COSC 475 FINAL STUDY GUIDE

Content preview

COSC 475 FINAL STUDY GUIDE

Activity - Answer -A task or process to be accomplished in a set period of time as part
of working toward a larger project goal. An **** can be assigned to a resource(s) and
have an associated cost. **** are ordered with logic links.

Actual Cost - Answer -The real amount paid of incurred for labor or materials.

Bar Chart - Answer -A chart on which activities are represented by Bars. The Bars
length is represented by the activity Duration, and is lined-up on a X-axis time scale.

Base Line - Answer -A set of dates and costs frozen at the start of the project and used
as a basis for performance evaluation as the project progresses.

Budgeted Cost - Answer -The amount planned ahead and placed aside to execute an
activity or an entire project from start to finish.

Cost Breakdown Structure (CBS) - Answer -A breakdown of the project into cost
elements for cost control planning. A **** will deconstruct a project into various cost
elements or types such as area, phase, discipline, or materials.

Critical Activity - Answer -An activity that is on the project's critical path.

Critical Path - Answer -The sequence of network activities which add up to the longest
overall duration. This determines the shortest time possible to complete the project.

Date Constraint - Answer -A date restriction imposed on an activity's start or finish date
in scheduling software. Applying a **** will swap the computed date to a date imposed
by the user. Often used to impose deadlines or to delay activities in a schedule

Direct Labor - Answer -(1) Labor which can be directly related/allocated to the output of
a productive account or cost center, compared with indirect labor which is not directly
related to output. (2) Labor employed directly by owner or main contractor, as opposed
to sub-contract labor

Duration - Answer -The number of calendar periods it takes (or is estimated to take)
from the time the execution of an element starts to the moment it is completed.

Estimate - Answer -Evaluation of expected quantities, time and man-hours, with
allowances and provisions for expected unknowns.

Estimated Cost - Answer -An approximated cost derived through a cost estimation
technique such as using historical or empirical methods.

, Float - Answer -**** the amount of time that an activity in a project network can be
delayed without causing a delay to: subsequent tasks (free ****) or the project
completion date (total ****)

Indirects - Answer -**** costs are costs that are not directly accountable to an activity or
work package. **** costs may be either fixed or variable. **** costs include
administration and personnel. These are those costs which are not directly related to
production. Some **** costs may be overhead. But some overhead costs can be directly
attributed to a project and are direct costs.

Lost Time - Answer -Productive time lost because of inclement weather, labor
problems, equipment failure or other cause.

Planning - Answer -Project **** is part of project management, which relates to the use
of schedules such as Gantt charts to plan and subsequently report progress within the
project environment. Initially, the project scope is defined and the appropriate methods
for completing the project are determined.

Schedule - Answer -A **** is a listing of a project's milestones, activities, and
deliverables, usually ordered with intended start and finish dates. Those items are often
estimated in terms of resource allocation, budget and duration, linked by dependencies
and scheduled events.

Target Date - Answer -A fixed activity due date or deadline.

Work Package - Answer -A **** **** is a subset of a project that can be assigned to a
specific part for execution. Because of the similarity, **** **** are often misidentified as
projects.

Activity Relationship - Answer -An ordered link between activities representing the
order of execution. The **** types are:
FS - Finish to Start
SS - Start to Start
FF - Finish to Finish
SF - Start to Finish

Backward Pass (Backward Plan) - Answer -Critical path calculation process which
having calculated earliest date for activities on the network. Works **** to find activities
latest start and finish dates/float.

Change Estimate - Answer -An Estimate evaluating a potential change to a project.
Often the estimate focuses on Cost, Schedule and Resource changes.

Early Start - Answer -The earliest time an activity can start within the logic and imposed
targets in the network

Document information

Uploaded on
September 23, 2025
Number of pages
6
Written in
2025/2026
Type
Other
Person
Unknown
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA
3.8
(376)
Sold
2221
Followers
1450
Items
62671
Last sold
1 day ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions