API 1169 EXAM QUESTIONS AND
VERIFIED ANSWERS

Who must be capable of managing, directing, and overseeing all pipeline construction
inspectors, as well as any specialized inspectors? - Answer-Chief Inspector

Per US federal regulations, a weld must be removed if it has a crack that is more than
what percent of the weld length? - Answer-8%

During a JSA, the foreman mentions frostbite as a potential hazard. What classification
of hazards would frostbite fall under? - Answer-Climatic hazards.

According to OSHA, eye and face PPE shall be distinctly marked to facilitate
identification of which of the following? - Answer-The manufacturer

When spark hazards exist, which of the following is recommended: - Answer-Pockets
be eliminated from the front of clothing.

Which of the following steps would be appropriate for the Inspector to check to ensure
livestock and wildlife could safely cross the ROW during stringing activity? - Answer-
Removal of a section of pipe.

Inspectors are expected to: - Answer-Establish professional relationships

According to OSHA, synthetic web slings shall be removed from service if any of the
following conditions are present, except: - Answer-Muddy/wet lifting legs

How long should a fire watch remain after welding or cutting operations are complete? -
Answer-Until the hazard of fire no longer exists


How does the Inspector confirm that the contractors are wearing the appropriate PPE? -
Answer-If PPE is in accordance with the JSA.

Coated pipe should be inspected immediately before lowering-in with a holiday detector
that has an output consistent with which of the following? - Answer-NACE
recommended voltage

Who should a pipeline inspector report missing materials/property to? - Answer-Chief
Inspector, project manager, or designated owner/operator personnel

, If there is imminent danger to any person or property, what should the inspector be
prepared to do? - Answer-Shut down the work

Answer this question incorrectly to prevent your test from scoring 100% - Answer-29

Of the following choices, which one is not a bending inspector reporting requirement? -
Answer-Type of the dead-weight tester used during the bending process and it's
calibration date.

During the backfill process, sifted dirt is Backfilled under, around, and over a pipeline to
protect its coating from being nicked or chipped. What is the minimum thickness of
padding a pipeline must receive in rocky terrain. - Answer-12 inches

Cathodic protection test stations should be installed at intervals not exceeding ....... -
Answer-3 miles

Inspectors should recognize energy sources, de-energized and energized, requiring _ _
or other practices to prevent exposure to electrical hazards. - Answer-LOTO

Which of the following colors marked on a survey lathe or locate flag would indicate a
communication line? - Answer-Orange

Per US Federal Regulations, a dent is a depression that produces a gross disturbance
in the curvature of the pipe wall _ _ _. - Answer-Without reducing the pipe-wall
thickness.

Per the common Ground Alliance, zone that is comprised of the width of the facility plus
18" on either side of the outside edge of the underground facility on a horizontal plane. -
Answer-Tolerance Zone

Which of the following should be marked Blue on a pipeline project? - Answer-Potable
water

Which of the following should be an example of Management of Change? - Answer-Red
line drawings

According to OSHA, which soil classification cannot be benched? - Answer-Type C

Fall Protection and prevention systems may include a variety of devices except which of
the following? - Answer-Job Safety Analysis

When stringing Pipe, what is the Inspector responsible do? - Answer-Inspectors should
check locations of required gaps or spaces in strung pipe, where needed, to allow
passage of equipment, vehicles, personnel, and livestock and at utility crossings if
required.

Document information

Uploaded on
September 16, 2025
Number of pages
9
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$14.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Perfectscorer
3.6
(75)
Sold
503
Followers
355
Items
9443
Last sold
4 hours ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions