This standard shall apply to ______ intended to carry water for fire service
!| !| !| !| !| !| !| !| !| !| !| !| !|
mains - correct answer✔✔Combined Service Mains
!| !| !| !| !|
Working plans shall be submitted for approval to the _____ before any
!| !| !| !| !| !| !| !| !| !| !| !|
equipment is installed or remodeled. - correct answer✔✔AHJ !| !| !| !| !| !| !|
____ shall not be used - correct answer✔✔Pressure-Regulating devices
!| !| !| !| !| !| !| !|
______ shall not be installed in the piping from the fire department
!| !| !| !| !| !| !| !| !| !| !| !|
connection to the fire service main - correct answer✔✔Control Valves
!| !| !| !| !| !| !| !| !|
_____ shall be permitted in the system downstream of the fire department
!| !| !| !| !| !| !| !| !| !| !| !|
connection - correct answer✔✔Control Valves !| !| !| !|
When more than one water supply exists, a ___________ shall be installed
!| !| !| !| !| !| !| !| !| !| !| !|
in each connection - correct answer✔✔Check Valve
!| !| !| !| !| !|
All check valves shall have a ________ installed upstream and downstream
!| !| !| !| !| !| !| !| !| !| !|
of the check valve. - correct answer✔✔Control Valve
!| !| !| !| !| !| !|
A post indicator valve installed not less than____ from the building -
!| !| !| !| !| !| !| !| !| !| !| !|
correct answer✔✔40 ft !| !|
Where post indicator valves are used, they shall be set so that the top of
!| !| !| !| !| !| !| !| !| !| !| !| !| !| !|
each post is _______ above final grade - correct answer✔✔32-40 inches
!| !| !| !| !| !| !| !| !| !|
verified detailed answers !| !|
This standard shall apply to ______ intended to carry water for fire service
!| !| !| !| !| !| !| !| !| !| !| !| !|
mains - correct answer✔✔Combined Service Mains
!| !| !| !| !|
Working plans shall be submitted for approval to the _____ before any
!| !| !| !| !| !| !| !| !| !| !| !|
equipment is installed or remodeled. - correct answer✔✔AHJ !| !| !| !| !| !| !|
____ shall not be used - correct answer✔✔Pressure-Regulating devices
!| !| !| !| !| !| !| !|
______ shall not be installed in the piping from the fire department
!| !| !| !| !| !| !| !| !| !| !| !|
connection to the fire service main - correct answer✔✔Control Valves
!| !| !| !| !| !| !| !| !|
_____ shall be permitted in the system downstream of the fire department
!| !| !| !| !| !| !| !| !| !| !| !|
connection - correct answer✔✔Control Valves !| !| !| !|
When more than one water supply exists, a ___________ shall be installed
!| !| !| !| !| !| !| !| !| !| !| !|
in each connection - correct answer✔✔Check Valve
!| !| !| !| !| !|
All check valves shall have a ________ installed upstream and downstream
!| !| !| !| !| !| !| !| !| !| !|
of the check valve. - correct answer✔✔Control Valve
!| !| !| !| !| !| !|
A post indicator valve installed not less than____ from the building -
!| !| !| !| !| !| !| !| !| !| !| !|
correct answer✔✔40 ft !| !|
Where post indicator valves are used, they shall be set so that the top of
!| !| !| !| !| !| !| !| !| !| !| !| !| !| !|
each post is _______ above final grade - correct answer✔✔32-40 inches
!| !| !| !| !| !| !| !| !| !|