QUESTIONS AND ANSWERS GRADED A+ LATEST UPDATE.
1. In what division are Procurement and Contracting Requirements located?
a. Division 01
b. Division 00
c. AIA 101
d. AIA201: Division 00
2. List the sections for Procurement Requirements: a. Solicitation
,b. Advertisement for bids
c. Invitation to bid
d. Instructions for procurement
e. Supplementary instructions to bidders
f. Available information
g. Preliminary schedules
h. Existing condition information
i. Geotechnical data
j. Procurement forms and supplements
k. Bid forms
l. Procurement form supplements
m. Bid security form
n. Representations and certifications
3. List the sections for Contracting requirements: a. Contracting forms and
supplements
b. Agreement forms
, c. Project forms
d. Bond forms
e. Certificates and other forms
f. Conditions of the contract (example: A101)
g. General conditions (example: A201)
h. Supplementary conditions
4. Division 01 General Requirements include which of the following? Select all
that apply.
a. Administrative and procedural requirements for contract administration
b. Temporary facilities
c. Performance requirements for facilities and systems
d. Life cycle activities
e. A, B, and D
f. All of the above: f. All of the above
5. List the four phases of Life cycle activities: a. Commissioning
b. Facility operation