PJM Practice Exam UPDATED ACTUAL Exam Questions and CORRECT Answers Real time transmission constraints or contingencies may be alleviated with generators operating________. A. below 60 Hz. B. on a new price curve. C. on a new cost curve. D. off cost (out of merit). - CORRECT ANSWER -off cost (out of merit) What is the minimum size for a solar park to be required to have real and reactive power telemetry? A. 1 MW. B. 3 MW C. 5 MW D. 7 MW - CORRECT ANSWER -3 MW

Show more Read less
Institution
PJM Generation
Course
PJM Generation









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PJM Generation
Course
PJM Generation

Document information

Uploaded on
July 26, 2025
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PJM Practice Exam UPDATED ACTUAL
Exam Questions and CORRECT Answers
Real time transmission constraints or contingencies may be alleviated with generators
operating________. A. below 60 Hz. B. on a new price curve. C. on a new cost curve. D. off cost
(out of merit). - CORRECT ANSWER -off cost (out of merit)


What is the minimum size for a solar park to be required to have real and reactive power

telemetry? A. 1 MW. B. 3 MW C. 5 MW D. 7 MW - CORRECT ANSWER -3 MW


PJM calls for which of the following to recover the ACE so that tie line schedules are
maintained? A. instantaneous reserve check B. synchronized reserves C. supplemental status
report D. minimum generation calculation - CORRECT ANSWER -synchronized reserves


If not cancelled by PJM, the minimum generation alert expires A. at the end of the specified light
load period. B. when notified by NERC. C. 12 hours after the alert was issued. D. after a 24hour
period. - CORRECT ANSWER -at the end of the specified light load period.


When PJM declares a hot weather alert, the generation dispatcher should A. determine if
maintenance can be deferred. B. notify transmission operators. C. direct all generating stations to
increase MW output D. direct all generating stations to reduce MVAR output - CORRECT
ANSWER -determine if maintenance can be deferred.


During system restoration, the two categories of reserves are A. dynamic and secondary. B.
spinning and quick start. C. dynamic and spinning. D. spinning and primary - CORRECT
ANSWER -dynamic and spinning


During system restoration, frequency should be maintained between A. 59.50 and 60.00 Hz. B.
59.75 and 61.50 Hz. C. 59.75 and 61.00 Hz. D. 59.50 and 60.50 Hz. - CORRECT
ANSWER -59.75 and 61.00 Hz


PJM issues a heavy load voltage schedule. Member companies who own generation facilities

, should A. remove 230 kV capacitors from service. B. ensure voltage regulators on generating
units are in service on automatic. C. inform transmission providers to have marketers in their
areas cut transactions. D. instruct generating stations to curtail nonessential building loads -
CORRECT ANSWER -ensure voltage regulators on generating units are in service on
automatic


A unit being dispatched economically by PJM should set its MW output based on the A. LMP at
generator bus. B. LMP in the unit's zone. C. Unit's dispatch rate or desired MW level. D.
generation owner's discretion. - CORRECT ANSWER -Unit's dispatch rate or desired MW
level


What hourly revenue data is required of a generator by PJM? A. Compensated MWh delivered
by each unit B. Integrated LMP data per generator node C. Availability by generator schedule D.
Estimated compensation dollars by generator - CORRECT ANSWER -Compensated
MWh delivered by each unit


During system restoration prior to synchronization of a unit, the dispatcher should ensure
sufficient
load is available to A. economize unit operation. B. maximize unit operation. C. stabilize unit
operation. D. minimize unit operation. - CORRECT ANSWER -stabilize unit operation


A non-zero ACE indicates A. over-excitation. B. an imbalance of generation and load C. a
capacity shortage situation D. low temperatures in a localized zone - CORRECT
ANSWER -an imbalance of generation and load


During certain emergency conditions, a Capacity Performance generation resource that fails to
generate the required amount of energy may be charged: A. a peak period maintenance penalty
B. a non-performance assessment charge C. an additional credit requirement D. the synchronized
reserve market clearing price for the past 19 days - CORRECT ANSWER -a non-
performance assessment charge


Control center facilities must have a minimum of how many days of fuel for the backup
generator? . A. 3 B. 5 C. 7 D. 9 - CORRECT ANSWER -5

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1053
Member since
1 year
Number of followers
100
Documents
68976
Last sold
1 hour ago
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

166 reviews

5
72
4
30
3
42
2
8
1
14

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions