Questions and CORRECT Answers
You work as a tester in a software house and you concurrently work on two projects. One of
them is an internal tool for on-line room reservation, done within an agile life cycle. The other
one is a commercial software for managing hospital patients' data, conducted in the waterfall
model. In one-month, new versions of both systems will be released. You don't have time to
perform all the planned tests for both systems. You decide to focus on testing the commercial
system.
A. This is a bad decision, because testing commercial project will be much more expensive than
testing the internal one
B. This is a good decision, because the commercial software is much more important for the
company than the internal system
C. This is a bad decision, because critical defects can occur in both systems, and one of them will
not be tested
D. This is a good decision, because the waterfall model requires testing during the end of the -
CORRECT ANSWER - C. This is a bad decision, because critical defects can occur in
both systems, and one of them will not be tested
fb chọn b
Which of the following requirements is testable?
A. There should be no faults in the safety-critical components of the system.
B. The platform must be designed with portability as a key feature
C. The system is required to be easy for users to navigate and use.
D. The required response time for the designated design load should not exceed one second. -
CORRECT ANSWER - D. The required response time for the designated design load
should not exceed one second.
Test planning has which of the following major tasks?
i. Determining the scope and risks, and identifying the objectives of testing.
, ii. Determining the test approach (techniques, test items, coverage, identifying and interfacing
the teams involved in testing, testware)
iii. Reviewing the Test Basis (such as requirements, architecture, design, interface)
iv. Determining the exit criteria.
i, ii, iv are true and iii is false
i, ili, iv are true and ii is false
i, ii are true and iii, iv are false
i, ii, iv are true and i is false - CORRECT ANSWER - i, ii, iv are true and iii is false
The inputs for developing a test plan are taken from
A. Support plan
B. Business plan
C. Project plan
D. None of the above - CORRECT ANSWER - C. Project plan
A social media platform is planning to roll out a new feature that allows users to upload and
share videos. The development team has implemented the video upload functionality, and the
product manager is concerned about the potential impact on the existing image upload
functionality. They want to ensure that the introduction of video uploads does not negatively
affect the core functionality of image uploads. Which test should be performed in this situation?
A. Re-test
B. Performance test
C. Functional test
D. Regression test - CORRECT ANSWER - D. Regression test
Which of the following BEST distinguishes the terms "validation" and "verification"
A. Verification is confirmation through the provision of subjective evidence that the specified
requirements have been met while validation confirmation through the provision of subjective
evidence that the designs for a specific intended use have been met