Exam latest update
m2-Which of the following is not a construction schedule milestone: a) submittal
approval b) Project Delivery and team selection process c) Procurement
(Bidding/negotiating/purchasing) Activities. d) Contract Completion - CORRECT
ANSWER-Project Delivery and team selection process
m6-If a date to proceed is not stipulated in the agreement, the owner should issue to the
contractor a: - CORRECT ANSWER-Notice to Proceed
m6-Pre-construction Activities Begin when the contractor has receivedL - CORRECT
ANSWER-A Letter of Intent to Award
m6-Which of the following is not a mobilization and Start up cost - CORRECT
ANSWER-Royalties, Licenses and Fees
m6-It is important to establish the site conditions prior to: - CORRECT ANSWER-
mobilization
m6-Mobilization typically occurs after: - CORRECT ANSWER-Receipt of a notice to
proceed and following a reconstruction meeting
m6-Which two types of bonds might be required during construction - CORRECT
ANSWER-Performance Bond and Bid Bond
m6-Inspections are done by the AHJ to determine if the construction complies with -
CORRECT ANSWER-Codes and Regulations
m6-The contractor Should being Preparation and Delivery for the Pre-construction
Submittals after which Event - CORRECT ANSWER-Execution of Agreement
m6-Payment and Performance bonds are which type of document - CORRECT
ANSWER-Pre-construction Submittal
m6-It is important for subcontract and purchase order documents to reference the -
CORRECT ANSWER-contract documents
, m6-Which two Parties are responsible for submittal of a set of construction documents
tot he AHJ for permit review - CORRECT ANSWER-Owner and Architect
m6-What is typically the contractor's first activity on the project site - CORRECT
ANSWER-
Mobilization
m7According to the AIA A201 The contractor has sole responsibility and control over
the following construction activities - CORRECT ANSWER-Means, methods,
techniques, sequences, procedures, coordination, job site safety
m7The responsibility of inspecting work already performed for proper conditions to
receive subsequent work lies with the - CORRECT ANSWER-Contractor
M7- The contractor's superintendent: - CORRECT ANSWER-Can not be changed
without the owners consent and communication is as binding as if given by the
contractor
m7- True or False - by executing the contract the contractor confirms that the contract
time is reasonable - CORRECT ANSWER-True
m7- The date of substantial completion is established by the - CORRECT ANSWER-
A/E
`m7- Under A201 who has the responsibility to pay sales, consumer, use and similar
taxes for the work provided? - CORRECT ANSWER-contractor
m-7If the contractor is delayed in the progress of the work by the owner the contractor
should: - CORRECT ANSWER-Write the A/E requesting a change order granting an
extension of time.
m7- Product equivalency, manufacturer, installation, operating cost, maintenance costs,
and warranty are major factors to be considered for: - CORRECT ANSWER-
Substitution Request
m7- All of the following my be accomplished through issuing change order except which
one? a) Change in bid date. b)Decrease in contract cost. c)Extension of Contract time.
d) Reduction in Scope of work. - CORRECT ANSWER-a Change in bid date.
m7 - All of the following are defined as a contract modification except which one?
a)change order b) Construction change Directive/work change directive c)Architect's
supplemental instructions/field order d) Addendum - CORRECT ANSWER-addendum