Any interested party may file a protest against the government if they
feel that a contract has been unfairly awarded to another company.
The protest can be filed directly with______ or with _____ -
ANSWERS-The contracting officer or the General Accounting Office
(GAO)
This type of modification involves the use of administrative changes -
ANSWERS-Unilateral
You are monitoring a custodial contract (bathroom). What remedies
are available to you? - ANSWERS-Notify to Contracting Officer,
contact the Contractor, document the results, and request re-
performance
All of the following statement are correct about COR inspection
EXCEPT: - ANSWERS-The COR may not conduct inspections
In more complex acquisition, the Government uses two common
approaches in contractor selection. These are: - ANSWERS-Tradeoff
and Lowest Price Technically Acceptable
With regard to contract modifications, the COR CANNOT: -
ANSWERS-Authorize the contractor to proceed with changes in
anticipation of the changes being incorporated into the next
modification under the contract
, You are a COR working on the third year of a 5-year contract. The
contractor shows his appreciation by offering you four box tickets to
your university's football game. Can you accept these tickets as a gift?
- ANSWERS-No, the tickets exceed the gratuity dollar threshold of
$20.00
The purpose of market research is to maximize the capabilities,
technology and competitive forces of the marketplace to meet an
organization's needs for supplies and services. - ANSWERS-True
Acceptance means the act of an authorized representative of the
Government assuming ownership of supplies or approving services.
Based on what you have learned about the responsibilities of the
COR, choose a true statement from the following: - ANSWERS-It is
the policy of the Government that contract quality assurance is
conducted before acceptance.
When conducting assessment of contractor performance, the COR
must consider: (Check all that apply) - ANSWERS-The inspection
plan shown in the Quality Assurance Surveillance Plan, The terms and
conditions of the contract, including attachments, Concerns of safety
and welfare of contractor employees
A solicitation used in negotiated procurement to communicate
government requirement to prospective contractors and to solicit
proposals or offers from is a/an - ANSWERS-Request for Proposal
(RFP)
Any interested party may file a protest against the government if they
feel that a contract has been unfairly awarded to another company.
The protest can be filed directly with______ or with _____ -
ANSWERS-The contracting officer or the General Accounting Office
(GAO)
This type of modification involves the use of administrative changes -
ANSWERS-Unilateral
You are monitoring a custodial contract (bathroom). What remedies
are available to you? - ANSWERS-Notify to Contracting Officer,
contact the Contractor, document the results, and request re-
performance
All of the following statement are correct about COR inspection
EXCEPT: - ANSWERS-The COR may not conduct inspections
In more complex acquisition, the Government uses two common
approaches in contractor selection. These are: - ANSWERS-Tradeoff
and Lowest Price Technically Acceptable
With regard to contract modifications, the COR CANNOT: -
ANSWERS-Authorize the contractor to proceed with changes in
anticipation of the changes being incorporated into the next
modification under the contract
, You are a COR working on the third year of a 5-year contract. The
contractor shows his appreciation by offering you four box tickets to
your university's football game. Can you accept these tickets as a gift?
- ANSWERS-No, the tickets exceed the gratuity dollar threshold of
$20.00
The purpose of market research is to maximize the capabilities,
technology and competitive forces of the marketplace to meet an
organization's needs for supplies and services. - ANSWERS-True
Acceptance means the act of an authorized representative of the
Government assuming ownership of supplies or approving services.
Based on what you have learned about the responsibilities of the
COR, choose a true statement from the following: - ANSWERS-It is
the policy of the Government that contract quality assurance is
conducted before acceptance.
When conducting assessment of contractor performance, the COR
must consider: (Check all that apply) - ANSWERS-The inspection
plan shown in the Quality Assurance Surveillance Plan, The terms and
conditions of the contract, including attachments, Concerns of safety
and welfare of contractor employees
A solicitation used in negotiated procurement to communicate
government requirement to prospective contractors and to solicit
proposals or offers from is a/an - ANSWERS-Request for Proposal
(RFP)