This document is a complete and professionally curated collection of 48 exam questions with verified answers for the Design-Build Test #1 (2025/2026). It covers all fundamental and advanced topics in Design-Build project delivery and is tailored to help learners guarantee a 100% pass mark. The questions span true/false, multiple choice, and short answer formats, making it ideal for thorough exam preparation.
Key focus areas include:
Design-Build vs. Design-Bid-Build vs. CM-at-Risk vs. Multi-Prime
Federal laws like the Miller Act and Brooks Act
Types of contracts: Cost-Plus-Fee, Target Price, Guaranteed Maximum Price (GMP)
Key concepts: Lean Construction, Building Information Modeling (BIM), IPD, LEED
Roles of Owner, Architect, and Contractor in various delivery models
Advantages and disadvantages of each delivery and procurement strategy
The document also addresses:
The decision-making process for selecting delivery methods
Risk allocation, performance expectations, and contract responsibilities
Key metrics like cost control, speed of delivery, and owner flexibility
This resource is exceptionally valuable for:
Construction Management students
Architecture and Civil Engineering undergraduates
Built Environment and Infrastructure programs
Professionals preparing for DBIA certification exams
Courses in Project Delivery Systems, Contract Administration, Construction Law, and Integrated Project Delivery
The structure and content are based on the current 2025/2026 academic year and align with industry and educational standards. Whether you are aiming to pass a university-level exam or achieve certification, this guide offers essential insights into modern construction project delivery.
Keywords:
Design-Build, DBIA, Design-Bid-Build, CM-at-Risk, Multi-Prime, Procurement, Contract Models, Target Price, GMP, Lean Construction, BIM, IPD, LEED, Brooks Act, Miller Act, Spearin Doctrine, Construction Management, Risk Allocation, Delivery Systems
Content preview
Design-Build Test #1 2025/2026 Exam
Questions and Corresponding Answers
with Surety of 100% Pass Mark
T/F: The solicitation and basis for award for Design-Bid-Build is both quantitative
and qualitative. - 🧠ANSWER ✔✔False
T/F: Design-Bid-Build is typically Low Bid Based. - 🧠ANSWER ✔✔True
T/F: One of the factors for success of a Design-Build delivery system is to engage
the construction team before 20% of the design is completed by the owner. -
🧠ANSWER ✔✔True
T/F: Proposals with 35% or more of the design in the RFP will more than likely be
based on Low Bid (Price). - 🧠ANSWER ✔✔True
T/F: As long as Design-Builder meets performance requirements, the Design-
Builder has some flexibility to figure out the best approach. - 🧠ANSWER ✔✔True
, What existing Federal Law required any federal project exceeding $100,000 to
require two bonds (Performance Bond and Labor and Material Bond)? -
🧠ANSWER ✔✔Miller Act
What are the 3 fundamental decisions an Owner must make when initiating a
feasible project? - 🧠ANSWER ✔✔Type of delivery system, type of procurement
method, and type of contract format.
Design-Build means ________________. - 🧠ANSWER ✔✔One company/firm is
responsible for both design and construction, construction can begin before all the
designs are complete.
What is a primary reason for choosing a Design-Build delivery system? -
🧠ANSWER ✔✔If the project needs to be done fast, it places more risk on owner, if
the owner wishes to fast track project design and construction, if the project is
complex and requires close coordination of design and construction.
Owners who choose to use Design-Build as their project delivery method of choice
should expect all of the following outcomes except for:
a) cost guarantee during design
b) time savings