20 days Correct Answer - Deadline for filing preliminary 20-day notice
(late notices are only effective for up to 20 days before filing). A.R.S. § 33-981
60 days Correct Answer - Deadline to file a lien after a "notice of
completion" is filed. A.R.S. § 33-993(A)
120 days Correct Answer - Deadline to file a lien after "completion," if a
notice of completion is not filed. A.R.S. § 33-993(A
6 months Correct Answer - Deadline for enforcing a lien (by filing a
lawsuit).
10 days Correct Answer - Deadline to dispute a lien after notice of
owner's intent to retain payment for the lien from payment to the contractor.
A.R.S. § 33-994
20 days Correct Answer - Deadline for releasing a lien that has been paid
in full or following written request, to avoid owing penalties and damages.
A.R.S. § 33-1006
A contractor license is required when the total cost, including materials is
more than Correct Answer - $1000
Which state agency has the authority to issue a contractor license Correct
Answer - ROC
What is the role of the ROC Correct Answer - ALL OF THE ABOVE
If you have a B- general license which of the items below must be
subcontracted ? Correct Answer - all of the above
-repairing an hvac
-installing a pool
-wiring a homes electrical circuit
, Which of the following commercial license classifications is permitted to
subcontract electical work Correct Answer - B-1 General Commercial
Contractor
A B- general residential contractor must subcontract what type of work
Correct Answer - electrical, boilers, and water wells
What business type is eligible for a contractor license Correct Answer -
llc, sole prop, and partnership
A new qualifying party must have at least two years of experience performing
or supervising the type of work covered by a license within the last Correct
Answer - 10 years
A military spouse who is relocating to arizona may waive the trade exam if
they have had a license in a comparable classification for: Correct Answer -
1 year
A person who has been convicted of contracting without a license is barred
from being part of a license application for: Correct Answer - 1 year
One person may act as the qualifying party for up to two licensees if he owns
at least _________ of each entity Correct Answer - 25%
If the qualifying party stops working for the licensee, the licensee and the
qualifying party must notify the ROC within _____ Correct Answer - 15
days
If a qualifying party dissasociates with the licensee, the licensee must
requalify with a new party in Correct Answer - 60 days
Once the application has been submitted a license app and paid the fees the
ROC must return, deny, or approve an app in_____ Correct Answer - 60
days
If a license app is determined to be incomplete, the ROC will notify the
applicant in___ Correct Answer - 20 days
20 days Correct Answer - Deadline for filing preliminary 20-day notice
(late notices are only effective for up to 20 days before filing). A.R.S. § 33-981
60 days Correct Answer - Deadline to file a lien after a "notice of
completion" is filed. A.R.S. § 33-993(A)
120 days Correct Answer - Deadline to file a lien after "completion," if a
notice of completion is not filed. A.R.S. § 33-993(A
6 months Correct Answer - Deadline for enforcing a lien (by filing a
lawsuit).
10 days Correct Answer - Deadline to dispute a lien after notice of
owner's intent to retain payment for the lien from payment to the contractor.
A.R.S. § 33-994
20 days Correct Answer - Deadline for releasing a lien that has been paid
in full or following written request, to avoid owing penalties and damages.
A.R.S. § 33-1006
A contractor license is required when the total cost, including materials is
more than Correct Answer - $1000
Which state agency has the authority to issue a contractor license Correct
Answer - ROC
What is the role of the ROC Correct Answer - ALL OF THE ABOVE
If you have a B- general license which of the items below must be
subcontracted ? Correct Answer - all of the above
-repairing an hvac
-installing a pool
-wiring a homes electrical circuit
, Which of the following commercial license classifications is permitted to
subcontract electical work Correct Answer - B-1 General Commercial
Contractor
A B- general residential contractor must subcontract what type of work
Correct Answer - electrical, boilers, and water wells
What business type is eligible for a contractor license Correct Answer -
llc, sole prop, and partnership
A new qualifying party must have at least two years of experience performing
or supervising the type of work covered by a license within the last Correct
Answer - 10 years
A military spouse who is relocating to arizona may waive the trade exam if
they have had a license in a comparable classification for: Correct Answer -
1 year
A person who has been convicted of contracting without a license is barred
from being part of a license application for: Correct Answer - 1 year
One person may act as the qualifying party for up to two licensees if he owns
at least _________ of each entity Correct Answer - 25%
If the qualifying party stops working for the licensee, the licensee and the
qualifying party must notify the ROC within _____ Correct Answer - 15
days
If a qualifying party dissasociates with the licensee, the licensee must
requalify with a new party in Correct Answer - 60 days
Once the application has been submitted a license app and paid the fees the
ROC must return, deny, or approve an app in_____ Correct Answer - 60
days
If a license app is determined to be incomplete, the ROC will notify the
applicant in___ Correct Answer - 20 days