1) A major function of the True
DOT is to carry out
Construction and
Reconstruction programs
to provide the public with
adequate transportation
service.
For the DOT, the E. All of the above
management of
Construction and
reconstruction projects
involves the following
specific responsibilities:
A. Planning, Programming
and design
B. Contract administration
C. Contractor payments
D. Design and Contract
Management
E. All of the above
3) To pay for the work True
performed by
Contractors, progress and
Final Estimates are
needed. True or False?
https://quizlet.com/1064556234/ctqp-final-estimates-level-1-flash-cards/?new 1/18
,8/8/25, 8:27 AM CTQP Final Estimates Level 1 Flashcards | Quizlet
These standards are made available for Design,
Construction, Maintenance, and Utility operations on
DESIGN STANDARDS the State Highway System. This booklet provides
guidelines and technical drawings for design and
Construction personnel.
SA'S are work of a different characteristic from that
SUPPLEMENTAL
shown in the original plans and contract; such as to
AGREEMENTS (SA)
clarify the Specifications, or pay for unforeseen work.
WO's are similar to SA's but can't be used in all
WORK ORDERS (WO) instances. They are used to include additional work
into the original contract, and to do minor changes.
JPA's or Locally Funded Agreements (LFA)'s are part of
the State Contract with a separate Financial ID
JOINT PARTICIPATION Number. They are legal documents between the
AGREEMENTS (JPA) Department and other government or private entities.
The work would be a utility relocations or installations,
etc.
1) Multiple choice. Which E. Answer B & D
of the following is NOT
officially considered to be
a "Contract Document"?
A. Supplemental
Agreements and Work
Orders.
B. Notebooks and
Estimates Procedure
Manual.
C. Standard Specifications.
D. Construction Manual.
E. Answers B &D
https://quizlet.com/1064556234/ctqp-final-estimates-level-1-flash-cards/?new 2/18
, 8/8/25, 8:27 AM CTQP Final Estimates Level 1 Flashcards | Quizlet
2) Multiple choice. B Supplemental Specifications
Between printings of the
Standard Specifications,
what does the
Department publish to
identify and describe
changes in the
Specifications?
A. CPAM
B. Supplemental
Specifications
C. Work orders
D. Specifications Changes