25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
TASK ASSIGNED TO START END
Day M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Planning
Identify scope of project Project Mgr 8/19/24 8/21/24 3
Conduct SWOT Analysis Business Analyst 8/22/24 8/25/24 3
Develop strategic plan Project Mgr 8/26/24 8/29/24 3
Resource allocation CFO 8/30/24 9/2/24 3
Communicate with team Project Mgr 9/3/24 9/3/24 1
Milestone: Initial Project Plan 8/19/24 8/19/24
Analysis
Collect system data System Analyst 9/4/24 9/9/24 5
Determine system requirements System Analyst 9/10/24 9/14/24 4
Prioritize requirements Project Mgr 9/15/24 9/17/24 2
Review credible sources Project Mgr 9/18/24 9/22/24 4
Evaluate requirements with users Project Mgr 9/23/24 9/25/24 2
Milestone: Final Design Approval 9/4/24 9/4/24
Design & Development
Design system structure IT Engineer 9/26/24 9/30/24 4
Design technical structure IT Engineer 10/1/24 10/5/24 4
Create user interface IT Engineer 10/6/24 10/10/24 4
Protype development IT Engineer 10/11/24 10/15/24 4
Conduct system testing IT Engineer 10/16/24 10/20/24 4
Milestone: Determine Go/No Go 9/26/24 9/26/24
Implementation
System testing IT Engineer 10/21/24 10/25/24 4
User acceptance testing End user 10/26/24 10/30/24 4
Data conversion IT Engineer 10/31/24 11/4/24 4
Build training material CIO 11/5/24 11/9/24 4
Fixbugs Project Mgr 11/10/24 11/14/24 4
Milestone: Go-Live 10/21/24 10/21/24
Maintenance/Monitoring/Evaluation
Test system functionality IT Engineer 11/15/24 11/18/24 3
Monitor system performance System Adm. 11/19/24 11/22/24 3
Provide help-desk support System Adm. 11/23/24 11/28/24 5
Solicit user experience Project Mgr 11/29/24 12/4/24 5
Provide corrective maintenance System Adm. 12/5/24 12/14/24 9
Milestone: System Fully Operational & In Use 11/15/24 11/15/24