A supply manager issues a request to proposal for engineering services. In order to provide
clarification on the specification on the specifications, the company holds a question-and-
answer session for interested suppliers. Shortly after the question-and-answer session is held
and before any proposals are actually received, the firm's engineering department revises the
specifications. Given this situation, which of the following should the supply manager do FIRST?
(A) Call and email the suppliers of the change, tell them when the new specifications will be
available, and ask for immediate notification if additional time will be required.
(B) Write a letter to each supplier advising of the change, tell each supplier when the new
specifications will be available, and ask for immediate notification if additional time will be
required.
(C) Hold an interim pre-bid meeting withal suppliers to discuss and clarify the revi - ANS (A)
Call and email the suppliers of the change, tell them when the new specifications will be
available, and ask for immediate notification if additional time will be required.
Copyright ©2025 BRIGHTSTARS ALL RIGHTS RESERVED 1
,Which of the following should have the MOST influence in determining end product
specifications, so as to minimize the potential for returns?
(A) Marketing
(B) Supply management
(C) Engineering
(D) Manufacturing - ANS (A) Marketing
When developing specifications, a buyer may consider information from which of the
following?
I. Suppliers
II. Industry Standards
III. Professional Organizations
IV. Competitors
(A) I and IV only
(B) II and III only
Copyright ©2025 BRIGHTSTARS ALL RIGHTS RESERVED 2
,(C) I, II and III only
(D) I, II, III and IV - ANS (D) I, II, III and IV
A supply manager completes a category profile and identifies services provided through
multiple suppliers. A market and industry analysis shows that the service provides are growing
their businesses by acquiring competitors, thus enabling them to provide a greater range of
services. Which of the following techniques will BEST enable the supply manager to leverage
market competition?
(A) Lotting strategy
(B) Market-basket model
(C) Market segmentation
(D) Sole sourcing - ANS (A) Lotting strategy
A supply manager implements a system whereby the potential supplier names are hidden until
final contract awards are made. This example is BEST described as ensuring
(A) confidential information is protected
Copyright ©2025 BRIGHTSTARS ALL RIGHTS RESERVED 3
, (B) diversity initiatives are met
(C) total costs are minimized
(D) collusion will not occur - ANS (A) confidential information is protected
A supply manager for a privately held manufacturing company is preparing an RFP for raw
materials. None of
the RFP recipients is an incumbent, and the award resulting from the RFP is expected to be of
significant dollar value. The supply manager is concerned that the lack of publicly available
financial information could impact willingness of the prospective suppliers to submit proposals.
Which of the following will BEST address the concerns of the prospective bidders?
(A) Escrow account
(B) Letter of credit
(C) Payment bond
(D) Surety bond - ANS (B) Letter of credit
Which of the following is the LEAST critical element in a best alternative to a negotiated
agreement (BATNA)?