How would you know a technical order (TO) number is in the utility aircraft TO category?
The first group of numbers will contain the letter U.
Group two of an aircraft technical order (TO) number identifies the: Aircraft series and
model.
The "2" in group 3 of technical order (TO) number 1U-2S-2-10 designates that the TO is a:
Maintenance instruction.
When the technical order (TO) number has only three parts, group three identifies the:
Individual TO
The fourth group of a technical order (TO) number contains one or two parts identifying a:
TO's particular system and purpose.
If a page is found missing from a TO, it: Is not valid and must be removed from service.
How would you repair pages that have been ripped out of a TO binder? Use paper
reinforcements.
You can use cellophane tape to mend a torn TO page as long as: the tape does not obscure
any technical data.
When a TO change takes place, the changed (new) TO page: replaces the corresponding
page number in the existing publication.
Changes in the text of a TO are indicated by: A heavy black vertical line in the outer margin
of the page.
, Supplements are issued to augment or change data in the basic TO: without replacing the
existing page.
Routine TO supplements are filed: In the back of the affected publication.
Interim safety supplements are transmitted: Electronically.
How can you tell if a supplement is filed in a TO? By a supplement number, entered in
pencil, next to a circled TO paragraph number.
An inventory of each TO page is also known as: List of effective pages check
The two types of recommended TO changes are: Correction and improvement.
What would the priority recommendation be if a TO deficiency WOULD result in a fatal or
serious injury to personnel? Emergency
What would the priority recommendation be if a TCTO were deficient? Urgent
Responsibility for initiating follow-up action on a TO change recommendation with a delayed
reply rests with: The local product improvement manager (PIM).
Which action WILL NEVER be done after removing a LRU? Use of electrical tape to cover
open connectors when high humidity is a problem.
What should be used on open hydraulic lines? Metal caps only.