Have a heating starting: - Answer -Note About Extra Work and Change Orders
From the CSLB "Extra Work and Change Orders become part of the contract once the
order is ______ in _____ and signed by ______ prior to the commencement of any
work covered by the new change order. - Answer --Prepared in writing
-the Parties
The order must describe the scope of the extra work or change the cost to be _______
or ______ from the contract, and the effect the order will have on the schedule or
progress payments. - Answer --Added or Subtracted
When a customer asks for something not included on the contract... - Answer -Do not
do anything until getting something signed because if you do, they do not have to pay.
You can also get in trouble for doing something not on the contract
If another trade damages your work, charge again either - Answer --the client or other
trade contractor, but talk to client first.
Commercial General Liability INS (CGL) should be in a header stating whether -
Answer -the Contractor has or does not have general liability insurance.
If he/she does have CGL, they must put the info on - Answer -Who covers them, and
contact INFO
If the company is self covered - Answer -It must be stated
If the company is not covered, they must include - Answer -That they are not covered,
must disclose
Workers Compensation INS must be - Answer -Written as a header
If the contractor has no employees then it must be - Answer -stated that they are
exempt from workers comp (ROOFING MUST BE COVERED)
If they company does have employees, it must be in this area that - Answer -the
Contractor does carry workers comp and all of his employees are covered and insured
ALl legit businesses will ask for proof - Answer -Before starting work
Performance of Extra or Change-Order Work Notice is a notice explains to the client
that - Answer -No extra work or change in work can be done unless signed by both
parties (Change Order Notice)