TCM 226 Final Graded A+ (Verified) All project related functions between parties to a contract" is the definition of - ANSWER-Project Administration A common method to transport large equipment from one location to another is to use a lowboy (T/F) - ANSWER-True A letter of transmittal is: - ANSWER-A dated record of when a document was sent to another party

Content preview

TCM 226 Final Graded A+ (Verified)
All project related functions between parties to a contract" is the definition of -
ANSWER-Project Administration

A common method to transport large equipment from one location to another is to use a
lowboy (T/F) - ANSWER-True

A letter of transmittal is: - ANSWER-A dated record of when a document was sent to
another party

A pre-construction conference to establish ground rules for operations and the
successful completion of the project should be held: - ANSWER-During the bid phase

A pre-final inspection: - ANSWER-Generates the initial punch list for the project

A projects LEED certification fee paid to the GBCI is based on which of the following
factors? - ANSWER-Project square footage, USGBC membership status

After an RFI response is received, the general contractor and its subcontractors should
review the change to see if there is a change in scope of work and possible cost or
schedule impacts. (T/F) - ANSWER-True

AHJ stands for: - ANSWER-Authority having Jurisdiction

All submittals must be approved by the project architect/engineer (T/F) - ANSWER-
False

An optimum job site layout plan maximizes on-site labor in material movement travel,
and transportation, allowing workers to spend the minimum amount of time performing
construction activities. (T/F) - ANSWER-False

As discussed in the class, the superintendent is the critical link to the craft workers. He
is responsible for "pushing" the work. (T/F) - ANSWER-False

Coined by Autodesk and popularized by Jerry Laiserin, BIM stands for: - ANSWER-
Building Information modeling

Ethics are a theory or system of values that answers the question, "What can I do and
still not get caught?" (T/F) - ANSWER-False

Functional organizational structures are most common for small to mid-sized
construction companies. (T/F) - ANSWER-True

, In a limited liability partnership (LLP), the profits of the business are subject to double
taxation. - ANSWER-False

In a sole proprietorship, the owner of the business is personally liable for the debts and
action of the business. - ANSWER-True

In a(n) __ contract, quantities are specified and compensation for variance with the
specified quantities may - ANSWER-Unit-price

In prolog, what module would I open in order to complete an RFI? - ANSWER-Doc
Control

In which sector of the construction industry is mobilization referred to as the ongoing
process of moving project material and equipment from one work area to another? -
ANSWER-Heavy highway

Individuals can be LEED Accredited. (T/F) - ANSWER-True

LEED stands of Leadership in Energy and Efficient Design. (T/F) - ANSWER-False.
Leadership in Energy and Environment

Lien releases may be requested from the contractor and all subcontractors. (T/F) -
ANSWER-True

Most contracts specify that the owner can take a period of __ to process progress
payment after receipt of the certified application, but this may vary depending on
specific factors relating to the owner and project financing. - ANSWER-30 days

Most RFI's are: - ANSWER-Brief questions requesting clarification

NTP stands for no time penalty. (T/F) - ANSWER-False

Only the owner, not the A/E, has the authority to accept non-conforming work. (T/F) -
ANSWER-True

Procedures for discovering defects and deficiencies or deviations to the contract
documents before and during the execution of the work is also known as: - ANSWER-
Quality assurance

Productivity is measured in terms of: - ANSWER-Output / Input

Project administration software should NOT include the following features - ANSWER-
Anonymous commenting

Provisional payments are pre-determined partial amount to be paid when certain
identified milestones are achieved (T/F) - ANSWER-True

Document information

Uploaded on
August 24, 2025
Number of pages
5
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
CLOUND
3.9
(128)
Sold
657
Followers
389
Items
12264
Last sold
3 weeks ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions