What makes up a quality asphalt mixture? - correct-answer-A quality asphalt
| | | | | | | | | |
mixture is determined by the constructability, if it conforms to Specifications, and
| | | | | | | | | | | |
if it satisfies functional requirements.
| | | | |
CQC - correct-answer-contractor quality control
| | | |
Superpave - correct-answer-Asphalt mix design system since 1998
| | | | | | |
QCP - correct-answer-Quality control plan
| | | |
QCM - correct-answer-Quality control Manual
| | | |
,2 || |P |a |g
|e
What is the tack application rate tolerance? - correct-answer-+/- 0.01 gal/syd
| | | | | | | | | |
Step 1 for figuring the tack spread rate - correct-answer-Find the length of the
| | | | | | | | | | | | |
tack shot
| |
Station - station = ft | | | |
Step 2 for figuring the tack spread rate - correct-answer-Find the square yards
| | | | | | | | | | | |
feet x width / 9 = syds
| | | | | | |
Step 3 for figuring the tack spread rate - correct-answer-Use the distributor chart
| | | | | | | | | | | |
to find the gallons used
| | | | |
start 11/13 - 1319 gal
| | | |
end 18/14 - 1140 gal
| | | | |
1319 - 1140 = gallons used
| | | | |
Step 4 for figuring the tack spread rate - correct-answer-Find the correction factor
| | | | | | | | | | | |
on the temperature sheet corresponding to the correct liquid to convert the
| | | | | | | | | | | |
gallons to 60F
| | |
EX: 160F correction factor = 0.9756
| | | | |
gallons used x correction factor = gallons at 60F
| | | | | | | |
, 3 || |P |a |g
|e
Step 5 for figuring the tack spread rate - correct-answer-gallons used at 60F / syds
| | | | | | | | | | | | | |
= tack spread rate
| | |
What is the application rate for ARMI layers? - correct-answer-0.6 - 0.8 gal/syd
| | | | | | | | | | | |
Use the AC(ARB) temperature correction factor
| | | | | |
What is the spread rate for the chip spreader? - correct-answer-0.26 to 0.33 ft/syd
| | | | | | | | | | | | |
with the actual spread rate determined by the engingeer
| | | | | | | | |
What is the minimum thickness for asphalt being placed over an ARMI layer? -
| | | | | | | | | | | | |
correct-answer-1 1/2 inches unless plans call for a thicker mat
| | | | | | | | | |
Where should you stick a thermometer in a truck? - correct-answer-The hole
| | | | | | | | | | |
should be 1/4 of an inch
| | | | | |
In the middle third of the length of the body
| | | | | | | | |
and 6 to 10 inches above the bottom of the bed
| | | | | | | | | | |
|e
FDOT Asphalt Paving Level 2 Exam 2025-
2026 Actual Questions With Answers
What makes up a quality asphalt mixture? - correct-answer-A quality asphalt
| | | | | | | | | |
mixture is determined by the constructability, if it conforms to Specifications, and
| | | | | | | | | | | |
if it satisfies functional requirements.
| | | | |
CQC - correct-answer-contractor quality control
| | | |
Superpave - correct-answer-Asphalt mix design system since 1998
| | | | | | |
QCP - correct-answer-Quality control plan
| | | |
QCM - correct-answer-Quality control Manual
| | | |
,2 || |P |a |g
|e
What is the tack application rate tolerance? - correct-answer-+/- 0.01 gal/syd
| | | | | | | | | |
Step 1 for figuring the tack spread rate - correct-answer-Find the length of the
| | | | | | | | | | | | |
tack shot
| |
Station - station = ft | | | |
Step 2 for figuring the tack spread rate - correct-answer-Find the square yards
| | | | | | | | | | | |
feet x width / 9 = syds
| | | | | | |
Step 3 for figuring the tack spread rate - correct-answer-Use the distributor chart
| | | | | | | | | | | |
to find the gallons used
| | | | |
start 11/13 - 1319 gal
| | | |
end 18/14 - 1140 gal
| | | | |
1319 - 1140 = gallons used
| | | | |
Step 4 for figuring the tack spread rate - correct-answer-Find the correction factor
| | | | | | | | | | | |
on the temperature sheet corresponding to the correct liquid to convert the
| | | | | | | | | | | |
gallons to 60F
| | |
EX: 160F correction factor = 0.9756
| | | | |
gallons used x correction factor = gallons at 60F
| | | | | | | |
, 3 || |P |a |g
|e
Step 5 for figuring the tack spread rate - correct-answer-gallons used at 60F / syds
| | | | | | | | | | | | | |
= tack spread rate
| | |
What is the application rate for ARMI layers? - correct-answer-0.6 - 0.8 gal/syd
| | | | | | | | | | | |
Use the AC(ARB) temperature correction factor
| | | | | |
What is the spread rate for the chip spreader? - correct-answer-0.26 to 0.33 ft/syd
| | | | | | | | | | | | |
with the actual spread rate determined by the engingeer
| | | | | | | | |
What is the minimum thickness for asphalt being placed over an ARMI layer? -
| | | | | | | | | | | | |
correct-answer-1 1/2 inches unless plans call for a thicker mat
| | | | | | | | | |
Where should you stick a thermometer in a truck? - correct-answer-The hole
| | | | | | | | | | |
should be 1/4 of an inch
| | | | | |
In the middle third of the length of the body
| | | | | | | | |
and 6 to 10 inches above the bottom of the bed
| | | | | | | | | | |