When is the initial pressure test conducted, by a medical gas
installer, on a nitrous oxide system? - Correct Answers
✅After blowdown of a distribution piping
In those portions of systems intended to handle oxygen at
pressures greater than 350 psi the interconnecting hose shall
NOT contain ________ materials? - Correct Answers
✅Polymeric
In a Category 1 Dental and Gas Vacuum Piping system, which
of the following is an NFPA 99 requirement for the labeling of
pipes? - Correct Answers ✅Color coding & non-standard
pressure
Which of the following treatments shall be performed before
brazing cut ends of a tube to be installed in a medical gas
piping system? - Correct Answers ✅Cut ends shall be
rolled smooth or deburred
Manifolds for gas cylinders shall actuate a(an) _______ signal
and shall activate an indicator at all _______ alarm panels to
indicate when or just before changeover from one header to
the other. - Correct Answers ✅Local, master
,Med Gas Study Guide Exam Questions
and Answers (Most Recent Version,
Complete Study Material)
In a non-anesthetizing area, on which side of a zone valve
shall the pressure/vacuum sensor be located? - Correct
Answers ✅Station outlet/inlet
What is the purpose of using an oxygen analyzer during the
piping purge prior to brazing? - Correct Answers ✅Assure
that all ambient air has been removed from the pipeline
A medical gas master or area alarm panel shall be set to
actuate a(an) _____ indicator when the communication with
an alarm-initiating device is disconnected. - Correct
Answers ✅Audible and visual
When an EOSC becomes the temporary supply source, a
facility will monitor the system by use of which of the
following? - Correct Answers ✅Providing four connection
points to both master alarms
Which of the following conditions must be met where medical
gas and vacuum systems are installed by non-certified
personnel? - Correct Answers ✅installation by anyone
other than 6010 certified personnel is NOT permitted
Which of the following systems shall NOT be permitted to be
located in an outdoor enclosure? - Correct Answers
✅Medical air compressor supply sources
,Med Gas Study Guide Exam Questions
and Answers (Most Recent Version,
Complete Study Material)
Metallic flexible joints are being used in the pipeline for
vibration control. Which of the following is NOT required of
such joints? - Correct Answers ✅suitable for service at 150
psig or above
who shall witness the installer-performed standing vacuum
test? - Correct Answers ✅the authority having jurisdiction,
or its designee
the medical air compressor intake shall be located a
minimum of how many feet from any exhaust or plumbing
vents? - Correct Answers ✅25 feet
the gas produced by evaporation from the secondary header
in a cryogenic liquid cylinder system shall enter the supply
system ________ of the final line regulator. - Correct Answers
✅upstream
with the approval of the Authority Having Jurisdiction, in
which areas shall the zone valves be permitted to be secured
to prevent inappropriate access? - Correct Answers
✅pediatric
, Med Gas Study Guide Exam Questions
and Answers (Most Recent Version,
Complete Study Material)
factory installed inlet tubes on station outlets shall be NOT
less than __________with 0.3 inch minimum inside diameter. -
Correct Answers ✅NPS 1/4, 3/8 in. O.D.
which of these operations would not breach the vacuum
system? - Correct Answers ✅testing a system component
with a leak detector solution
except for valves in zone valve boxes, all valves shall be
located in secured areas such as locked pipe chases, or be
__________. - Correct Answers ✅latched or locked in
operation position
medical gas Central Supply systems are NOT permitted to be
located where? - Correct Answers ✅in an unlocked location
fittings, valves, and other components for field-installed
positive pressure distribution systems shall be ________ until
prepared for installation. - Correct Answers ✅delivered
sealed, labeled, and kept sealed
vacuum piping for __________ shall be connected separately
from the medical surgical system directly to the receiver tank
through its own isolation valve and fluid trap located at the
receiver. - Correct Answers ✅a teaching laboratory
and Answers (Most Recent Version,
Complete Study Material)
When is the initial pressure test conducted, by a medical gas
installer, on a nitrous oxide system? - Correct Answers
✅After blowdown of a distribution piping
In those portions of systems intended to handle oxygen at
pressures greater than 350 psi the interconnecting hose shall
NOT contain ________ materials? - Correct Answers
✅Polymeric
In a Category 1 Dental and Gas Vacuum Piping system, which
of the following is an NFPA 99 requirement for the labeling of
pipes? - Correct Answers ✅Color coding & non-standard
pressure
Which of the following treatments shall be performed before
brazing cut ends of a tube to be installed in a medical gas
piping system? - Correct Answers ✅Cut ends shall be
rolled smooth or deburred
Manifolds for gas cylinders shall actuate a(an) _______ signal
and shall activate an indicator at all _______ alarm panels to
indicate when or just before changeover from one header to
the other. - Correct Answers ✅Local, master
,Med Gas Study Guide Exam Questions
and Answers (Most Recent Version,
Complete Study Material)
In a non-anesthetizing area, on which side of a zone valve
shall the pressure/vacuum sensor be located? - Correct
Answers ✅Station outlet/inlet
What is the purpose of using an oxygen analyzer during the
piping purge prior to brazing? - Correct Answers ✅Assure
that all ambient air has been removed from the pipeline
A medical gas master or area alarm panel shall be set to
actuate a(an) _____ indicator when the communication with
an alarm-initiating device is disconnected. - Correct
Answers ✅Audible and visual
When an EOSC becomes the temporary supply source, a
facility will monitor the system by use of which of the
following? - Correct Answers ✅Providing four connection
points to both master alarms
Which of the following conditions must be met where medical
gas and vacuum systems are installed by non-certified
personnel? - Correct Answers ✅installation by anyone
other than 6010 certified personnel is NOT permitted
Which of the following systems shall NOT be permitted to be
located in an outdoor enclosure? - Correct Answers
✅Medical air compressor supply sources
,Med Gas Study Guide Exam Questions
and Answers (Most Recent Version,
Complete Study Material)
Metallic flexible joints are being used in the pipeline for
vibration control. Which of the following is NOT required of
such joints? - Correct Answers ✅suitable for service at 150
psig or above
who shall witness the installer-performed standing vacuum
test? - Correct Answers ✅the authority having jurisdiction,
or its designee
the medical air compressor intake shall be located a
minimum of how many feet from any exhaust or plumbing
vents? - Correct Answers ✅25 feet
the gas produced by evaporation from the secondary header
in a cryogenic liquid cylinder system shall enter the supply
system ________ of the final line regulator. - Correct Answers
✅upstream
with the approval of the Authority Having Jurisdiction, in
which areas shall the zone valves be permitted to be secured
to prevent inappropriate access? - Correct Answers
✅pediatric
, Med Gas Study Guide Exam Questions
and Answers (Most Recent Version,
Complete Study Material)
factory installed inlet tubes on station outlets shall be NOT
less than __________with 0.3 inch minimum inside diameter. -
Correct Answers ✅NPS 1/4, 3/8 in. O.D.
which of these operations would not breach the vacuum
system? - Correct Answers ✅testing a system component
with a leak detector solution
except for valves in zone valve boxes, all valves shall be
located in secured areas such as locked pipe chases, or be
__________. - Correct Answers ✅latched or locked in
operation position
medical gas Central Supply systems are NOT permitted to be
located where? - Correct Answers ✅in an unlocked location
fittings, valves, and other components for field-installed
positive pressure distribution systems shall be ________ until
prepared for installation. - Correct Answers ✅delivered
sealed, labeled, and kept sealed
vacuum piping for __________ shall be connected separately
from the medical surgical system directly to the receiver tank
through its own isolation valve and fluid trap located at the
receiver. - Correct Answers ✅a teaching laboratory