owner is considering building a 120 unit housing development on the outskirts of town. What would you refer to in determining if livestock would be allowed as part of the property development? - ANS-Zoning Ordinance Private owners may prefer to negotiate a fixed price with a contractor. In that situation, the delivery method is called - ANS-Design Negotiate Build (DNB) In an agency construction management (agency CM) delivery method, the CM is financially responsible and self-performs work. - ANS-False The primary technology enabler for the Integrated Project Delivery (IPD) method is - ANS-Building Information Modeling (BIM) . The primary advantages of the Design-Bid-Build delivery method include which of the following (3) - ANS-Competitively Bid , Known upfront cost , Most familiar to all parties For typical projects that are competitively bid, the process is fairly consistent and includes five key steps. Which of the following is NOT one these steps. (4) - ANS Architect analyzes bids and awards contract; Architect completes bid package , Owner solicits bids , Contractors review bid information , Contractors develop and submit bids Integrity of the bidding process is important to the industry in protecting contractor's bid submissions in a competitive environment. Trade secrets refers to maintaining the confidentiality of Contractor's bid estimate. - ANS-True There is a unique difference between open or closed projects during the bidding process. For most publicly funded projects, open bidding (or allowing any qualified contractor to bid) is the norm. - ANS-True A "responsible" bidder is one who meets all the bidding requirements outlined in the bid package. - ANS-False Contractors consider many factors when deciding whether to bid on a job. These include which of the following? Select all of the correct answers. (4) - ANS-Location of the job, Time frame and liquidated damages, type of contract The three primary types of surety bonds include which of the following. Select all of the correct answers. - ANS-Bid bonds , performance bonds, payment bonds An Owner estimate of project costs is the same as the Contractor estimate. - ANS-False Which of the following are considerations when developing a project construction estimate? (L, M, S, T) - ANS-Location of the Project, Market Conditions, Schedule and Time Frame Value Engineering is not the same as cost cutting. - ANS-True ENCE 325 ENCE 325 An owner is interested in building a 50,000 square foot (SF) office building. He/She develops a cost estimate based on cost per SF using industry references such as RS Means. This is an example of which type of estimate. - ANS-Preliminary Estimate Project costs are generally identified in two categories - direct and indirect. Direct costs include which of the following? 3 - ANS-Labor, Materials, Equipment The Davis-Bacon Act is important in the estimating process to determine which of the following of the cost categories? - ANS-Labor What are the primary ingredients of a contract? - ANS-Mutual Agreement, Capacity, Consideration, Lawfulness From an Owner's perspective, a cost plus fee contract is the riskiest of all the types of contracts. - ANS-True One way to reduce Owner's risk is to have a cap on the contract cost of a project. This is an example of which type of contract? - ANS-Cost Plus with a GMP According to Dykstra, what issues impact the choice of a contract? - ANS-The Project's Delivery Method, Risk Allocation, The Quality of Design Information The key to mutual agreement is that all parties agree to exactly what is written in the contract documents. - ANS-True The following is an example of which type of contract? A contractor bids a fixed unit price and at the completion of work is paid based on the actual quantities. - ANS-Unit Price Contract Documents include many key components - ANS-General Conditions, agreement, supplementary conditions, drawings & specs Specifications complement drawings by answering several key information requirements. Select all of the following applicable areas that Specifications address. (S, Q, IR) - ANS-Submittals, Quality of material and products & quality assurance, Special installation requirements General conditions are standards that can be used on multiple projects and are provided with the agreement. General conditions outline and specify many key provisions, including which of the following? - ANS-Outline broad rights and responsibilities of the parties, Outline terms for making changes to the work, Provide guidance for dealing with disputes or delays , Specify the procedures for contractor payment ENCE 325 The agreement is one of the documents that make up a contract and is sometimes referred to as the contract because it includes by reference all the other documents. Select all of the following applicable components of the agreement. - ANS-Address of the project and brief description of the work, List of documents ref

Content preview

ENCE 325




ENCE 325 Exam 2025

The widening of a state highway is an example of which sector of the construction
industry? - ANS-Infrastructure

Specialty trade contractors are typically hired on the job by which of the following? -
ANS-The contractor

A construction project is characterized by the following? - ANS-It results in deliverables,
it is unique, it uses resources (DUR)

In which of the following stages does the contractor have the major responsibility to
coordinate all necessary tasks associated with that stage? - ANS-Close-out

Which member of the contractor's team is responsible for the day-to-day production
activities on the jobsite? - ANS-The superintendent

The residential sector of the industry is characterized by which of the following? - ANS-
Projects are fairly low tech

What is the major rating system for green buildings - ANS-LEED

During the start-up and mobilization stage the following activities occur? - ANS-The
contractor moves onto the jobsite

The Owner is responsible for the project feasibility stage. - ANS-True

3 outcomes of the bidding and award stage - ANS-bid submittals by contractors, bid
package , award of construction contract

A design-build delivery method typically results in the owner having one contract with
the architect and another contract with the contractor. - ANS-False

The owner will decide which of the following as a result of the feasibility stage - ANS-
Move forward with project, abandon the project, adjust the scope, budget, and/or
schedule

Project design typically occurs in three distinct phases Schematic Design , Design
Development , and Construction Documents . Answer in the order of design phase
progression. - ANS-Schematic Design, Design Development , Construction Documents



ENCE 325

, ENCE 325


An owner is considering building a 120 unit housing development on the outskirts of
town. What would you refer to in determining if livestock would be allowed as part of the
property development? - ANS-Zoning Ordinance

Private owners may prefer to negotiate a fixed price with a contractor. In that situation,
the delivery method is called - ANS-Design Negotiate Build (DNB)

In an agency construction management (agency CM) delivery method, the CM is
financially responsible and self-performs work. - ANS-False

The primary technology enabler for the Integrated Project Delivery (IPD) method is -
ANS-Building Information Modeling (BIM) .

The primary advantages of the Design-Bid-Build delivery method include which of the
following (3) - ANS-Competitively Bid , Known upfront cost , Most familiar to all parties

For typical projects that are competitively bid, the process is fairly consistent and
includes five key steps. Which of the following is NOT one these steps. (4) - ANS-
Architect analyzes bids and awards contract; Architect completes bid package , Owner
solicits bids , Contractors review bid information , Contractors develop and submit bids

Integrity of the bidding process is important to the industry in protecting contractor's bid
submissions in a competitive environment. Trade secrets refers to maintaining the
confidentiality of Contractor's bid estimate. - ANS-True

There is a unique difference between open or closed projects during the bidding
process. For most publicly funded projects, open bidding (or allowing any qualified
contractor to bid) is the norm. - ANS-True

A "responsible" bidder is one who meets all the bidding requirements outlined in the bid
package. - ANS-False

Contractors consider many factors when deciding whether to bid on a job. These
include which of the following? Select all of the correct answers. (4) - ANS-Location of
the job, Time frame and liquidated damages, type of contract

The three primary types of surety bonds include which of the following. Select all of the
correct answers. - ANS-Bid bonds , performance bonds, payment bonds

An Owner estimate of project costs is the same as the Contractor estimate. - ANS-False

Which of the following are considerations when developing a project construction
estimate? (L, M, S, T) - ANS-Location of the Project, Market Conditions, Schedule and
Time Frame

Value Engineering is not the same as cost cutting. - ANS-True

ENCE 325

Document information

Uploaded on
September 29, 2025
Number of pages
7
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
AlexScorer
2.5
(2)
Sold
11
Followers
0
Items
1800
Last sold
2 weeks ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions