Exam (elaborations)

ACI Flatwork All Possible Questions and Answers with complete solution

Document preview thumbnail
Preview 2 out of 7 pages

It is important that the finisher foreman read and understand project specifications. If the crew can place and finish 100 yd³ of concrete per hour, the producer's delivery rate should be about 100 yd³ per hour. Concrete is sold by the ton? — False Delays in discharging concrete trucks can result in the concrete being hard to: pump, place, and finish When there is room for two concrete trucks ready to discharge into a pump hopper, placement is faster because: as one truck is finishing, the other is ready to unload the concrete Concrete from a ready mix truck must usually be completely discharged within 1.5 hours after water has been added at the plant. You can tell when water has been added to the concrete truck by looking at the: batch ticket When concrete for a slab placement will be discharged from the truck chute, truck arrivals should usually be spaced at about: 15 minutes When finishers get behind because the concrete is setting faster than expected and the placing crew is also shorthanded, one solution is slowing the concrete delivery rate to match worker output. — True In deciding how much concrete to order for a floor placement, you should calculate the number of cubic yards needed to fill the forms, then order two to three cubic yards less so you don't waste concrete that is not needed. — False

Content preview

ACI Flatwork

It is important that the finisher foreman read and understand project specifications.

If the crew can place and finish 100 yd³ of concrete per hour, the producer's delivery rate should
be about 100 yd³ per hour.

Concrete is sold by the ton? — False

Delays in discharging concrete trucks can result in the concrete being hard to: pump, place, and
finish

When there is room for two concrete trucks ready to discharge into a pump hopper, placement is
faster because: as one truck is finishing, the other is ready to unload the concrete

Concrete from a ready mix truck must usually be completely discharged within 1.5 hours after
water has been added at the plant.

You can tell when water has been added to the concrete truck by looking at the: batch ticket

When concrete for a slab placement will be discharged from the truck chute, truck arrivals
should usually be spaced at about: 15 minutes

When finishers get behind because the concrete is setting faster than expected and the placing
crew is also shorthanded, one solution is slowing the concrete delivery rate to match worker
output. — True

In deciding how much concrete to order for a floor placement, you should calculate the number
of cubic yards needed to fill the forms, then order two to three cubic yards less so you don't
waste concrete that is not needed. — False

The question, "What finisher or finishers can request addition of water to the concrete truck on
site?" should be answered at the Pre-construction meeting.

Concrete made with portland cement will set and harden while under water. — True

If a concrete slab on ground won't be exposed to sulfates, the cement used is most likely to be:
Type I

, Most concrete used in slabs on ground has coarse aggregate with a maximum size of: 3/4 to 1 1/2
in.

Sand for concrete used in slabs on ground is easier to finish when it has close to the largest
allowable amount of material passing the No. 50 and No. 100 sieve. — True

Increasing the amount of sand in a concrete usually decreases the amount of water needed to
make the concrete workable. — False

All concrete that will be subject to freezing when moist or be exposed the deicing salts should
contain: an air-entraining agent

Strength of normal weight concrete depends mainly on: water-cement ratio

Overhanded concrete mixtures are likely to produce floors with poor wear resistance and
excessive shrinkage. — True

To minimize shrinkage and reduce cracking and curling: use as much coarse aggregate as
possible, use as little mixing water as possible, and use aggregates with low shrinkage

Changes in concrete slump most often represent changes in the amount of water in the mixture.

Air-entrained concrete is not recommended for use in concrete slabs: finished by repeated steel
troweling passes

Changes in concrete temperatures affect: setting time, air content, and slump

To determine if concrete, in place, has the strength needed to put it into service, test cylinders
should be: kept at the job site and cured under conditions similar to the curing conditions
for the concrete they represent

Granular sub bases for slabs on ground can be compacted with sheepsfoot rollers. — False

In cold weather, the sub grade soil must be free of frost before concrete placing begins.

Before a concrete slab on ground is placed under severe drying conditions that threaten plastic
shrinkage cracking, water should be sprayed on the sub grade until puddles are formed and the
surface is soft. — False

Before concreting, workers should check the elevation of the subbase by: measuring down from
a straightedge spanning between the side forms

If the surface of the subbase for a concrete slab on ground is too low, the slab is likely to be too
thin. — False

Document information

Uploaded on
June 10, 2025
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ACADEMICMATERIALS
4.0
(101)
Sold
630
Followers
185
Items
10503
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions