• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 3 out of 19 pages
Exam (elaborations)

Cmit 2025 Exam With All Correct & 100% Verified Answers|Already Graded A+|Just Released!!!

Document preview thumbnail
Preview 3 out of 19 pages

CMIT 2025 EXAM WITH ALL CORRECT & 100% VERIFIED ANSWERS|ALREADY GRADED A+|JUST RELEASED!!!

Content preview

CMIT 2025 EXAM WITH ALL CORRECT & 100%
VERIFIED ANSWERS|ALREADY GRADED A+|JUST
RELEASED!!!
A CM's role and responsibilities are governed solely by the Owner/CM Agreement.
True False Correct answer-True

There are two basic forms of CM, agency and at-risk. Each form provides for the basic services of
construction management practice. However, there are some key differences. Which of the following
do not apply to both CM forms?
A) Both forms provide advice to the owner on constructibility, budget and the schedule.
B) Both require that the liabilities and risks assumed by the parties be clearly understood,
coordinated, and stated in the respective contracts.
C) Both forms allow the CM to function in an advisory role for the entire engagement of the CM.
D) Services can vary based on the contractual relationships of the parties and the risks that are
assumed. Correct answer-C) Both forms allow the CM to function in an advisory role for the entire
engagement of the CM.

Construction management had its beginnings in the early to mid-1960's. Which of the following
factors contributed to the initial use of this delivery system?
A) The need to reduce the overall time and cost associated with project delivery.
B) The increasing cost of money and the unpredictability of project funding streams.
C) The changing role of the general contractor and the increasing numbers of specialty trade
contractors.
D) All of the above. Correct answer-D) All of the above.

The General Services Administration was the first federal agency to use construction management.
Correct answer-True

The General Services Administration, the Department of Health, Education and Welfare (now HHS),
and the Veterans Administration ran into similar difficulties in the use of construction management.
Which of the following was/were common problems for all three agencies?
A) Funding restrictions
B) Claims
C) Change conditions
D) All of the above Correct answer-D) All of the above

CMAA was formed and incorporated 1982 with its primary focus being the growth and development
of the construction management profession. Correct answer-True

The CMAA Construction Management Standards of Practice is intended as a guide to the range of
services that constitute professional construction management. They seek to meet the documented
need for definitions of what construction management services are, without unduly structuring the
methodologies by which those services are provided by the CM. Correct answer-True

The goals of the Construction Management Association of America (CMAA) include:
A) Setting standards and developing contract documents for construction management practice.
B) Expanding the understanding of the construction management concept and its use in the
marketplace.

,C) Advocacy for construction management in the legislative, regulatory, and judicial arenas of
federal, state, and local governments.
D) All of the above. Correct answer-D) All of the above

The fact that an individual is certified or licensed in any other profession does not, per se, establish
him/her as a qualified CM.
True False Correct answer-True

Certification as a CM means the construction management practitioner has "state of the art"
knowledge and capability to practice construction management.
True False Correct answer-False

Recruiting and training are business matters and normally do not involve ethical concerns.
True False Correct answer-False

Construction management is a concept that is susceptible to overselling.
True False Correct answer-True

Failure to provide quality services is a business and not an ethical question.
True False Correct answer-False

Contracting for adequate fees is both a business and an ethical issue.
True False Correct answer-True

The ethics of the CM profession focus primarily on a CM's relationships in dealing with its clients.
True False Correct answer-True

The possible approaches for delivering a project are virtually unlimited. A key reason for such
variations is:
A) The different roles that can be assumed by project participants.
B) Different forms of contracts and methods of compensation that can be used.
C) The different levels of care, responsibility, and risks assumed by the parties involved.
D) All of the above. Correct answer-D) All of the above

The traditional delivery system is characterized by executing the major phases of a project in:
A) An overlapping concept
B) A linear sequence
C) A fast track method
D) All of the above Correct answer-B) A linear sequence

A key advantage of the traditional delivery approach is:
A) With the traditional delivery system, the cost of the construction phase is known before
construction starts.
B) Facility features are fully determined & specified.
C) When the construction contract is signed, the major risk belongs to the contractor.
D) All of the above Correct answer-B) Facility features are fully determined & specified.

Design-build and at-risk construction management delivery systems allow the option to fast-track or
phase a project.
True False Correct answer-True

, Most definitions of construction management are similar. However, a contractual definition is not
known until:
A) The legal form of the CM contract is chosen.
B) The specific scope of services to be provided is identified.
C) The relationship of the CM to others and the risks and authority assumed by the parties are clearly
defined.
D) All of the above Correct answer-D) All of the above

21.
In a CM-at-Risk arrangement once construction begins and the CM converts from the professional
advisory role of a CM to the contractual role of a general contractor, the CM has no implied duties of
loyalty and care to the owner.
True False Correct answer-True

The agency CM does not perform design or actual construction work.
True False Correct answer-True

Under the CM-at-Risk delivery method, the owner usually must deal with the hybrid of a
construction manager and a general contractor.
True False Correct answer-True

Under a CM-at-risk contract, which of the following statements are true?
A) The CM, in most cases, holds the trade and/or specialty contracts.
B) The CM has the right to enforce the schedule, pay the trade or subcontractors, and terminate
them if such action becomes necessary.
C) On some CM-at-Risk contracts, the CM has the option of performing portions of the work with its
own resources (unless prohibited by law on certain public projects).
D) All of the above Correct answer-D) All of the above

In considering the differences between agency CM and CM-at-Risk, which one of the following
statements is NOT true?
A) With the CM-at-Risk, the CM is responsible for means, methods, and sequencing of work.
B) In an agency CM role, the CM does none of the physical work.
C) The CM, in most cases, is clearly responsible for schedule and coordination.
D) In an agency CM role, the CM directly subcontracts all trade contracts. Correct answer-D) In an
agency CM role, the CM directly subcontracts all trade contracts.

The agency CM maintains a direct contractual relationship with the trade or prime contractors.
True False Correct answer-False

Placing the CM in an agency role always transfers the risk to the contractor.
True False Correct answer-True

In an agency CM relationship, the CM has no vested financial interest in the project.
True False Correct answer-True

Under agency CM, agency is a relationship between owner and CM as agent acting in the owner's
interest.
True False Correct answer-True

Actual usage of a particular contract form for the construction phase depends on:

Document information

Uploaded on
July 28, 2025
Number of pages
19
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$21.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Studyclub
3.6
(14)
Sold
70
Followers
1
Items
13607
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions