1.) Which one of the following statements regarding COR appointments is FALSE? - Answer A
COR may be delegated authority from the supervisor, program manager or contracting officer.
2.) All of the following statements are correct about COR inspection EXCEPT: - Answer The COR
may not conduct inspections
3.) The technical experts and nominated COR are usually involved in evaluating the technical
merits of the submitted proposals and rating them against _____ of the final RFP. - Answer
Section M Evaluation Factors for Award
4.) Wide Area Work Flow (WAWF) is a Paperless Contracting DoD-wide application designed to
eliminate paper from the receipts and acceptance process of the DoD contracting lifecyle. The
goal is to enable authorized Defense contractors and DoD personnel the ability to create
invoices and receiving reports and access contract related documents. - Answer True
5.) Which selection below describes a fixed price contract type? - Answer The Government's
obligation is to pay the agreed-upon price, regardless of whether the contractor's costs increase
or decrease during performance.
6.) As a COR, you will assess the contractor's performance to ensure it conforms to contract
performance requirements, using the _____. - Answer Quality Assurance Surveillance Plan
(QASP)
7.) The Statement of Work or Performance Work Statement: - Answer Specifies how the work
will be performed in order to reduce the number of proposals
8.) The purpose of market research is to maximize the capabilities - Answer True
9.) A nominated COR frequently is asked to write evaluation factors during the source selection
process. Evaluation factors: - Answer Clearly state how the government will evaluate the bid or
proposal.