CM 413 JOBSITE FINAL EXAM | 100
QUESTIONS | WITH ACCURATE
SOLUTIONS 2025!!
1 of 100
Term
What was the name of the entrepreneur that said this phrase on the
pacific courtyard: "When a large publicly traded one-builder could no
longer sustain itself on the central coast, we will start our own
gig".
Give this one a try later!
Grant Robbins Eric Bet
, Design Builder: Webcor Builders Tayler Simpson
Don't know?
2 of 100
Term
Temp Structures RATAY
The responsibility for inspection of temporary structures rests with
which entity(s)?
A) subcontractor
B) General Contractor
C) Projects Inspector
D) A & B
E) All the above
Give this one a try later!
B. Mediation E. All of the above
E) All of the above D. All of the Above
, Don't know?
3 of 100
Term
Temp Structures: Tech & Bus
In an extremely complex job involving temporary work such as
a cofferdam for bridge piers,___will design the temporary
structures for that project. On a less complex job, such as one that
requires a temporary ramp that might be used by an
excavation tractor moving in an out of a building's
foundation;________________________________________is
responsible for the design.
a.The Engineer of Record; the Project Superintendent.
b.The designer of the permanent project ; the General Contractor.
c. A 3rd party specialty contractor ; the responsible trade contractor.
d.The designer of the permanent project ; the responsible trade
contractor.
Give this one a try later!
e.a and c only e. Both b & c
, d. The designer of the
D- All of the
above permanent project ; the
responsible trade contractor.
Don't know?
4 of 100
Term
Icon Student Housing
What type of temporary structure is required at the entrance of
every jobsite?
Give this one a try later!
Concrete barriers are optional at No structures are needed at job-
job-sites in CA sites in CA
Shaker Plates are Safety Nets are required at
mandatory on all job-sites every job-site in CA
in CA
Don't know?
QUESTIONS | WITH ACCURATE
SOLUTIONS 2025!!
1 of 100
Term
What was the name of the entrepreneur that said this phrase on the
pacific courtyard: "When a large publicly traded one-builder could no
longer sustain itself on the central coast, we will start our own
gig".
Give this one a try later!
Grant Robbins Eric Bet
, Design Builder: Webcor Builders Tayler Simpson
Don't know?
2 of 100
Term
Temp Structures RATAY
The responsibility for inspection of temporary structures rests with
which entity(s)?
A) subcontractor
B) General Contractor
C) Projects Inspector
D) A & B
E) All the above
Give this one a try later!
B. Mediation E. All of the above
E) All of the above D. All of the Above
, Don't know?
3 of 100
Term
Temp Structures: Tech & Bus
In an extremely complex job involving temporary work such as
a cofferdam for bridge piers,___will design the temporary
structures for that project. On a less complex job, such as one that
requires a temporary ramp that might be used by an
excavation tractor moving in an out of a building's
foundation;________________________________________is
responsible for the design.
a.The Engineer of Record; the Project Superintendent.
b.The designer of the permanent project ; the General Contractor.
c. A 3rd party specialty contractor ; the responsible trade contractor.
d.The designer of the permanent project ; the responsible trade
contractor.
Give this one a try later!
e.a and c only e. Both b & c
, d. The designer of the
D- All of the
above permanent project ; the
responsible trade contractor.
Don't know?
4 of 100
Term
Icon Student Housing
What type of temporary structure is required at the entrance of
every jobsite?
Give this one a try later!
Concrete barriers are optional at No structures are needed at job-
job-sites in CA sites in CA
Shaker Plates are Safety Nets are required at
mandatory on all job-sites every job-site in CA
in CA
Don't know?