1. appropriate and useful quantitative analysis ensures the use of ___________
data to understand a business situation - ANSWER valid and measurable
2. when is QA most useful? - ANSWER when the problem being evaluated can be
represented by discrete data that are valid, objective, and reliable
3. under what circumstances could QA be used successfully? - ANSWER when
then problem being analyzed can be numerically represented and valid and
reliable data are available
4. which of the following accurately describes QA? - ANSWER ensuring the use of
valid, reliable, and objectively measurable data in order to understand a
phenomena
5. what would be the best reason for not wanting to use QA? - ANSWER when
the problem being evaluated lacks the presence of objective, valid, and
measurable data to use for the analysis
6. what would be the best application of QA for the situations below? - ANSWER
a marketing director wants to determine the average household income of the
company's key customers
1
,7. your company has been asked to build a playground for an elementary school.
the project must be completed before the first day of school. which of the
following steps would increase the likelihood of finishing the project on time?
- ANSWER have the most experienced workers complete the tasks on the
critical path
8. the critical path denotes the longest time to complete any path that is part of
the project. why might the critical path be the longest? - ANSWER due to
predecessors, the path that is the longest may have to start later than other
tasks
9. you contract to have your house built, the first thing you do is hire an architect
to design the building to specifications. After that, there are series of jobs with
various time commitments associated. They include ordering materials, laying
foundation, constructing the house, selecting the siding, selecting the interior,
and finishing the work. Each step takes a different amount of time. Without
determining the critical path, what are the elements that possibly make up the
critical path? - ANSWER the various jobs that are involved in constructing the
house
10.if a task is delayed, but it does not lie on the critical path, will the total time of
project completion be extended? - ANSWER maybe
11.does a critical path have to have a slack (time) equal to zero - ANSWER yes
12.in the critical path method (CPM) of project management, the soonest time
that a specific task can begin is known as the _____. After the time is noted,
then the _____ time can be calculated by adding on the task duration -
ANSWER earliest start; earliest finish
2
,13.forward pass - ANSWER the first pass in calculating the total duration of the
individual tasks in a project, moves from left to right
14.backward pass - ANSWER finds the latest start and finish times/dates for the
project, moves from right to left
15.how is the latest start time calculated? - ANSWER subtract the task duration
from the latest finish
16.what is the early start time of the first activity in a network diagram? -
ANSWER 1
17.which of the following statements is true regarding slack time in a project? -
ANSWER any task on the critical path cannot be delayed without delaying the
entire project
18.cost slope calculation - ANSWER crash cost - normal cost / normal duration -
crash duration
19.a company is looking to expand production of its paper products. It contacts
its current raw material supplier and checks to see if they can deliver 25%
more raw material on a monthly basis. In order to accommodate the
increased inventory of raw materials, the company will need to expand its
storage facility. The budget to increase the storage facility is $50K and will
take 3 weeks to accomplish. Based on the above scenario, what should the
manager do first? - ANSWER determine if the supplier can deliver the
increased raw materials and if they cannot, find out whether there is another
legal source for the raw material
3
, 20.what is the key advantage of using the beta distribution technique to estimate
task times? - ANSWER it allows you to calculate project duration
21.a project manager (PM) held discussions with a subject matter expert (SME)
about the durations for a particular task. The SME said the task was usually
completed in about 32 working days. The PM then asked the SME about the
fastest and slowest times the SME could recall for the task. The SME said the
worst time for a similar task was 45 days. What is the expected time in days
using the beta distribution technique? - ANSWER 32.5 days
22.the critical path method (CPM) is a method for doing project planning. Before
beginning with the analysis, what must be known about each task? - ANSWER
the estimated time duration
23.in defining a cause and effect relationship, the variable that drives some
change in another variable is called what? - ANSWER independent variable
24.in defining a cause and effect relationship, the variable that is changed as a
result of the action of some other variable is called what? - ANSWER
dependent variable
25.if there is a linear relationship between variables, we can say they are
correlated. Determining that variable are correlated is very important;
however, to draw specific conclusions about the cause and effect relationship
will take additional advanced analytical techniques to further test the
relationship in order to exclude other contributory factors that could have
caused the change.