Q. 301: Cost of the reviews will not include.
A. Review process itself
B. Metrics analysis
C. Tool support.
D. Process improvement. - CORRECT ANSWER -C
Q. 302: Regression testing always
involves
A. Testing whether a known software fault been fixed.
B. Executing a large number of different tests.
C. Testing whether modifications have introduced adverse side effects.
D. Using a test automation tool. - CORRECT ANSWER -C
Q. 303: Capture and replay facilities are least likely to be used to _______
A. Performance testing
B. Recovery testing
C. GUI testing
D. User requirements. - CORRECT ANSWER -D
Q. 304: Which tool will be used to test the flag memory leaks and unassigned pointers
A. Dynamic analysis tool
,B. Static Analysis tool.
C. Maintenance tool.
D. Configuration tool. - CORRECT ANSWER -A
Q. 305: Cyclomatic complexity is used to calculate
A. Number of independent paths in the basis set of a program
B. Number of binary decisions + 1
C. Number bound for the number of tests that must be conducted to ensure that all statements
have been executed at least once
D. Number of branches and decisions - CORRECT ANSWER -B
Q. 306: Which of the following is not included in Test Plan.
A. Features to be tested.
B. Environmental needs.
C. Suspension criteria.
D. Expected results. - CORRECT ANSWER -D
Q. 307: Software quality is not relevant to _______
A. Correctness
B. Usability
C. Viability
D. Reusability. - CORRECT ANSWER -C
Q. 308: Match the following:
,1. Test estimation
2. Test control
3. Test monitoring
a. Measures of tracking process
b. Effort required to perform activities
c. Reallocation of resources
A. 1-b, 2-c, 3-a
B. 1-b, 2-a, 3-c
C. 1-c, 2-a, 3-b
D. 1-a, 2-b, 3-c - CORRECT ANSWER -A
Q. 309: When do you stop testing?
A. When the specified number of faults are found.
B. When the test completion criteria are met.
C. When all high and medium priority tests are complete.
D. When all statements have been executed - CORRECT ANSWER -B
Q. 310: What is the smallest number of test cases required to Provide 100% branch coverage?
If(x>y) x=x+1;
else y=y+1;
while(x>y)
{
y=x*y; x=x+1;
}
, A. 1
B. 2
C. 3
D. 4 - CORRECT ANSWER -B
Q. 311: Match the following.
1. Configuration identification
2. Configuration control
3. Status reporting
4. Configuration auditing
a. Maintains of CI�s in a library
b. Checks on the contents of the library
c. Function recording and tracking problems.
d. Requires the all CI�s and their versions in the system are known
A.
1-d, 2-c, 3-d, 4-a.
B. 1-d, 2-a, 3-c, 4-b.
C. 1-a, 2-b, 3-d, 4-c.
D. 1-c, 2-b, 3-a, 4-d. - CORRECT ANSWER -B
Q. 312: Integration testing in the large involves:
A. Testing the system when combined with other systems.