Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 5 out of 7 pages
Exam (elaborations)

VA Contractors License Exam – Advanced (Class A) 2025 Practice Questions and Verified Answers for Actual State Test Preparation

Document preview thumbnail
Preview 5 out of 7 pages

A comprehensive and exam-focused study resource designed to help candidates prepare for the Virginia Class A Contractor License (Advanced) examination. This guide includes realistic, up-to-date practice questions with thoroughly explained answers aligned to current DPOR testing standards. It covers essential topics such as financial management, contract administration, project scheduling, OSHA safety regulations, insurance, and business law. Structured to simulate the actual exam environment, this material helps improve both knowledge and speed for the open-book test format, increasing the chances of passing on the first attempt.

Content preview

VA CONTRACTORS: VA ADVANCED (CLASS A)
(ACTUAL 2025) QUESTIONS WITH ANSWER

A contractor pays a workers' compensation rate of $0.08 per
$100 of office employee payroll, $0.15 per $100 of field
supervisor payroll, and $0.26 per $100 of field employee
payroll. Total office employee payroll for the year is $25,000.
Total field supervisor payroll is $48,000. Total field employee
payroll is $225,000. The contractor receives a discount of 5%
of total premiums for having a safety program in place. The
total workers' compensation for the year is... -
<<Answers>>>More than $600


A permit is obtained on Friday, May 1. The materials are to be
delivered May 8. The materials are needed when labor begins
on May 11. It is estimated that 15 days of labor are
REQUIRED. The crew will work every day, including
weekends and holidays. The project is scheduled to be
completed on June 8. How many float days are available for
the labor for this project? - <<Answers>>>13


A contractor puts in a claim under a comprehensive standard
general liability policy. The policy has no additional coverage,
riders, or floaters, and has a $500 deductible per occurrence.
The claim is for a job-site accident that caused $2,000 of
injuries to employees, $1,800 of injuries to a pedestrian,
$2,300 damage to the contractor's equipment, and $1,750 loss
of project materials purchased by the contractor. The
insurance company is liable for... - <<Answers>>>$1,300

, VA CONTRACTORS: VA ADVANCED (CLASS A)
(ACTUAL 2025) QUESTIONS WITH ANSWER
What is the MAXIMUM amount of a lien that can claimed by
a subcontractor who notifies the lien agent for a two-family
residential property on August 1 that the subcontractor first
provided labor and materials on the project on May 1? The
subcontractor billed the general contractor for $4,000 per
month, through September 30, and was never paid. -
<<Answers>>>$8,000


What percent should the employer withhold for Virginia
withholding for an employee who is to receive a separate
supplemental payment for vacation? The employer is using a
flat percentage rate. - <<Answers>>>5.75%
A lump sum contract on a project has a total contract price of
$160,000. Retainage has been held back at 10%. The
contractor has received progress payments for 75% of the
project. The contractor submits a request for final payment for
the new completed project. The final payment amount should
be for... - <<Answers>>>More than $50,000


What is the total value of current assets for an accrual basis
company that has the following? Checking account cash
balance is $4,800; materials inventory for work-in-progress is
$4,200; a pick-up truck that cost $12,460- paid for with
$2,460 in cash and a note for $10,000- and is used 100% in
the business; accounts receivable is $5,700; suppliers'
accounts payable is $6,300; other accounts payable is $2,200;
and quarterly income tax payment due is $1,180... -
<<Answers>>>Between $12,000 and $16,000

, VA CONTRACTORS: VA ADVANCED (CLASS A)
(ACTUAL 2025) QUESTIONS WITH ANSWER

What is the total project overhead for a project that lasts 3
months and has the following costs? Labor is $4,000;
materials are $9,500; equipment rentals are $1,200;
superintendent's annual salary is $36,000; office rent is $800
per month; and office utilities are $375 per month. -
<<Answers>>>Less than $12,000


For 1 month a company bills out $38,000 in completed work,
and receives $22,000 in payments plus $8,000 from the
previous month's billings. They pay their total bill of $26,000
to supply houses for this month's purchases, and another
$5,000 to supply houses for last month's purchases. Using a
cash accounting method and NOT considering any other
revenue or expenses, what is the company's net income for the
month? - <<Answers>>>Loss of $1,000


The owner requests for change which will cost the contractor
$15,000 in labor and materials and $2,250 in overhead costs.
With the change, the contractor would be relieved of $18,000
in labor and materials costs, and $2,400 in overhead costs
from the original contract. The original bid included profit of
20% of all costs. The contractor wants to make a profit of
20% of all costs on the changes. The adjusted contract price
for the change order should be... - <<Answers>>>A decrease
of $3,780

, VA CONTRACTORS: VA ADVANCED (CLASS A)
(ACTUAL 2025) QUESTIONS WITH ANSWER
Which of the following would typically be covered by a
contractor's comprehensive general liability insurance policy?
- <<Answers>>>Damage to adjoining property from a crane
accident


What is the total gross compensation and employment status
for a carpenter, given the following information? A contractor
hires a carpenter to do the finish work for a 10-home project.
The carpenter is to be paid $16 per hour. The contractor
provides all materials and equipment, such as a table saw. The
carpenter provides all of his own hand tools. The contractor
and the carpenter agree that all of the homes are to be
completed within 60 8-hour working days, without overtime.
The contractor provides the carpenter with a schedule of the
order in which homes are to be worked on. The contractor
provides a helper to assist the carpenter. The contractor sets
the work schedule each day. The carpenter spends 600 hours
to complete this project, including 120 hours of overtime. -
<<Answers>>>The carpenter is an employee and is owed
$10,560 for the project


What is the name of the process when a facilitator meets with
the major participants in a project, prior to the commencement
of the project, to identify the shared goals of all participants? -
<<Answers>>>Partnering

, VA CONTRACTORS: VA ADVANCED (CLASS A)
(ACTUAL 2025) QUESTIONS WITH ANSWER
What is the average collection period ratio for a firm that has
$365,000 in annual revenues, $6,600 in current receivables,
and net income of $32,000? - <<Answers>>>6.6


Who oversees compliance with Material Safety Data Sheets? -
<<Answers>>>OSHA


A non-exempt employee of a contractor covered by the Fair
Labor Standards Act works 60 hours during a workweek. The
agreement is to pay the employee $400 each week regardless
of the numbers of hours worked. What should be the
employee's gross pay for the worksheet? -
<<Answers>>>$700.50


In the previous year, a company had revenues of $500,000
project overhead of $40,000 and company overhead of
h h h h h h h




$75,000. The company expects the percentage for project and
h h h h h h h h h




company overhead to remain the same for the current year.
h h h h h h h h h




The company desires to make a 10% profit on a project it is
h h h h h h h h h h h h h




bidding. The project would have $80,000 in direct costs. What
h h h h h h h h h h




should the bid price be? - <<Answers>>>Between $110,000 and
h h h h h h h h h




$120,000


How much state income tax MUST be paid by a corporation that
h h h h h h h h h h h h




has $30,000 of Federal taxable income? The company deducted
h h h h h h h h h




$2,000 of state and local taxes on the Federal return, and had
h h h h h h h h h h h h




$2,000 of qualified worker retraining expenses. The
h h h h h h

Document information

Uploaded on
August 12, 2025
Number of pages
7
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$16.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
walterkariuki
4.3
(4)
Sold
47
Followers
1
Items
368
Last sold
2 days ago

Reviews from verified buyers




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions