CDT Practice Delivery Study Guide Exam latest update CDT Practice Delivery Study Guide Exam latest update CDT Practice Delivery Study Guide Exam latest update CDT Practice Delivery Study Guide Exam latest update CDT Practice Delivery Study Guide Exam latest update CDT Practice Delivery Study Guide Exam latest update CDT Practice Delivery Study Guide Exam latest update

Content preview

CDT Practice Delivery Study Guide
Exam latest update

m2-Which of the following is not a construction schedule milestone: a) submittal
approval b) Project Delivery and team selection process c) Procurement
(Bidding/negotiating/purchasing) Activities. d) Contract Completion - CORRECT
ANSWER-Project Delivery and team selection process

m6-If a date to proceed is not stipulated in the agreement, the owner should issue to the
contractor a: - CORRECT ANSWER-Notice to Proceed

m6-Pre-construction Activities Begin when the contractor has receivedL - CORRECT
ANSWER-A Letter of Intent to Award

m6-Which of the following is not a mobilization and Start up cost - CORRECT
ANSWER-Royalties, Licenses and Fees

m6-It is important to establish the site conditions prior to: - CORRECT ANSWER-
mobilization

m6-Mobilization typically occurs after: - CORRECT ANSWER-Receipt of a notice to
proceed and following a reconstruction meeting

m6-Which two types of bonds might be required during construction - CORRECT
ANSWER-Performance Bond and Bid Bond

m6-Inspections are done by the AHJ to determine if the construction complies with -
CORRECT ANSWER-Codes and Regulations

m6-The contractor Should being Preparation and Delivery for the Pre-construction
Submittals after which Event - CORRECT ANSWER-Execution of Agreement

m6-Payment and Performance bonds are which type of document - CORRECT
ANSWER-Pre-construction Submittal

m6-It is important for subcontract and purchase order documents to reference the -
CORRECT ANSWER-contract documents

, m6-Which two Parties are responsible for submittal of a set of construction documents
tot he AHJ for permit review - CORRECT ANSWER-Owner and Architect

m6-What is typically the contractor's first activity on the project site - CORRECT
ANSWER-
Mobilization

m7According to the AIA A201 The contractor has sole responsibility and control over
the following construction activities - CORRECT ANSWER-Means, methods,
techniques, sequences, procedures, coordination, job site safety

m7The responsibility of inspecting work already performed for proper conditions to
receive subsequent work lies with the - CORRECT ANSWER-Contractor

M7- The contractor's superintendent: - CORRECT ANSWER-Can not be changed
without the owners consent and communication is as binding as if given by the
contractor

m7- True or False - by executing the contract the contractor confirms that the contract
time is reasonable - CORRECT ANSWER-True

m7- The date of substantial completion is established by the - CORRECT ANSWER-
A/E

`m7- Under A201 who has the responsibility to pay sales, consumer, use and similar
taxes for the work provided? - CORRECT ANSWER-contractor

m-7If the contractor is delayed in the progress of the work by the owner the contractor
should: - CORRECT ANSWER-Write the A/E requesting a change order granting an
extension of time.

m7- Product equivalency, manufacturer, installation, operating cost, maintenance costs,
and warranty are major factors to be considered for: - CORRECT ANSWER-
Substitution Request

m7- All of the following my be accomplished through issuing change order except which
one? a) Change in bid date. b)Decrease in contract cost. c)Extension of Contract time.
d) Reduction in Scope of work. - CORRECT ANSWER-a Change in bid date.

m7 - All of the following are defined as a contract modification except which one?
a)change order b) Construction change Directive/work change directive c)Architect's
supplemental instructions/field order d) Addendum - CORRECT ANSWER-addendum

Document information

Uploaded on
July 29, 2025
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Edunursepro
4.0
(45)
Sold
179
Followers
10
Items
10385
Last sold
2 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions