The possible approaches for delivering a project are virtually unlimited. A key reason for such
variations is:
a. The different roles that can be assumed by project participants.
b. Different forms of contracts and methods of compensation that can be used.
c. The different levels of care, responsibility, and risks assumed by the parties involved.
d. All of the above. ✔Correct answer-d. All of the above.
The traditional delivery system is characterized by executing the major phases of a project in:
a. An overlapping concept
b. A linear sequence
c. A fast track method
d. All of the above. ✔Correct answer-b. A linear sequence
A key advantage of the traditional delivery approach is:
a. With the traditional delivery system, the cost of the construction phase is known before
construction starts.
b. Construction documents are 100% complete.
c. When the construction contract is signed, the major risk belongs to the contractor.
d. All of the above. ✔Correct answer-d. All of the above.
Design-build and at-risk construction manage.ment delivery systems allow the option to fasttrack or
phase a project.
a. True
b. False ✔Correct answer-a. True
Most definitions of construction management are similar. However, a contractual definition is not
known until:
a. The legal form of the CM contract is chosen.
b. The specific scope of services to be provided is identified.
, c. The relationship of the CM to others and the risks and authority assumed by the parties are clearly
defined.
d. All of the above. ✔Correct answer-d. All of the above.
The at-risk CM has no obligation to place duty to the Owner above its own interests.
a. True
b. False ✔Correct answer-a. True
The agency CM does not normally have any independent power to sanction contractors or force
contractors to abide by their contractual obligations.
a. True
b. False ✔Correct answer-a. True
When a GMP is rendered by a CM and agreed to by the Owner, there are no longer any implied
duties of loyalty and care to the Owner.
a. True
b. False ✔Correct answer-a. True
Under a CM-at-risk contract, which of the following statements are true?
a. The CM, in most cases, holds the trade and/or specialty contracts.
b. The CM has the right to enforce the schedule, pay the trade or subcontractors, and terminate
them if such action becomes necessary.
c. On some CM-at-risk contracts, the CM has the option of performing portions of the work with its
own resources (unless prohibited by law on certain public projects).
d. All of the above. ✔Correct answer-d. All of the above.
In considering the differences between Agency CM and CM-at-risk, which one of the following
statements is NOT true?
a. With the CM-at-risk, the CM is responsible for means, methods, and sequencing of work.
b. In an Agency CM role, the CM does none of the physical work.
c. The CM, in most cases, is clearly responsible for schedule and coordination.
d. Project controls under both forms of CM equally serve the interest of the Owner as a priority.
✔Correct answer-d. Project controls under both forms of CM equally serve the interest of the Owner
as a priority.
The agency CM maintains a direct contractual relationship with the trade or prime contractors.
a. True
CORRECT & 100% VERIFIED ANSWERS|LATEST
UPDATE|ALREADY GRADED A+
The possible approaches for delivering a project are virtually unlimited. A key reason for such
variations is:
a. The different roles that can be assumed by project participants.
b. Different forms of contracts and methods of compensation that can be used.
c. The different levels of care, responsibility, and risks assumed by the parties involved.
d. All of the above. ✔Correct answer-d. All of the above.
The traditional delivery system is characterized by executing the major phases of a project in:
a. An overlapping concept
b. A linear sequence
c. A fast track method
d. All of the above. ✔Correct answer-b. A linear sequence
A key advantage of the traditional delivery approach is:
a. With the traditional delivery system, the cost of the construction phase is known before
construction starts.
b. Construction documents are 100% complete.
c. When the construction contract is signed, the major risk belongs to the contractor.
d. All of the above. ✔Correct answer-d. All of the above.
Design-build and at-risk construction manage.ment delivery systems allow the option to fasttrack or
phase a project.
a. True
b. False ✔Correct answer-a. True
Most definitions of construction management are similar. However, a contractual definition is not
known until:
a. The legal form of the CM contract is chosen.
b. The specific scope of services to be provided is identified.
, c. The relationship of the CM to others and the risks and authority assumed by the parties are clearly
defined.
d. All of the above. ✔Correct answer-d. All of the above.
The at-risk CM has no obligation to place duty to the Owner above its own interests.
a. True
b. False ✔Correct answer-a. True
The agency CM does not normally have any independent power to sanction contractors or force
contractors to abide by their contractual obligations.
a. True
b. False ✔Correct answer-a. True
When a GMP is rendered by a CM and agreed to by the Owner, there are no longer any implied
duties of loyalty and care to the Owner.
a. True
b. False ✔Correct answer-a. True
Under a CM-at-risk contract, which of the following statements are true?
a. The CM, in most cases, holds the trade and/or specialty contracts.
b. The CM has the right to enforce the schedule, pay the trade or subcontractors, and terminate
them if such action becomes necessary.
c. On some CM-at-risk contracts, the CM has the option of performing portions of the work with its
own resources (unless prohibited by law on certain public projects).
d. All of the above. ✔Correct answer-d. All of the above.
In considering the differences between Agency CM and CM-at-risk, which one of the following
statements is NOT true?
a. With the CM-at-risk, the CM is responsible for means, methods, and sequencing of work.
b. In an Agency CM role, the CM does none of the physical work.
c. The CM, in most cases, is clearly responsible for schedule and coordination.
d. Project controls under both forms of CM equally serve the interest of the Owner as a priority.
✔Correct answer-d. Project controls under both forms of CM equally serve the interest of the Owner
as a priority.
The agency CM maintains a direct contractual relationship with the trade or prime contractors.
a. True