A project team is in the process of estimating the types and quantities of
resources required to perform each activity. Which of the following activities will
NOT be done by the team during this process?
A. Estimate the type and quantity of resource required to perform each activity
B. Go through the past data and lessons learned from previous projects
C. Study the organization policies and procedures regarding staffing
D. Identify and show network dependency in the project activities
-:- Correct Option: D
EXPLANATION
The project team is in the process of Estimating Activity Resources, and the
activities provided as options (b) and (c) are done as part of this process. Option
(d), which involves creating a schedule network diagram to display project
schedule activities and logical relationship between them, is part of the Sequence
Activities process.
1|Page | Grade A+| 2024/2025
,2024 / 2 0 2 5 | © copyright | This work may not be copied for profit gain | Excel!
During the initiating stage, which of the following elements will be identified to
meet the project goals?
A. Key deliverable
B. Stakeholders
C. Quality
D. Vendors
-:- Correct Option: A
EXPLANATION
Even though the identification of stakeholders and potential sellers happens as
part of initiating phase through the "identify stakeholders" process, this will not
help to meet the project goals. Key deliverables help in meeting the project goals.
Quality identification happens during planning.
A car manufacturing company conceptualized a new car that will be more fuel
efficient, ergonomically designed, and that satisfies the latest safety regulations.
This car was recently launched and has now moved into full-fledged production.
This is an example of:
A. Operation, as the company is into car manufacturing, which is an ongoing process
B. Project, as this car was conceptualized, designed, and has now been launched
2|Page | Grade A+| 2024/2025
,2024 / 2 0 2 5 | © copyright | This work may not be copied for profit gain | Excel!
C. Project, as it has clear scope and requirements in terms of safety
compliance, fuel efficiency, etc.
D. Operation, as this activity didn't create a unique product
-:- Correct Option: B
EXPLANATION
This is a typical scenario where project intersects with operation during product
life cycle. Notice the word launched. All the activities before launch of the vehicle
are part of a project, which is a temporary activity with a well-defined unique
output. Once the car moves to production, it becomes an ongoing operation for
the company.
When is the cost highest in the project life cycle?
A. At the initiating phase
B. During planning
C. Midway during the project
D. During closure
-:- Correct Option: C
3|Page | Grade A+| 2024/2025
, 2024 / 2 0 2 5 | © copyright | This work may not be copied for profit gain | Excel!
EXPLANATION
Project cost peaks in the middle of the project as maximum resources are utilized
during this phase. Project cost is low at the beginning, peaks midway, and drops
rapidly as the project draws to an end. Initiating, planning, and closing are not
part of the project life cycle and are process groups.
As a part of Stakeholder Management, a Project Manager can follow all of these
management practices, EXCEPT:
A. Identify all the stakeholders and capture them in the project team directory
B. Ensure that stakeholders' expectations are met and gain support for the project
C. Give preference to stakeholders over customers in case of conflict of interest
D. Communicate all relevant information about the project to stakeholders
-:- Correct Option: C
EXPLANATION
In case of conflict of interest, it should generally be resolved in favor of the
customer or organization who would use the project's product or service.
4|Page | Grade A+| 2024/2025