NCCCO PREP
1. To provide protection in the cranes work area, barri- Within the equipment's ro-
ers MUST be erected in accessible areas; tating structure
2. All of the following can cause a two-block condition Raising the boom
except:
3. When rotation of load may be hazardous, the oper- Ensure tag line is used
ator must
4. According to OSHA 1926 Subpart cc, which of the Qualified evaluator
following individuals is not allowed within the fall
zone?
5. The term that is used to define the load plus all Gross load
rigging components, hooks, blocks and lifting equip-
ment is:
6. According to OSHA 1926 Subpart CC, the minimum 10ft
distance that must be maintained between a work-
ing crane, load or load line and an 8kV power line is:
7. What is the sum of the following deductions? Block 1623lbs
1250lbs, Rigging 23lbs, Spreader beam 350lbs
8. When a crane is set up to close to a new building, Soft
expect the ground to be:
9. A vertical basket hitch is rated at what percentage of 200%
a vertical hitch?
10. When is the hoist line on top of the boom considered It is not considered
part of the load?
11. When a heavy load is lifted, what is the result? Boom deflection
, NCCCO PREP
12. According to OSHA 1926 Subpart CC, for cranes trav- 6ft
eling with no load, what is the minimum clearance
for energized power lines at 40kV?
13. Wich of the following rigging configurations is listed Basket, Vertical, Choker
in order of the strongest to weakest?
14. According to OSHA 1926 Subpart CC, how many ran- 2 broken wires in 6 rope di-
domly distributed broken wires in rotation resistant ameters
wire rope are cause for replacement?
15. What site conditions must an operator be concerned Soil stability must be suffi-
about prior to setting up a crane? cient
16. The best way to determine the weight of load to be Have certified load weight
lifted is to: and add in the weight of all
the rigging
17. What source should be used to determine boom tip Working range diagram
height?
18. In order for an overhead power line to be considered Line owner
de-energized it must be verified by the:
19. The purpose of the load moment indicator is to: Warn the operator of an
overload condition
20. On what principle is crane stability based? Leverage
21. According to OSHA 1926 Subpart CC, prior to hoist- 125%
ing employees at each job site, the personnel plat-
form rigging must be proof tested to what percent-
age of the platforms rated capacity?
1. To provide protection in the cranes work area, barri- Within the equipment's ro-
ers MUST be erected in accessible areas; tating structure
2. All of the following can cause a two-block condition Raising the boom
except:
3. When rotation of load may be hazardous, the oper- Ensure tag line is used
ator must
4. According to OSHA 1926 Subpart cc, which of the Qualified evaluator
following individuals is not allowed within the fall
zone?
5. The term that is used to define the load plus all Gross load
rigging components, hooks, blocks and lifting equip-
ment is:
6. According to OSHA 1926 Subpart CC, the minimum 10ft
distance that must be maintained between a work-
ing crane, load or load line and an 8kV power line is:
7. What is the sum of the following deductions? Block 1623lbs
1250lbs, Rigging 23lbs, Spreader beam 350lbs
8. When a crane is set up to close to a new building, Soft
expect the ground to be:
9. A vertical basket hitch is rated at what percentage of 200%
a vertical hitch?
10. When is the hoist line on top of the boom considered It is not considered
part of the load?
11. When a heavy load is lifted, what is the result? Boom deflection
, NCCCO PREP
12. According to OSHA 1926 Subpart CC, for cranes trav- 6ft
eling with no load, what is the minimum clearance
for energized power lines at 40kV?
13. Wich of the following rigging configurations is listed Basket, Vertical, Choker
in order of the strongest to weakest?
14. According to OSHA 1926 Subpart CC, how many ran- 2 broken wires in 6 rope di-
domly distributed broken wires in rotation resistant ameters
wire rope are cause for replacement?
15. What site conditions must an operator be concerned Soil stability must be suffi-
about prior to setting up a crane? cient
16. The best way to determine the weight of load to be Have certified load weight
lifted is to: and add in the weight of all
the rigging
17. What source should be used to determine boom tip Working range diagram
height?
18. In order for an overhead power line to be considered Line owner
de-energized it must be verified by the:
19. The purpose of the load moment indicator is to: Warn the operator of an
overload condition
20. On what principle is crane stability based? Leverage
21. According to OSHA 1926 Subpart CC, prior to hoist- 125%
ing employees at each job site, the personnel plat-
form rigging must be proof tested to what percent-
age of the platforms rated capacity?